April 1, 2003 LICENSEE:
Nuclear Management Company, LLC FACILITY:
Prairie Island Nuclear Generating Station, Unit 1
SUBJECT:
SUMMARY
OF MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION STAFF AND NUCLEAR MANAGEMENT COMPANY, LLC, HELD ON MARCH 12, 2003, REGARDING THE STEAM GENERATOR REPLACEMENT PROGRAM (TAC NO. MB4607)
The Nuclear Regulatory Commission (NRC) staff met with representatives of the Nuclear Management Company, LLC (NMC), at NRC Headquarters, at the request of NMC, on March 12, 2003, regarding the steam generator (SG) replacement program for the Prairie Island Nuclear Generating Station, Unit 1. Enclosure 1 lists the meeting participants.
A public meeting notice for the subject meeting was issued on February 14, 2003, and a copy of the meeting notice was posted on the NRCs external (public) web page (ADAMS Accession No. ML030440271).
The purpose of the meeting was to discuss the status of NMCs activities for the SG replacement project at Prairie Island Unit 1. During the meeting, NMC provided a program overview, including the current condition of Unit 1 SGs, justification for replacement, project organization, and program milestone schedule (Enclosure 2). NMC stated that there is no safety concern with the current condition of Unit 1 SGs. The reasons for NMCs decision to replace the SGs include (1) increasing repair costs, (2) potential need for planned mid-cycle inspections and forced outages, (3) increasing outage time, (4) reduction in plant output, and (5) replacement energy costs. NMC stated that Framatome-ANP is the SG replacement vendor. NMC plans to replace the SGs during a planned refueling outage in September 2004.
At the conclusion of the meeting, it was agreed in principle that another meeting should be scheduled in the fall 2003 to focus on the licensing and fabrication of the replacement SGs, followed by a meeting in Spring 2004 to focus on pre-installation.
/RA/
John G. Lamb, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
Enclosures:
- 1. Meeting Attendees
- 2. NMC Handouts cc w/encls: See next page
The purpose of the meeting was to discuss the status of NMCs activities for the SG replacement project at Prairie Island Unit 1. During the meeting, NMC provided a program overview, including the current condition of Unit 1 SGs, justification for replacement, project organization, and program milestone schedule (Enclosure 2). NMC stated that there is no safety concern with the current condition of Unit 1 SGs. The reasons for NMCs decision to replace the SGs include (1) increasing repair costs, (2) potential need for planned mid-cycle inspections and forced outages, (3) increasing outage time, (4) reduction in plant output, and (5) replacement energy costs. NMC stated that Framatome-ANP is the SG replacement vendor. NMC plans to replace the SGs during a planned refueling outage in September 2004.
At the conclusion of the meeting, it was agreed in principle that another meeting should be scheduled in the fall 2003 to focus on the licensing and fabrication of the replacement SGs, followed by a meeting in Spring 2004 to focus on pre-installation.
/RA/
John G. Lamb, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
Enclosures:
- 1. Meeting Attendees
- 2. NMC Handouts cc w/encls: See next page DISTRIBUTION:
PUBLIC JLamb LMiller KRiemer, RIII BDavis PDIII-1 Reading RBouling DTerao JZwolinski/LMarsh DJones WRuland JTsao MKotzalas LRaghavan PKlein HNieh ADAMS Accession No. ML030910082 (Meeting Summary)
ADAMS Accession No. ML030980830 (Enclosure 2)
ADAMS Accession No. ML030910090 (Package)
- Concurred via e-mail OFFICE PDIII-1/PM PDIII-1/LA*
PDIII-1/SC NAME JLamb RBouling LRaghavan DATE 04/01/03 03/31/03 04/01/03
ENCLOSURE 1 MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION AND THE NUCLEAR MANAGEMENT COMPANY, LLC, REGARDING STEAM GENERATOR REPLACEMENT PROJECT AT PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 WEDNESDAY, MARCH 12, 2003 NAME ORGANIZATION D. Jones NRC/RIII J. Tsao NRC/NRR P. Klein NRC/NRR J. Lamb NRC/NRR L. Miller NRC/NRR D. Terao NRC/NRR B. Davis NRC/NRR K. Albrecht NMC R. Pearson NMC A. Laux Framatone J. Billoue Framatone NRR = Office of Nuclear Reactor Regulation NMC = Nuclear Management Company, LLC RIII = Region III
Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire General Counsel Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Manager, Regulatory Affairs Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089 Adonis A. Neblett Assistant Attorney General Office of the Attorney General 455 Minnesota Street Suite 900 St. Paul, MN 55101-2127 U.S. Nuclear Regulatory Commission Resident Inspectors Office 1719 Wakonade Drive East Welch, MN 55089-9642 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Administrator Goodhue County Courthouse Box 408 Red Wing, MN 55066-0408 Commissioner Minnesota Department of Commerce 121 Seventh Place East Suite 200 St. Paul, MN 55101-2145 Tribal Council Prairie Island Indian Community ATTN: Environmental Department 5636 Sturgeon Lake Road Welch, MN 55089 Mr. Roy A. Anderson Executive Vice President Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Xcel Energy, Inc.
550 15th St., Suite 1000 Denver, CO 80202 John Paul Cowan Chief Nuclear Officer Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Mano K. Nazar Senior Vice President Nuclear Management Company, LLC Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch, MN 55089 Mr. Joseph M. Solymossy Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089 March 2002