Letter Sequence Meeting |
---|
|
|
MONTHYEARML0308504672003-03-20020 March 2003 TS Proposed Change No.257, Implementation of Arts/Mella Project stage: Request ML0309206482003-04-15015 April 2003 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0312101232003-05-0707 May 2003 Summary of April 29, 2003, Category 1 Meeting with ENVY, to Discuss Arts/Mella Application Project stage: Meeting ML0313900392003-05-21021 May 2003 Request for Additional Information, Arts/Mellla Project stage: RAI ML0322702812003-08-25025 August 2003 Request for Withholding Information from Public Disclosure, GE Proprietary Information, GE-VYNPS-AEP-214, Panacea and Iscor Files Project stage: Withholding Request Acceptance ML0331000472003-10-30030 October 2003 Sign-in Sheet for 10/30/2003 Meeting with ENVY and ENO Re to Discuss Arts/Mellla, Alternate Source Term, and Extended Power Uprate Aplications Project stage: Meeting ML0330403972003-10-30030 October 2003 Meeting Handouts for Meeting with Entergy Re Issues for Alternate Source Term, Power Uprate & Acts/Mellla Application Project stage: Meeting ML0331000232003-11-19019 November 2003 10/30/2003 Meeting with Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc Regarding Arts/Mellla, Alternate Source Term, and Extended Power Uprate Applications Project stage: Meeting ML0411202522004-04-14014 April 2004 Technical Specification Pages for Vermont Yankee Nuclear Power Station, License Amendment, Issuance of Amendment Implementation of Arts/Mellla Project stage: Approval ML0409203522004-04-14014 April 2004 License Amendment, Revise Technical Specifications (Tss) to Reflect an Expanded Operating Domain Resulting from Implementation of Average Power Range Monitor, Rod Block Monitor Tss/Maximum Extended Load Line Limit Analysis (Arts/Mellla) Project stage: Other BVY 05-002, Corrected Technical Specification Bases Page and Administrative Changes to Facility Operating License Page2005-01-17017 January 2005 Corrected Technical Specification Bases Page and Administrative Changes to Facility Operating License Page Project stage: Other 2003-05-21
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML19317D0762019-11-18018 November 2019 Summary of Meeting Near Vermont Yankee Power Station Regarding Establishment and Opration of Community Advisory Boards ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17192A3752017-05-25025 May 2017 Summary of Vermont Nuclear Decommissioning Citizens Advisory Panel Public Meeting of May 25, 2017 ML17031A2772017-02-0101 February 2017 January 24, 2017, Summary of NRC Public Meeting on the Proposed License Transfer of Vermont Yankee for Decommissioning ML15068A2672015-03-0909 March 2015 Summary of Meeting with Vermont Yankee and the Public Webinar Regarding the Decommissioning of Vermont Yankee ML14154A4422014-06-0303 June 2014 Summary of Annual Assessment Meeting for Vermont Yankee Nuclear Power Station on 5/28/14 ML13181A0062013-07-0303 July 2013 6/12/13 Summary of Conference Call with Entergy Nuclear Operations, Inc. to Discuss Draft Requests for Additional Information for Vermont Yankee NRC Order Number EA-12-049 Related to Mitigation Strategies ML13127A0372013-05-0606 May 2013 4/30/13 - Summary of Annual Assessment Meeting with Vermont Yankee ML12333A2222012-11-30030 November 2012 Summary of Pre-Application Meeting with Entergy Nuclear Operations, Inc., Regarding the Proposed License Amendment Request to Revise the Vermont Yankee Licensing Basis for Station Blackout Diesel Generator ML12156A1572012-06-0404 June 2012 2011 Annual Assessment Meeting Summary ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors ML1118613262011-07-0505 July 2011 Summary of the June 22, 2011 Annual Assessment Public Meeting ML1117906392011-06-28028 June 2011 Summary of Meeting with Entergy Operations Inc ML11166A1342011-06-22022 June 2011 Meeting Summary with the Beyond Nuclear Petitioners Regarding Their 2.206 Petition to Suspend Operating Licenses (Ols) of General Electric (GE) Boiling Water Reactors (Bwrs) Mark I (Bwrs) ML1110401712011-04-27027 April 2011 04/5/2011 Summary of Preapplication Meeting with Entergy Operations, Inc. to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1022204552010-08-10010 August 2010 Summary of Vermont Yankee Annual Assessment Open House and Public Meeting ML1022204782010-08-10010 August 2010 Summary of the July 14, 2010 Roundtable Meeting with Representatives of Stakeholder and Public Interest Groups Regarding Vermont Yankee ML1011100082010-04-21021 April 2010 Summary of Public Meeting to Discuss the Results of Entergy Nuclear Plant Safety Culture Workplace Survey ML1006802992010-03-0303 March 2010 Transcript of 2.206 Petition Vermont Yankee and Raymond Shadis Teleconference Dated March 3, 2010. Pages 1-30 ML0916304732009-06-17017 June 2009 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Discuss a Proposed License Amendment for the Use of a Fiber-Reinforced Polymer (FRP) System ML0908603802009-05-0808 May 2009 Audit Summary Regarding the Vermont Yankee Nuclear Power Station License Renewal Application ML0835100522008-12-0101 December 2008 Summary of October 14, 2008 Vermont Yankee Cooling Tower Special Inspection Public Meeting, Dated 12/01/08 ML0815601802008-05-29029 May 2008 Summary of Annual Assessment Meeting with Entergy Nuclear Operations, Inc ML0805202692008-02-29029 February 2008 02/01/2008 Summary of Telephone Conference Call Between the NRC & Entergy Nuclear Operations, Inc., Concerning Confirmatory Analysis Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0802205082008-01-31031 January 2008 01/08/2008 Summary of Meeting Between the NRC Staff and Entergy Nuclear Operations, Inc. to Discuss the Response to a Request for Additional Information Pertaining to the Vermont Yankee License Renewal ML0803501662008-01-15015 January 2008 (PA-LR) Draft January 8, 2008 NRC-VY/Entergy Meeting Summary ML0736104692008-01-0202 January 2008 Summary of Telephone Conf Call Held on 10/23/07 Between NRC and Entergy Nuclear Operations Concerning Audit Questions Pertaining to the Vermont Yankee Nuclear Power Station LRA ML0736501182007-12-21021 December 2007 (PA-LR) 12/18 Meeting Summary and Draft RAI ML0733001522007-11-26026 November 2007 Summary of Telephone Conference Call Held on October 16, 2007, Between U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Audit Questions Pertaining to the Vermont Yankee Nuclear Power Station License Renewa ML0733902012007-11-19019 November 2007 (PA-LR) 10/16/2007 Summary of Telephone Conference Call Between NRC and Entergy Nuclear Operations, Inc., Concerning Audit Questions Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0731101582007-11-16016 November 2007 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Requests for Additional Information Pertaining to Vermont Yankee ML0730202072007-11-16016 November 2007 Summary of Telephone Conference Call Held on September 14, 2007, Between the NRC and Entergy Nuclear Operations, Inc., Concerning a Request for Additional Information Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Ap ML0731803742007-11-16016 November 2007 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Audit Questions Pertaining to the Vermont Yankee Nuclear Power Station LRA ML0729200762007-10-25025 October 2007 08/20/2007 Summary of Telephone Conference Call with Entergy Nuclear Operation, Inc., Concerning License Renewal Application ML0733811982007-10-24024 October 2007 (PA-LR) 08/27/2007 and 09/15/2007 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information Pertaining to the Vermont Yank ML0733811942007-10-24024 October 2007 (PA-LR) 10/20/07 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Vermont Yankee Nuclear Power Station License Renewal Application ML0726300102007-10-0101 October 2007 08/13/2007 Summary of Meeting with Entergy Nuclear Operation, Inc., Representatives Re License Renewal Application ML0727403852007-09-18018 September 2007 (PA-LR) 8/17 Summary of Telephone Conference - August 17, 2007, Between the NRC and Entergy Nuclear Operations, Inc., Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0723601112007-09-0505 September 2007 08/08/2007 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Information Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0722703942007-08-28028 August 2007 Summary of Telephone Conference Call Held on August 1, 2007, Between the Us NRC and Entergy Nuclear Operations, Inc., Concerning New Information Pertaining to the Vermont Yankee Nuclear Power Station, License Renewal Application ML0727403672007-08-23023 August 2007 (PA-LR) 08/08 Teleconference Letter Comments ML0727403862007-08-23023 August 2007 (PA-LR) August 8 Call Summary ML0724705292007-08-20020 August 2007 (PA-LR) Review and Response ML0724705342007-08-0101 August 2007 (PA-LR) Call Summaries for Your Review and Comment ML0718301872007-07-10010 July 2007 06/01/2007 Summary of Telephone Conference Call Between the NRC and Entergy Nuclear Operations, Inc., Concerning Items Pertaining to the Vermont Yankee License Renewal Safety Evaluation Report ML0718301562007-06-29029 June 2007 Summary of Telephone Conference Call Held on May 29, 2007, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Vermont Yankee Nuclear Power Station License Renewal Application ML0717100572007-06-25025 June 2007 03/23/2007 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0717101412007-06-25025 June 2007 Summary of Telephone Conference Call Held on April 2, 2007, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0715000282007-05-30030 May 2007 Meeting Summary for Vermont Yankee AA Meeting 2019-11-18
[Table view] |
Text
May 7, 2003 LICENSEE: Entergy Nuclear Vermont Yankee (ENVY)
FACILITY: Vermont Yankee Nuclear Power Station (VY)
SUBJECT:
SUMMARY
OF APRIL 29, 2003, CATEGORY 1 MEETING WITH ENVY, TO DISCUSS THEIR ARTS/MELLLA APPLICATION (TAC NO. MB8070)
On April 29, 2003, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives from ENVY, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss ENVYs Average Power Range Monitor, Rod Block Monitor Technical Specifications/Maximum Extended Load Line Limit Analysis (ARTS/MELLLA) application of March 20, 2003 and communication expectations.
No formal presentations were made. The licensee and the NRC staff discussed their respective expectations for having coordinated communications during this review and subsequent reviews of future applications through the proposed power uprate process.
The NRC staff queried the licensee about several issues, including expected review time and the need for sufficient detail to support the applications. The staff had not completed the request for additional information (RAI) process, however, several questions were discussed concerning the ARTS/MELLLA application. These questions allowed the licensee to understand the nature or reason for the questions and allowed the staff to better articulate the questions that will be addressed in the RAI.
No members of the public were in attendance. Public Meeting Forms were distributed to the attendees. Any forms returned will be forwarded to the Office of the Executive Director for Operations.
A list of meeting attendees is enclosed.
If you have additional inquiries, please contact me by phone at 301-415-3016, or via e-mail at rmp3@nrc.gov.
/RA/
Robert M. Pulsifer, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosure:
List of Meeting Attendees cc w/encl: See next page
If you have additional inquiries, please contact me by phone at 301-415-3016, or via e-mail at rmp3@nrc.gov.
/RA/
Robert M. Pulsifer, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosure:
List of Meeting Attendees cc w/encl: See next page DISTRIBUTION:
PUBLIC OGC PDI-2 R/F ACRS/ACNW J. Clifford J.Zwolinski/T.Marsh R. Pulsifer Z. Abdullahi C. Raynor K. Coyne C. Anderson, RI R. Caruso F. Akstulewicz M. Shuaibi E. Kendrick G. Thomas H. Garg M. Kotzalas T. McGinty Accession No.: ML031210123 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC NAME RPulsifer C. Raynor R. Ennis forJ.Clifford DATE 5/6/03 5/6/03 5/6/03 OFFICIAL RECORD COPY
LIST OF MEETING ATTENDEES ENTERGY NUCLEAR VERMONT YANKEE AND NRC ARTS/MELLLA April 29, 2003 NAME AFFILIATION Brian Hobbs Entergy Ronda DeFlucas Entergy Craig Nichols Entergy Edward Duda Entergy Chris Rose Entergy C.J. Richardson Entergy Kenneth Hutka PSEG Nuclear Michael Dick GE Nuclear Energy Edward Schrull GE Nuclear Energy Christina Roberts GE Nuclear Energy Carl Hinds GE Nuclear Energy Ralph Caruso NRC/ACRS Edward Kendrick NRC/NRR Bob Pulsifer NRC/NRR Mohammed Shuaibi NRC/NRR George Thomas NRC/NRR Zena Abdullahi NRC/NRR Frank Akstulewicz NRC/NRR Hukam Garg NRC/NRR Kevin Coyne NRC/NRR Enclosure