|
---|
Category:Inspection Report
MONTHYEARIR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 IR 05000263/20244012024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20230022023-08-0707 August 2023 Plantintegrated Inspection Report 05000263/2023002 IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 IR 05000263/20230012023-05-0404 May 2023 Integrated Inspection Report 05000263/2023001 IR 05000263/20234012023-05-0404 May 2023 Security Baseline Inspection Report 05000263/2023401 IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) IR 05000263/20220042023-01-17017 January 2023 Integrated Inspection Report 05000263/2022004 IR 05000263/20220122022-12-15015 December 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000263/2022012 IR 05000263/20220132022-11-21021 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000263/2022013 IR 05000263/20223012022-11-21021 November 2022 NRC Initial License Examination Report 05000263/2022301 IR 05000263/20220032022-11-17017 November 2022 Reissue - Monticello Nuclear Generating Plant - Integrated Inspection Report 05000263/2022003 ML22307A1822022-11-14014 November 2022 Integrated Inspection Report 05000263/2022003 IR 05000263/20224032022-10-19019 October 2022 Security Baseline Inspection Report 05000263/2022403 (Public) IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20220022022-07-28028 July 2022 Integrated Inspection Report 05000263/2022002 IR 05000263/20220012022-05-10010 May 2022 Generation Plant - Integrated Inspection Report 05000263/2022001 IR 05000263/20224022022-05-0505 May 2022 Security Baseline Inspection Report 05000263/2022402; Independent Spent Fuel Storage Installation Security Inspection Report 07200058/2022401 IR 05000263/20224012022-03-28028 March 2022 Generation Plant - Cyber Security Inspection Report 05000263/2022401 IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) IR 05000263/20210042022-01-28028 January 2022 Integrated Inspection Report 05000263/2021004 and 07200058/2021001 IR 05000263/20214022021-12-16016 December 2021 Triennial Material Control and Accounting Report 05000263/2021402 IR 05000263/20214202021-11-15015 November 2021 Security Baseline Inspection Report Cover Letter 05000263 2021420 IR 05000263/20210032021-10-27027 October 2021 Plan, Integrated Inspection Report 05000263/2021003 IR 05000263/20210102021-10-0808 October 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000263/2021010 IR 05000263/20210112021-09-29029 September 2021 Plan - Temporary Instruction 2515/194 Inspection; Ibspection Report 05000263/2021011 IR 05000263/20215012021-09-0101 September 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000263/2021501 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) IR 05000263/20210022021-08-0303 August 2021 Integrated Inspection Report 05000263/2021002 IR 05000263/20210012021-04-30030 April 2021 Integrated Inspection Report 05000263/2021001 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) IR 05000263/20200102021-03-0202 March 2021 Reissue - Monticello Nuclear Generating Plant - Biennial Problem Identification and Resolution Inspection Report 05000263/2020010 IR 05000263/20200042021-01-20020 January 2021 Integrated Inspection Report 05000263/2020004 ML21013A4222021-01-13013 January 2021 Biennial Problem Identification and Resolution Inspection Report 05000263/2020010 IR 05000263/20203012020-12-0909 December 2020 NRC Initial License Examination Report 05000263/2020301 IR 05000263/20204022020-12-0303 December 2020 Security Baseline Inspection Report 05000263/2020402 (Cover Letter Only) IR 05000263/20200152020-11-0909 November 2020 NRC Inspection Report 05000263/2020015 IR 05000263/20200032020-11-0909 November 2020 Integrated Inspection Report 05000263/2020003 IR 05000263/20200132020-10-13013 October 2020 Design Basis Assurance Inspection (Programs) Inspection Report 05000263/2020013 IR 05000263/20204012020-09-22022 September 2020 Security Baseline Inspection Report 05000263/2020401 (Cover Letter Only) IR 05000263/20200052020-09-0101 September 2020 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2020005) IR 05000263/20200022020-08-0303 August 2020 Integrated Inspection Report 05000263/2020002 IR 05000263/20200142020-06-30030 June 2020 License Renewal Phase IV Report 05000263/2020014 IR 05000263/20200122020-05-26026 May 2020 Inspection of the Implementation of EA-13-09: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Report 05000263/2020012 IR 05000263/20200012020-05-0404 May 2020 Integrated Inspection Report 05000263/2020001 IR 05000263/20200112020-03-31031 March 2020 Triennial Fire Protection Inspection Report 05000263/2020011 2024-01-31
[Table view] Category:Letter
MONTHYEARML24025A9362024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0055 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000263/20230042024-01-31031 January 2024 Integrated Inspection Report 05000263/2023004 ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20244012024-01-22022 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2024401 L-MT-23-054, Subsequent License Renewal Application Supplement 82024-01-11011 January 2024 Subsequent License Renewal Application Supplement 8 L-MT-23-047, License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data2023-12-29029 December 2023 License Amendment Request: Revision to the MNGP Pressure Temperature Limits Report to Change the Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data L-MT-23-056, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 22023-12-18018 December 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 Part 2 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota IR 05000263/20234022023-12-13013 December 2023 Security Baseline Inspection Report 05000263/2023402 L-MT-23-042, 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462023-12-11011 December 2023 2023 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 L-MT-23-052, Subsequent License Renewal Application Supplement 72023-11-30030 November 2023 Subsequent License Renewal Application Supplement 7 L-MT-23-051, Update to the Technical Specification Bases2023-11-28028 November 2023 Update to the Technical Specification Bases L-MT-23-049, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 12023-11-21021 November 2023 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information - Set 1 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000263/20230032023-11-13013 November 2023 Integrated Inspection Report 05000263/2023003 and 07200058/2023001 L-MT-23-043, 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-092023-11-13013 November 2023 10 CFR 50.55a(z)(1) Request Regarding OMN-17, Revision 1. VR-09 L-MT-23-038, License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.62023-11-10010 November 2023 License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 L-MT-23-046, Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 12023-11-0909 November 2023 Subsequent License Renewal Application Response to Request for Additional Information Round 2 - Set 1 ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant L-MT-23-041, Subsequent License Renewal Application Response to Request for Confirmation of Information Set 22023-10-0303 October 2023 Subsequent License Renewal Application Response to Request for Confirmation of Information Set 2 L-MT-23-037, Subsequent License Renewal Application Response to Request for Additional Information Set 32023-09-22022 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 3 ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23248A2092023-09-18018 September 2023 Proposed Alternative VR-11 to the Requirements of the ASME OM Code Associated with Periodic Verification Testing of MO-2397, Reactor Water Cleanup Inboard Isolation Valve ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection IR 05000263/20230102023-09-0707 September 2023 Commercial Grade Dedication Inspection Report 05000263/2023010 L-MT-23-036, Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 62023-09-0505 September 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 2 and Supplement 6 ML23214A2412023-08-31031 August 2023 Letter: Aging Management Audit - Monticello Unit 1 - Subsequent License Renewal Application IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) L-MT-23-035, Subsequent License Renewal Application Supplement 52023-08-28028 August 2023 Subsequent License Renewal Application Supplement 5 ML23241A9732023-08-21021 August 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application (Docket No. 50-263) L-MT-23-034, Subsequent License Renewal Application Response to Request for Additional Information Set 12023-08-15015 August 2023 Subsequent License Renewal Application Response to Request for Additional Information Set 1 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence ML23215A1312023-08-0909 August 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000263/20230022023-08-0707 August 2023 Plantintegrated Inspection Report 05000263/2023002 L-MT-23-028, 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report2023-07-31031 July 2023 2023 Refueling Outage 90-Day Inservice Inspection (ISI) Summary Report L-MT-23-032, 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-112023-07-31031 July 2023 10 CFR 50.55a(z)(2) Request Regarding MO-2397, VR-11 ML23198A0412023-07-28028 July 2023 LRA Availability Letter ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) L-MT-23-031, Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 12023-07-18018 July 2023 Subsequent License Renewal Application Supplement 4 and Responses to Request for Confirmation of Information - Set 1 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan IR 05000263/20235012023-07-13013 July 2023 Emergency Preparedness Inspection Report 05000263/2023501 2024-01-31
[Table view] |
Text
March 27, 2003 Mr. D. Wilson Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 755 Monticello, MN 55362-9637
SUBJECT:
INFORMATION REQUEST TO SUPPORT NOVEMBER PROBLEM IDENTIFICATION AND RESOLUTION (PI&R) INSPECTION
Dear Mr. Wilson:
This letter is to provide you with advanced information regarding materials needed to support our November 2003 PI&R inspection. We will schedule a pre-inspection site visit to review the requested material and identify those areas where more detailed information will be needed.
If you have any questions regarding our schedule or the material being requested, please contact me at (630) 829-9629.
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket No. 50-263 License No. DPR-22
Enclosure:
Requested Information to Support PI&R Inspection See Attached Distribution
DOCUMENT NAME: C:\ORPCheckout\FileNET\ML030870109.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII NAME GWright/trn BBurgess DATE 03/27/03 03/27/03 OFFICIAL RECORD COPY
D. Wilson cc w/encl: J. Purkis, Plant Manager J. Cowan, Chief Nuclear Officer J. Forbes, Senior Vice President D. Neve, Manager, Regulatory Affairs J. Rogoff, Esquire General Counsel W. Brunetti, President and CEO Xcel Energy Inc.
Nuclear Asset Manager Site Licensing Manager Commissioner, Minnesota Department of Health J. Silberg, Esquire Shaw, Pittman, Potts, and Trowbridge R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA)
Commissioner, Minnesota Pollution Control Agency D. Gruber, Auditor, Wright County Board of Commissioners Commissioner, Minnesota Department of Commerce G. Wilson, Commissioner of Commerce P. Marker, Office of Attorney General C. Bomberger, Nuclear Asset Manager
D. Wilson ADAMS Distribution:
WDR DFT SXM1 DSH RidsNrrDipmIipb GEG HBC SXB3 C. Ariano (hard copy)
DRPIII DRSIII PLB1 JRK1
Requested Information to Support Problem Identification and Resolution (PI&R)
Inspection
- 1. A copy of administrative procedure(s) for the corrective action process, trending program, quality assurance audit program, self-assessment program, corrective action effectiveness review program, and industry experience review program.
- 2. A copy of Quality Assurance audits and/or self-assessments of the corrective action program completed since November 2001.
- 3. A copy of the QA manual.
- 4. A copy of the Employee Concerns Program/Ombudsman administrative procedure.
- 5. A list of Quality Assurance audits completed since November 2001 with brief description of areas where findings were identified.
- 6. A list of self-assessments completed since November 2001.
- 7. A list of root cause evaluations completed since November 2001.
- 8. A list of test failures (IST or Technical Specification surveillances) since November 2001, with a brief description of component/system which failed.
- 9. A list of all open condition reports sorted by significance level. Include a description of the issue and the significance category.
- 10. A list of condition reports closed since November 2001 including a description, significance category, date initiated, date closed, and whether there is an associated operability evaluation.
- 11. A list of condition reports initiated since November 2001 that involve inadequate or ineffective corrective actions. Include a brief description, status, and significance category of the issue.
- 12. A list of condition reports initiated since November 2001 that identify trends of conditions adverse to quality. Include a brief description, status, and significance category for each item.
- 13. A copy of any performance indicator reports used to track the corrective action program effectiveness.
- 14. A list of condition reports issued during the past 3 refueling outages sorted by system and component, including a brief description, status, and significant category for each item.