Minutes of Internal Meeting of the Davis-Besse Oversight Panel
ML030900860
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/25/2003
From: Grobe J
Division Reactor Projects III
To:
Shared Package
ML021480070 List:
References
Download: ML030900860 (16)


Text

March 25, 2003 MEMORANDUM TO: Davis-Besse Nuclear Power Station IMC 0350 Panel FROM: John A. Grobe, Chairman, Davis-Besse Oversight Panel /RA/

SUBJECT:

MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE OVERSIGHT PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held on February 21, 2003. Attached for your information are the minutes from the internal meeting of the Davis-Besse Oversight Panel, the Open Action Items List, and Inspection Plan for Davis-Besse Special Inspection for Resident Inspections.

Attachments: As stated cc w/att: H. Nieh, OEDO J. Dyer, RIII J. Caldwell, RIII M. Parker, RIII G. Wright, RIII DB0350

MEMORANDUM TO: Davis-Besse Nuclear Power Station IMC 0350 Panel FROM: John A. Grobe, Chairman, Davis-Besse Oversight Panel

SUBJECT:

MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE OVERSIGHT PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held on February 21, 2003. Attached for your information are the minutes from the internal meeting of the Davis-Besse Oversight Panel, the Open Action Items List, and Inspection Plan for Davis-Besse Special Inspection for Resident Inspections.

Attachments: As stated cc w/att: H. Nieh, OEDO J. Dyer, RIII J. Caldwell, RIII M. Parker, RIII G. Wright, RIII DB0350 DOCUMENT NAME: G:\Davis-Besse 0350\internalmtgminutes\internalmtgminutes0211.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII RIII NAME DPassehl CLipa JGrobe DATE 03/11/03 03/20/03 03/25/03 OFFICIAL RECORD COPY

MEETING MINUTES: Internal Davis-Besse Oversight Panel Meeting Davis-Besse Nuclear Power Station DATE: February 21, 2003 TIME: 12:00 p.m. Central ATTENDEES:

J. Grobe J. Hopkins M. Phillips C. Lipa G. Wright J. Collins B. Dean D. Passehl Agenda Items:

1. Discuss Plant Status and Inspector Insights J. Collins briefed the Davis-Besse Oversight Panel (DBOP) on plant status as follows:
  • Fuel Load - 50 fuel assemblies are loaded into the core. 127 assemblies are remaining. Fuel loading scheduled to be complete on Sunday evening.
  • Containment Air Coolers - Work continues on #1 CAC service water tree. A bump start of the #2 CAC was successful.
  • Mode 5 Restraints - 25 condition reports and 9 work orders remaining.
2. Discuss SRI Backlog Inspection A DBOP discussion was held on resident baseline inspections related to 0350 activities verses other 0350 time requirements.
3. Discuss RAM C. Lipa briefed the DBOP on the status of the RAM. A letter with the RAM as an attachment will be sent out today. It was up-to-date last week, however it should be considered a growing document. DBOP members were asked to review the document and assignments. M. Phillips was tasked to ensure that all NCVs were added to the RAM. The current RAM size is 43 pages with over 200 items.

The DBOP discussed the issue of two tracking lists being maintained on similar issues.

The RAM and a DLPM work-off list were identified as similar products. The DBOP agreed to continue using the two lists due to the identification of sufficient differences in format and use such that the work expended was not redundant.

4. Discuss and Approve Resident Inspector Inspection Plan The DBOP approved the Resident Inspector Inspection Plan. The approved plan is attached.
5. Review and Approve Programs Inspection Plan

The DBOP discussed the request by the State of Ohio to send observers to each of the Inspections being performed at Davis-Besse. It was recognized that the MOU between the NRC and the State of Ohio that a maximum of one observer per inspection would be used.

6. Review and Approve NOP/NOT Inspection Plan This item was not ready for DBOP review.
7. Review and Approve the CATI Inspection Plan The DBOP discussed the CATI inspection plan. Eight individuals are assigned to the team. Four personnel from DRS and four contractors. Current issue for the plan is licensee work completion to properly schedule inspection dates.
8. Review and Approve the Fire Protection Inspection Plan The DBOP discussed a modified Appendix R inspection consisting of three inspectors for a one week duration. The outcome of the inspection would form the basis for an additional full Appendix R inspection this year.
9. Discuss Action Items The DBOP discussed open action items and determined actions documented in the attached Action Item List.
10. Discuss Allegations Necessary to Be Resolved Prior to Restart Items discussed by DBOP, but no general resolution was derived.
11. Discuss Dates When Inspection Scheduling Letter Due Date not determined.
12. Status Allegations Older than 120 Days M. Phillips briefed the DBOP on the three remaining allegations older than 120 days.
13. Discussion of Licensing Issues and Actions Weekly licensing meetings with the licensee scheduled to begin next week.
14. Discuss/Update Milestones and Commitments The following items were discussed by the DBOP.

C 2/19 - Brief SCollins on End-of-Cycle meeting results C Dates for John Zwolinski and Brian Sheron Visit - March 10, 11 and 12 possibilities.

C 2/27 - Jim Dyer, Jack Grobe, Brian Sheron, and Roland Lickus will brief Ohio Governor Taft and 10-15 others in the state of Ohio offices on the Davis-Besse.

C 3/11 - 0350 Public Meeting at Camp Perry C 4/15 - 0350 Public Meeting C 5/6 - 0350 Public Meeting

  • 5/6 - Regulatory Information Conference C 6/17 - 0350 Public Meeting - expected to move

Item Action Item (Date Assigned to Comments Number generated) 24a Discuss making Panel Discuss by June 30, after safety information related to significance assessment complete.

HQ/licensee calls publicly 6/27 - Invite Bateman to panel mtg.

available To discuss what else is needed to closeout the CAL (i.e. quarantine plan). 7/2 - NRR not yet ready to discuss. 7/16 - See if procedures have changed on CAL closeout -

does JD need to send letter? 7/18

- Discussed - is there an applicable regional procedure? 8/6 -

Discussed. Need to determine the final approach on the core removed from the head and the final approach on the head before the quarantine can be lifted. 8/22 -

Revisit action item after letter sent to licensee confirming plans with old vessel head (head may be onsite longer than originally anticipated) 8/29 - Memo to be sent to Region, with a letter to go out next week. 10/01- Discussed.

1) Conduct NRC staff survey-due 10/7 2)Memo to NRR - due 10/11
3) Region to issue letter 11/07-Letter required from NRR on head quarantine status. 11/19 - Letter in draft. 01/03 - A. Mendiola to look at phone conference writeups on quarantine decision making to determine if they can be released to the public. 01/07 - discussed 01/21 - discussed. 01/31- A.

Mendiolas action. 02/11 -

Completion of Licensee Phase 3 sampling plan required.

02/21 - 17.5 Rem to cut samples, Less samples may be required.

Item Action Item (Date Assigned to Comments Number generated) 54a Review TSP amendment D. Pickett 7/9 - Discussed. Will wait for and advise the panel on response from licensee. 7/16 -

the need for a TIA on Discussed - added action item 54b.

Davis-Besse (7/2) 8/6 - Sent to the licensee on7/22 and a response is due by 8/22.

8/22 - Discussed - need to check if response has been received. 8/27

- Received response - DRS is reviewing - will fax to NRR for 54b.

8/29 - Discussed, DRS report of response to be issued to panel prior to item 54b. 10/1-Discussed.

DRS coordinating with NRR 11/07-Discussed - On hold for draft with specific information. 12/10 - B.

Dean believed B. Bateman thought a calculation for sufficient volume of TSP was completed to technical specification value. However questions whether the calculation was to technical specification or actual TSP level remain. 01/03 -

Item under NRR review.

Calculation completion expected on Jan 17. Allegation issue in RIII domain. 01/07 - Allegation Item #3 under NRR Review for Resolution.

01/21 - Item #3 is under Region III control for final letter, holding for NRR input. 02/11 - Writeup for NRR input provided 4 answers, going back to reviewer to ensure specific tasking is clear to answer allegation concerns. Action item 54c created. 02/21 - Allegation at 242 day mark. Effective expression of due date required.

54c In relation to action item A. Mendiola 02/11 - Address first meeting in 54a - Assess method to March ensure Technical Specifications are adequate for a cycle, administrative controls vs.

amending technical specifications (02/11)

Item Action Item (Date Assigned to Comments Number generated) 73 Send feedback form on Lipa 8/6 - Generate feedback after IMC 0350 procedure to Mendiola panel meetings reduced to once IIPB (8/6) per week. 8/29 - Discussed - no change. 10/1 - Discussed. 11/7 -

D Passehl sent email to C Carpenter and D Coe indicating that we would be able to perform a review of the draft IMC 0350 during the first quarter of 2003.

12/3- discussed. 01/03 - 2 parts, short part- C. Lipa with P. Harris, long part- B. Dean. 01/07 - 2nd larger response will require meeting between all parties. 01/21

- Communications with P. Harris 01/31-Meeting with P. Harris on Feb 4. 02/11 - Many concerns identified by the panel for inclusion.

02/21 - July 1 due date for larger input.

97 Bulletins 2002-01 and NRR 11/07 - Discussed, further 2002-02 response and research and discussion required; acceptance (9/5) 01/07 - RAI response expected Mid February; 01/31- On track; 02/11 - New Orders will supercede BL2002-01 and BL2002-02 responses with the exception of the BL2002-01 Boric Acid Corrosion program information request; 02/21 - Licensee RAI response delayed. Both Order and BL2002-01 Boric Acid Corrosion program responses to be tracked as RAM items.

Review LLTF report for Mendiola/ 01/07 - In progress 02/11 - Nearing 125 0350 issues / SMRT team Lipa Completion 02/21 - Closed 126 Review Davis- Strasma Besse/Vessel Head 02/11 - Checked, but revisiting Degradation web site item. 02/21 - Web site being content for ease of use by reassessed.

the public. (11/07) 132 Consolidate RAM (12/19) C.Lipa/ Due Fri 1/17. 01/31 - Item open A.Mendiola 02/11 - working 02/21 - to determine the need for ONE list.

Item Action Item (Date Assigned to Comments Number generated) 133 12/29 Taping of debate J.Collins/ 01/03 - Licensee to deliver tape to D.Simpkins J. Strasma 136 NRR acceptance of W. Dean 01/07 - Item discussed. Meeting NOP/NOT criteria and summary of November 26, 2002 method (01/03) meeting has notation of NRR staff impressions of test plan. Once drafted, issue will be surveyed to staff to determine if consciences is correct. 01/21 - Meeting summary to discuss Fluse System, Test agreement, and future inspections.

1/31 - T. Chan fwd to J. Hopkins.

2/11 - J. Jacobson questions need to be folded in (chem-wipes) 2/21 - Polling of staff discussed.

138 Evaluate the effectiveness A. Mendiola, 01/31 - Ongoing 02/21 - New EDO of the Comm Plan (01/07) C. Lipa Comm Plan for Crisis Update, A.

Mendiola to review for inclusion.

139 Licensing Actions Review J. Hopkins 01/21 - Moved to next internal for DBOP internal meeting meeting. 01/31 - Moved on 01/21/03 (01/07) 02/11 - Next meeting 02/21 -

Moved 142 Properly reassign past C. Lipa 01/31 - In progress inspection hours charged 02/11 - Resident Inspector 0350 to TAC W90086 into the special inspection plans presented Reactor Program System to the panel and accepted. 02/21 -

(RPS). Prepare a memo Note how many 0350 hours0.00405 days <br />0.0972 hours <br />5.787037e-4 weeks <br />1.33175e-4 months <br /> would to JDyer to reassign have been assigned to inspection hours. (01/09) prior to the 0350 inspection TAC creation.

143 Prepare a special J. Jacobson 02/21 - date to be determined inspection plan for the NOP/NOT test. (01/09) 144 Prepare a special D. Hills 01/31 - Working Z. Falevits and R.

inspection plan for the Gardner 02/21 - date to be corrective action team determined inspection. (01/09) 145 Prepare a special D. Passehl 02/21 - date to be determined inspection plan for the restart readiness team inspection. (01/09)

Item Action Item (Date Assigned to Comments Number generated) 146 Arrange a Panel briefing D. Passehl 01/31 - open; 02/21 - Closed by RLangstaff to get insight into the scope and depth of 10 CFR 50 Appendix R and EOP issues at Davis-Besse so that the Panel can factor this into the inspection plans for the corrective action team inspection and restart readiness team inspection. (01/09) 147 Generate a list of items to D. Passehl 01/31 - working; 02/11 - Include consider after restart as dates and deadlines to Manual well as transition back to Chapter 0350 restart inspections the normal 0350 when planner terminating the 0350 Panel. The items should include plans to augment inspection of corrective actions, inservice inspection, and safety culture monitoring.

(01/09) 149 SRI to coordinate with S. Thomas 01/31 - open GWright inspection of 02/11 - Documented items in corrective actions that Resident Inspection Report have been completed by 02/21 - Good communications the resident staff. The noted intent is to find ways to allow GWrights inspection to take credit for what the resident staff already accomplished. (01/09) 150 SBurgess to develop a S. Burgess position paper on the state of plant risk when the plant attains Mode 4 for the first time. The purpose is to support NRC scheduling of major inspections until closer to Mode 2. (01/09)

Item Action Item (Date Assigned to Comments Number generated) 151 Develop a plan to assess G. Wright the safety culture at the plant to close Restart Checklist Item 4.b, effectiveness of corrective actions. Discuss at next 0350 internal Panel meeting. (01/09) 153 Discuss with Ken OBrien D. Hills/ 02/21 - Closed which corrective actions J. Jacobson will be inspected and addressed in his programmatic effectiveness report so that items which warrant inspection which will not be addressed in Kens report get addressed during the corrective action inspection. (01/09) 154 Marty has action to M. Farber 02/21 - Date to be determined followup by 1/21 with licensee to understand licensees actions to address common mode failure issues (i.e., topical issues) and brief Panel.

Then develop inspection plan to address topical issues. (01/09) 155 Get resources to supplant C. Lipa 02/21 - Closed resident inspector staff vacancies in February.

SRI has military leave and the RI had househunting scheduled. (01/09) 156 Read Generic Safety J. Hopkins 01/21 - Determine status of GSI-Issue-191, "Assessment of 191; 02/21 - Check GL98-04 Debris Accumulation on response on coatings. Draft GL PWR Sump Pump and Draft Reg Guide needs review Performance" (01/09) for DB relevance.

Item Action Item (Date Assigned to Comments Number generated) 157 Have resident inspection S. Thomas 01/31 - Special Inspection Plan staff address whether the inclusion; 02/21 - Document then licensee is correctly Close classifying and categorizing their backlog relative to work orders, corrective actions, and modifications to hardware.

(01/09) 158 In Ken OBriens D. Hills/

programmatic inspection J. Jacobson plan, add to the summary page the addition of Restart Checklist Item 3.i, Process for Ensuring Completeness and Accuracy of Required Records and Submittals to the NRC, and deletion of Item 3.h, Radiation Protection Program.

(01/09) 159 Document closure of J. Hopkins 01/21 - Feb 1. 01/31 - One open Restart Checklist Items 6, item, send to S. Thomas for licensing issue resolution, inclusion in report; 02/11 -

in the resident inspector Followed up for inclusion; 02/21 -

report. (01/09) Included & closed 160 Draft fragnet of inspection C. Lipa 01/21 - Fragnet-time line. 01/31 -

resources, plans, and Names needed schedules. (01/09) 161 Update the RAM. (01/09) J. Jacobson 02/21 - Add NCVs to RAM M. Phillips 162 Modified Containment P. Lougheed 02/21 - Factor into ILRT plan Walkdown List assessment to look into effects on ILRT and NOP/NOT tests. (01/21) 163 Flag Allegations requiring M. Phillips 02/11 - All of them require action.

action prior to restart Resolve with one letter including (01/21) Item 164; 02/21 - Develop criteria for Allegations considered Restart Items. Criteria needs Panel approval.

Item Action Item (Date Assigned to Comments Number generated) 164 Discuss the need for a M. Phillips 01/31 - Pre-work and then ARB; Chilling Effect Letter with 02/11 - Resolve with one letter Bruce Berson (01/21) including Item 163; 02/21 - Draft letter with C. Lipa, emailed to Panel for review.

165 Ensure the CAT inspection Z. Falevits 02/21 - Closed to 144 is scoped accordingly (01/31) 166 Once DRS has developed Panel 02/11 - currently in planning a draft CY-2004 baseline 02/21 - inspection schedule letter inspection schedule for due as soon as possible.

Davis-Besse (in conjunction with the upcoming regional inspection planning meeting), DRS will present this to the 0350 panel for review. (01/31) 167 R. Gardner to brief panel R. Gardner 02/21 - Closed on Appendix R inspection requirements prior to restart.

168 Verify type of commitment Panel 02/11 - In process of, coordinating to D. Lochbaum in public with NRR, and submitting for panel documentation in review and approval.

inspection reports or 02/21 - Item closed tracked meeting minutes for through item #74 question resolution. Item developed from action item #74. (02/11) 169 Tracking of response G. Dick 02/21 - RAM closure item, item method commitments to closed Gurdziel letters. Item developed from action item #74 (02/11) 170 Prepare a special M. Farber inspection plan for the ILRT (02/11)

Item Action Item (Date Assigned to Comments Number generated) 171 Include dates and D. Passehl 02/21 - closed to 147 deadlines to Manual Chapter 0350 restart inspections planner (02/11) 172 Create a schedule letter to 02/11 - Panel determined that replace/notify that annual Annual Assessment letter and End assessment letter and end of Cycle public meetings not of cycle public meetings occurring.

are not occurring (02/11) 173 Prepare an OSHA MOU S.Thomas 02/21 - D. Simpkins working letter based on email dated 2/6 from Bilik (2/18) 174 Review 2/4 transcript for R. Lickus Mr. Witts recommendations (2/18) 175 LER licensee commitment J. Hopkins 02/21 - Attempt to get by end of on Containment Air Cooler February Supplement for 01/31/03 (02/21)

INSPECTION PLAN Davis-Besse Special Inspection for Resident Inspections Inspection Report Numbers: Various, beginning with 03-02 Inspection Background and Objectives Due to the large amount of direct inspection resources expended by the resident staff to followup on activities directly related to Davis-Besse Oversight Panel issues, the Panel decided to develop a means to allow for better documentation and tracking of direct inspection effort spent by the resident staff during evaluation of these issues, not specifically covered by baseline inspection procedures or other special inspections. The objective of this ongoing special inspection is to evaluate and document specific issues directly related to Davis-Besse restart issues not specifically covered by baseline inspection modules.

Inspection Dates The results of inspection activities, per this inspection plan, will be documented in the routine resident inspection reports. The inspection plan will be effective beginning with Inspection Report 50-346/03-02 and remain in effect for future routine resident inspection reports until the dissolution of the Davis-Besse Oversight Panel.

Inspection Procedure IP 93812 Special Inspection. This procedure implements the requirements for Special Inspection (SI) responses to operational events at power reactor licensee facilities. The IPE code to use is ER.

Prepared by: ____/RA DPassehl Acting for/ __ __

S. Thomas, Senior Resident Inspector Reviewed by: _ /RA DPassehl Acting for/ _____

C. Lipa, Chief Branch 4, Division of Reactor Project Approved by: _____/RA/ ___________________ _

J. Grobe, Chairman Davis-Besse Oversight Panel

INSPECTION PLAN DETAILS I Inspectors:

Davis-Besse Resident Inspection Staff and other inspectors supporting the resident office.

II Inspection Schedule:

The results of inspection activities, per this inspection plan, will be documented in the routine resident inspection reports. The inspection plan will be effective beginning with Inspection Report 50-346/03-02 and remain in effect for future routine resident inspection reports until determined by the Davis-Besse Oversight Panel.

III. Specific Inspection Activities:

The objective of this ongoing Special Inspection is to evaluate and document specific issues directly related to Davis-Besse restart issues not specifically covered by baseline inspection procedures or other existing procedures. The inspectors will perform inspections, as required, to adequately assess licensee performance and readiness for restart, in the following areas:

  • Inspecting the performance of plant activities, including maintenance activities;
  • Followup of specific Oversight Panel technical issues;
  • Attend and assess selected licensee restart readiness meeting;
  • Evaluate licensee performance in categorizing, classifying, and correcting deficient plant conditions during the restart process;
  • Review licensee controls, criteria, and assess licensee performance at meetings associated with adding work items to the back log, including deferral of work orders, work arounds, temp mods, and permanent mods; and
  • Review activities associated with safety conscious work environment and safety culture.

The inspectors will utilize IMC 0609, Significance Determination Process, to evaluate the risk significance of inspection findings. Preliminary findings, including green or above as determined by the Significance Determination Process will be discussed with NRC managers and with licensee managers at the applicable exit meeting.