NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999)
TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting.
Do not include proprietary materials.
DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 05/21/2003 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding-this meeting:
Docket Number(s)
SIN4* SIN50457, SIN50454, SIN50-455, 50461,50-237, 50-24-I 56-Y3'3,._3Or,2.5S,53,s
,a7ThZ51%z4,z4 Plant/Facility Name 1raiod 1t, ymn 1/2. Cintn, hDsden 2/3, 1Sa&le 112, Linrnck l/z.
TAC Number(s) (if available)
-r V'A' -
Reference Meeting Notice April 9, 2003 Purpose of Meeting (copy from meeting notice)
Tods siissusruxlig listivte forthe Exlou peeik V, {8w n\\j o v 4G p,
sq V-as' NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE Douglas V. Pickett Senior Project Manager OFFICE NRR DIVISION DLPM BRANCH LPD3 Distribution of this form and attachments:
Docket File/Central File PUBLIC This oirm was designed using InForms NRC FORM 658 (9-1999)
PRINTED ON RECYCLED PAPER
I K;
~
Nuclear Exelon/AmerGen Licensing Meeting with NRC May 21, 2003 7 (,F~,
i%
H
Agenda
- Introductions
- Organizational Structure
- Multi-Plant Submittals
- Risk Informed Initiative 5b
- Other Issues for Discussion
- Open Discussion
- Regional Break-out Sessions Submittals currently with NRC Upcoming submittals 2
Organizational Structure INPO Loaned Employee Gary Waldrep 11 Director-Licensing MWROG Keith Jury Director-Licensing MAROG Mike Gallagher Director-Emergency Preparedness Charlie Arnone I~~~
3 Vice President Licensing & Regulatory Affairs and Emergency Preparedness Jeff Benjamin Manager, Licensing Programs Darin Benyak Senior Program Specialist DaleAmbler Manager, Licensing Braidwood/Byron Ken Ainger Manager, Licensing Limerick/Peach Bottom Dave Helker Manager, Licensing Clinton/LaSalle Terry Simpkin Manager, EP MWROG Scott McCain Manager, Licensing Oyster Creek/TMI John Hufnagel Manager, Licensing Dresden/Quad Cities Pat Simpson Manager, EP MAROG Don Tailleart
}
Multi-Plant Submittals -
Instrument Bus Inverter AOT
- Lead Licensing Manager - Ken Ainger
- Strategy
- Separate submittals for Byron/Braidwood and Clinton
- Schedule
- Byron/Braidwood (submitted October 2002)
- Clinton (October 2003) 4
Multi-Plant Submittals-DC Systems
- Lead Licensing Manager - Ken Ainger
- Strategy - Multiple submittals due to DC system differences at each site
- Schedule
- Oyster Creek (submitted April 2003)
- Dresden (June 2003)
- LaSalle (September 2003) 5
Multi-Plant Submittals-Response Time Testing
- Lead Licensing Manager - Terry Simpkin
- Strategy - Separate Submittals for Clinton and LaSalle
- Schedule
- Scheduled Submittal: 11/14/03
- Desired Approval: 11/14/04 6
Multi-Plant Submittals ILRT Testing Lead Licensing Manager - John Hufnagel Strategy Multiple submittals, learning from experience Address early plant RAIs in later submittals Reduce review times/costs Take advantage of 20 year interval for later plants if available Schedule Peach Bottom 3 Extended; TMI, Clinton, LaSalle, Quad Cities under NRC Review Dresden currently targeted for November 2003 submittal Others several years away (LGS, Byron, Braidwood, Peach Bottom 2, Oyster Creek) 7
Multi-Plant Submittals Scram Time Testing
- Lead Licensing Manager - Patrick Simpson
- Strategy - Single submittal
- Clinton, Dresden, Limerick, Peach Bottom, and Quad Cities
- Schedule
- Expect to submit in December 2003 8
Multi-Plant Submittals Alternate Source Term
- Lead Licensing Manager - Dave Helker
- Strategy Multiple submittals Dresden & Quad Cities submitted October 2002 Clinton submitted April 2003
- Schedule Peach Bottom (June 2003)
Limerick (December 2003)
LaSalle/Byron/Braidwood (2004) 9
Risk Informed Initiative 5b
- Extend Surveillance Test Intervals
- NEI/BWROG Methodology
- Pilot Program (Peach Bottom & Limerick)
- Potential STIs in pilot
- Expected Submittal Date (January 2004)
Other Issues for Discussion
- Communication of NRC review schedules
- Exelon Risk Engineering
- PDI code alternatives
- Proprietary Information
- SLMCPR Exemption Request feedback/lessons learned
- Davis-Besse Task Force (PM visits.)
- Summer Schedules 11
Open Discussion 12
Break-out Sessions
- Regional Break-outs Review submittals currently with NRC Identify remaining submittals planned for 2003 13