March 2003 Monthly Operating Report for Surry Units 1 & 2
ML031060380
Person / Time
Site: Surry  Dominion icon.png
Issue date: 04/08/2003
From: Blount R
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
03-252, SPS Lic/JSA R0
Download: ML031060380 (19)


Text

i VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 April 8, 2003 U. S. Nuclear Regulatory Commission Serial No.03-252 Attention: Document Control Desk SPS Lic/JSA RO Washington, D.C. 20555-0001 Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS I AND 2 MONTHLY OPERATING REPORT The Monthly Operating Report for Surry Power Station Units 1 and 2 for the month of March 2003 is provided in the attachment.

If you have any questions or require additional information, please contact us.

Very truly yours, Richard H. Blount, Site Vice President Surry Power Station Attachment Commitments made by this letter: None cc:

United States Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23 T85 Atlanta, Georgia 30303-8931 Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT No. 03-03 Approved:

de1t Site Vice President

/ C~ite

Surry Monthly Operating Report No. 03-03 Page 2 of 18 TABLE OF CONTENTS Section Page Operating Data Report - Unit No. 1............................................................

3 Operating Data Report - Unit No. 2.............................................................

4 Unit Shutdowns and Power Reductions - Unit No. 1.............................................................

5 Unit Shutdowns and Power Reductions - Unit No. 2.............................................................

6 Average Daily Unit Power Level - Unit No. 1.............................................................

7 Average Daily Unit Power Level - Unit No. 2.............................................................

8 Summary of Operating Experience - Unit Nos. 1 and 2............................................................. 9 Facility Changes That Did Not Require NRC Approval............................................................

10 Procedure or Method of Operation Changes That Did Not Require NRC Approval................................................. 11 Tests and Experiments That Did Not Require NRC Approval............................................................

12 Chemistry Report............................................................

13 Fuel Handling - U nit Nos 1 and 2............................................................

14 Description of Periodic Test(s) Which Were Not Completed Within the Time Limits Specified in Technical Specifications............................................................

18

Surry Monthly Operating Report No. 03-03 Page 3 of 18 OPERATING DATA REPORT Docket No.:

Date:

Completed By:

Telephone:

50-280 04/01/03 R. Stief (757) 365-2486 1.

2.

3.

4.

5.

6.

7.

Unit Name:...........................................................

Reporting Period:.................................................

Licensed Thermal Power (MWt):..........................

Nameplate Rating (Gross MWe):.........................

Design Electrical Rating (Net MWe):....................

Maximum Dependable Capacity (Gross MWe):...

Maximum Dependable Capacity (Net MWe):.......

Surry Unit 1 March 2003 2546 847.5 788 842 810

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

9.

Power Level To Which Restricted, If Any (Net MWe):

10.

Reasons For Restrictions, If Any:

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

Hours in Reporting Period Hours Reactor Was Critical Reactor Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy Generated (MWH)

Net Electrical Energy Generated (MWH)

Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC Net)

Unit Capacity Factor (Using DER Net)

Unit Forced Outage Rate This Month 744.0 744.0 0.0 744.0 0.0 1894101.8 634113.0 611723.0 100.0%

100.0%

101.5%

104.3%

0.0%

Year-To-Date 2160.0 1869.7 0.0 1816.3 0.0 4537277.5 1514216.0 1459566.0 84.1%

84.1%

83.4%

85.8%

15.9%

Cumulative 265368.0 196391.3 3774.5 193678.5 3736.2 462043594.2 152019540.0 145201887.0 73.0%

74.4%

69.9%

69.4%

12.3%

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

April 2003 Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 20001

25.

If Shut Down at End of Report Period, Estimated Date of Start-up:

Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26.

Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

Surry Monthly Operating Report No. 03-03 Page 4 of 18 OPERATING DATA REPORT Docket No.:

Date:

Completed By:

Telephone:

50-281 04/01/03 R. Stief (757) 365-2486 1.

2.

3.

4.

5.

6.

7.

Unit Name:...........................................................

Reporting Period:.................................................

Licensed Thermal Power (MWt):..........................

Nameplate Rating (Gross MWe):.........................

Design Electrical Rating (Net MWe):....................

Maximum Dependable Capacity (Gross MWe):...

Maximum Dependable Capacity (Net MWe):.......

Surry Unit 2 March 2003 2546 847.5 788 847 815

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

9.

Power Level To Which Restricted, If Any (Net MWe):

10.

Reasons For Restrictions, If Any:

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

Hours in Reporting Period Hours Reactor Was Critical Reactor Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy Generated (MWH)

Net Electrical Energy Generated (MWH)

Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC Net)

Unit Capacity Factor (Using DER Net)

Unit Forced Outage Rate This Month 744.0 744.0 0.0 744.0 0.0 1893001.9 635482.0 613928.0 100.0%

100.0%

101.2%

104.7%

0.0%

Year-To-Date 2160.0 2097.1 0.0 2072.3 0.0 5261115.5 1784903.0 1703924.0 95.9%

95.9%

96.8%

100.1%

4.1%

Cumulative 262249.0 193980.5 328.1 191656.7 0.0 458488100.0 150925436.0 144184641.0 73.1%

73.1%

69.9%

69.8%

9.7%

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 2000]

25.

If Shut Down at End of Report Period, Estimated Date of Start-up:

Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26.

Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

Surry Monthly Operating Report No. 03-03 Page 5 of 18 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: March 2003 Docket No.:

50-280 Unit Name:

Surry Unit 1 Date:

04/01/03 Completed by: R. Stief Telephone:

(757) 365-2486 None during the Reporting Period (1)

F:

Forced S:

Scheduled (2)

REASON:

A -

Equipment Failure (Explain)

B -

Maintenance or Test C -

Refueling D -

Regulatory Restriction E -

Operator Training & Licensing Examination F -

Administrative G -

Operational Error (Explain)

H Other (Explain)

(3)

METHOD:

1 -

Manual 2 -

Manual Scram 3 -

Automatic Scram 4 -

Other (Explain)

(4)

Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG 0161)

(5)

Exhibit 1 - Same Source

Surry Monthly Operating Report No. 03-03 Page 6 of 18 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: March 2003 Docket No.:

50-281 Unit Name:

Surry Unit 2 Date:

04101/03 Completed by:

R. Stief Telephone:

(757) 365-2486 None during the Reporting Period (1)

F:

Forced S:

Scheduled (2)

REASON:

A -

Equipment Failure (Explain)

B -

Maintenance or Test C -

Refueling D -

Regulatory Restriction E -

Operator Training & Licensing Examination F -

Administrative G -

Operational Error (Explain)

H Other (Explain)

(3)

METHOD:

1 -

Manual 2 -

Manual Scram 3 -

Automatic Scram 4 -

Other (Explain)

(4)

Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG 0161)

(5)

Exhibit 1 - Same Source

Surry Monthly Operating Report No. 03-03 Page 7 of 18 AVERAGE DAILY UNIT POWER LEVEL Docket No.:

50-280 Unit Name:

Surry Unit 1 Date:

04/01/03 Completed by:

R. Stief Telephone:

(757) 365-2486 MONTH:

March 2003 Day 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 Average Daily Power Level (MWe - Net) 821 821 821 822 822 822 822 822 822 822 823 823 823 823 823 821 Day 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Average Daily Power Level (MWe - Net) 821 821 822 823 823 822 823 821 821 821 824 824 824 824 823 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 03-03 Page 8 of 18 AVERAGE DAILY UNIT POWER LEVEL Docket No.:

50-281 Unit Name:

Surry Unit 2 Date:

04/01/03 Completed by:

R. Stief Telephone: (757) 365-2486 MONTH:

March 2003 Day 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 Average Daily Power Level (MWe - Net) 825 825 825 825 825 825 812 826 826 826 825 825 825 826 827 827 Day 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Average Daily Power Level (MWe - Net) 827 826 827 826 826 826 826 826 826 826 825 825 825 824 823 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 03-03 Page 9 of 18

SUMMARY

OF OPERATING EXPERIENCE MONTHNEAR: March 2003 The following chronological sequence by unit is a summary of operating experiences for this month that required load reductions or resulted in significant non-load related incidents.

UNrr ONE:

03/01/03 0000 Unit started the month at 100% / 852 MWe.

03/31/03 2400 Unit finished the month at 100% /853 MWe.

UNrTTwo:

03/01/03 0000 Unit started the month at 100% / 854 MWe.

03/07/03 1252 Commenced ramp to 90% power in accordance with 2-OP-TM-005 in prep for swapping HP Heater Drain Pumps.

03/07/03 1350 Stopped ramp at 90% / 770 MWe.

03/07/03 1414 Started Heater Drain Pump 2-SD-P-1A.

03/07/03 1507 Secured Heater Drain Pump 2-SD-P-1 B.

03/07/03 1648 Commenced ramp to 100%.

03/07/03 1839 Unit at 100% /853 MWe.

03/31/03 2400 Unit finished the month at 100% / 854 MWe.

Surry Monthly Operating Report No. 03-03 Page 10 of 18 FACILrrY CHANGES THAT DID NOT REQUIRE NRC APPROVAL MoNTHNEAR: March 2003 None during the Reporting Period

Surry Monthly Operating Report No. 03-03 Page 11 of 18 PROCEDURE OR METHOD OF OPERATION CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTHNEAR: March 2003 None during the Reporting Period

Surry Monthly Operating Report No. 03-03 Page 12 of 18 TESTS AND EXPERIMENTS THAT DID NOT REQUIRE NRC APPROVAL MoNTH/YEAR: March 2003 None during the Reporting Period

Surry Monthly Operating Report No. 03-03 Page 13 of 18 CHEMISTRY REPORT MONTH/YEAR: March 2003 Unit No 1 Unit No. 2 Primary Coolant Analysis Max.

Min.

Avg.

Max.

Min.

Avg.

Gross Radioactivity, AiCiml 3.68E-1 1.89E-1 2.67E-1 3.69E-1 1.61 E-1 2.53E-1 Suspended Solids, ppm S 0.01

  • 0.01 S 0.01 S 0.01
  • 0.01 S 0.01 Gross Tritium, pCVml 9.67E-2 8.58E-2 9.27E-2 8.34E-1 7.73E-1 8.07E-1 1131, Ci/mI 2.88E-4 1.63E-4 2.23E-4 1.18E-4 6.76E-5 8.97E-5 1131/1133 0.09 0.05 0.07 0.11 0.06 0.08 Hydrogen, cc/kg 40.5 35.3 37.3 38.7 37.1 37.8 Lithium, ppm 1.71 1.15 1.4 2.32 2.08 2.19 Boron - 10, ppm*

43.5 23.7 33 7 139 120 130 Oxygen, (DO), ppm

  • 0.005
  • 0.005
  • 0.005
  • 0.005
  • 0.005
  • 0 005 Chloride, ppm 0.002 0.001 0.001 0.004 0.001 0.002 pH @ 25 degree Celsius 7.56 6.92 7.39 7.07 6.24 6.71 Boron - 10 = Total Boron x 0.196 Comments:

None

Surry Monthly Operating Report No. 03-03 Page 14 of 18 FUEL HANDLING UNITS 1 &2 MONTHIYEAR: March 2003 New Fuel Number of Shipment or Date Stored or Assemblies Cask No.

Received per Shipment Unit 1 Batch 21 Shipment #1 03/10/03 12 Assembly Number New or Spent ANSI Initial Fuel Shipping Number Enrichment Cask Activity 01F 06F 07F 13F 19F 29F 32F 37F 40F 45F LM 1 EYQ LM1EYV LM1 EYW LM1 EZ2 LM 1 EZ8 LM1 EZJ LM1 EZM LM1 EZS LM1 EZV LM1 FOO LM 1 F04 LM1 F07 LM1 EYR LM1 EYS LM1 EYT LM1 EYU LM1 EYX LM1 EYY 4.0983 573.13 GBq 4.0930 4.1090 4.1107 4.1039 4.2509 4.2484 4.2497 4.2475 4.2499 4.2518 4.2516 49F 52F 02F Unit 1 Batch 21 Shipment #2 03/11103 12 4.0970 563.88 GBq 03F 04F 05F 08F 09F 4.0951 4.0927 4.0958 4.1128 4.0923

Surry Monthly Operating Report No. 03-03 Page 15 of 18 FUEL HANDLING UNITS 1 &2 MONTHYEAR: March 2003 New Fuel Number of Shipment or Date Stored or Assemblies Cask No.

Received per Shipment Assembly Number ANSI Number New or Spent Initial Fuel Shipping Enrichment Cask Activity 1OF 11F 12F LM1 EYZ LM1 EZO LM1 EZ1 4.0993 4.1034 4.1064 14F 43F 44F 20F Unit 1 Batch 21 Shipment #3 03/12/03 12 21 F 24F 25F 26F 27F 28F 30F 31 F 33F 34F 35F LM1 EZ3 LM1 EZY LM1 EZZ LM1 EZ9 LM1 EZA LM1EZD LM1 EZE LM1EZF LM1 EZG LM1 EZH LM1 EZK LM1 EZL LM1EZN LM1 EZP LM1 EZQ 4.1063 4.2488 4.2518 4.1041 577.57 GBq 4.2410 4.2319 4.2390 4.2399 4.2535 4.2449 4.2448 4.2381 4.2545 4.2487 4.2447

Surry Monthly Operating Report No. 03-03 Page 16 of 18 FUEL HANDLING UNITS 1 &2 MONTH/YEAR: March 2003 New Fuel Number of Shipment or Date Stored or Assemblies Cask No.

Received per Shipment Unit 1 Batch 21 Shipment #4 03/13/03 12 Assembly Number New or Spent ANSI Initial Fuel Shipping Number Enrichment Cask Activity 15F 16F 17F 18F 22F 23F 36F 38F 39F 41 F 42F 46F 47F LM1 EZ4 LM1 EZ5 LM1 EZ6 LM1 EZ7 LM1 EZB LM1 EZC LM1 EZR LM1EZT LM1 EZU LM1 EZW LM1 EZX LM1 F01 LM1 F02 LM1 F03 LM1 F05 LM1 F06 LM1F08 LM1F09 4.1071 4.1188 4.1019 4.0963 4.2357 4.2367 4.2478 4.2500 4.2492 4.2489 4.2490 4.2505 574.61 GBq Unit 1 Batch 21 Shipment #5 03/14/03 8

4.2520 387.76 GBq 48F 5OF 51 F 53F 54F 4.2532 4.2503 4.2538 4.2498 4.2512

Surry Monthly Operating Report No. 03-03 Page 17 of 18 FUEL HANDLING UNITS 1 &2 MoNTH/YEAR: March 2003 New Fuel Shipment or Cask No.

Date Stored or Received Number of Assemblies per Shipment Assembly Number New or Spent ANSI Initial Fuel Shipping Number Enrichment Cask Activity 55F 56F LM1 FOA LM1 FOB 4.2519 4.2524

Surry Monthly Operating Report No. 03-03 Page 18 of 18 DESCRIPTION OF PERIODIC TEST(S) WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS MONTHIYEAR: March 2003 None during the Reporting Period