FPL Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 April 14, 2003 L-2003-090 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re:
St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the March 2003 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units I and 2.
Report also contains a corrected page from the Unit 1 Operating Data Report for February 2003. There was a calculation error on line 6 - Net Electrical Energy (MWH).
Please contact us should there be any questions regarding this information.
Vice PFsidert St. Lucie Plant WJ/spt Attachments
" A
,I an FPL Group company
DOCKET NO.:
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 St. Lucie Unit 1 April 1,2003 J. A. Rogers (772) 467-7296 REPORTING PERIOD: March 2003
- 1. Design Electrical Rating (Mwe-Net)
- 2. Maximum Dependable Capacity (Mwe-Net)_
- 3. Number of Hours Reactor Critical_
- 4. Number of Hours Generator On Line__
- 5. Unit Reserve Shutdown Hours_
- 6. Net Electrical Energy (MWH) 830 839 MONTH 744 744 0.0 638824
-YTD-2160 2160 0.0 1858480 CUMIJLATIVE 186944 185110.3 0.0 151454614
CORRECTED PAGE DOCKET NO.:
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 St. Lucie Unit 1 March 3,2003 J. A. Rogers (772) 467-7296 REPORTING PERIOD: February 2003
- 1. Design Electrical Rating (Mwe-Net)
- 2. Maximum Dependable Capacity (Mwe-Net).
- 3. Number of Hours Reactor Critical_
- 4. Number of Hours Generator On Line_
- 5. Unit Reserve Shutdown Hours_
- 6. Net Electrical Energy (MWH) 830 839 MONTH 672 672 0.0 578938
-YTD-1416 1416 0.0 1219656 CUMULATIVE 186200 184366.3 0.0 150815790
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 St. Lucie Unit I April 1, 2003 J. A. Rogers (772) 467-7296 REPORT MONTH: March 2003 Unit I operated at essentially full power through the entire month of March.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-335 St. Lucie Unit I April 1, 2003 J. A. Rogers (772) 467-7296 REPORT MONTH: March 2003 Number Date Typel Duration Reason2 Method of Cause & Corrective (Hours)
Shutting Down Action to Reactor3 Prevent Recurrence
=Unit 1 operated at essentially full power for the entire month of March.
I 2
3 F Forced S Scheduled Reason A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
Method I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 -Load Reduction 9 - Other (Explain)
DOCKET NO.:
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-389 St. Lucie Unit 2 April 1, 2003 J. A. Rogers (772) 467-7296 REPORTING PERIOD: March 2003
- 1. Design Electrical Rating (Mwe-Net)e
- 2. Maximum Dependable Capacity (Mwe-Net).
- 3. Number of Hours Reactor Critical_
- 4. Number of Hours Generator On Line_
- 5. Unit Reserve Shutdown Hours_
- 6. Net Electrical Energy (MWH) 830 839 MONTH 744 744 0.0 629103
-YTD-2160 2160 0.0 1836775 CUMULATIVE 150918.6 149160.3 0.0 122992409
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-389 St. Lucie Unit 2 April 1,2003 J. A. Rogers (772) 467-7296 REPORT MONTH: March 2003 Unit 2 operated at essentially full power through the entire month of March.
In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-389 St. Lucie Unit 2 April 1, 2003 J. A. Rogers (772) 467-7296 REPORT MONTH: March 2003 Number Date Typel Duration Reason2 Method of Cause & Corrective (Hours)
Shutting Down Action to Reactor3 Prevent Recurrence Unit 2 operated at essentially full power for the entire month of March.
I 2
3 F Forced S Scheduled Reason A - Equipment Failure (Explain) 8 - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error (Explain)
H - Other (Explain)
Method I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continued 5 -Load Reduction 9 - Other (Explain)