February 2003 Monthly Operating Report for Palo Verde, Units 1, 2 and 3
ML030790339
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 03/12/2003
From: Danni Smith
Arizona Public Service Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
219-02842-DMS/JMM
Download: ML030790339 (5)


Text

LAM A subsiluary of Pinnacle West Capital Corporation David M. Smith Operations Director Palo Verde Nuclear Generating Station Tel. 602-393-2656 Fax 602-393-1806 e-mail David M Smith(@apsc.com Mail Station 7294 PO Box 52034 Phoenix, Arizona 85072-2034 March 12, 2003 219-02842-DMS/JMM U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, DC 20555

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528/5291530 Monthly Operating Reports for FEBRUARY 2003 Enclosed are the Monthly Operating Reports for FEBRUARY 2003, prepared and submitted pursuant to Specification 5.6.4 of Appendix A, (Technical Specifications) to the PVNGS Units 1, 2, and 3 Operating Licenses.

By copy of this letter, Arizona Public Service Company is also forwarding the Monthly Operating Reports to the Regional Administrator, NRC Region IV and the NRC Resident Inspector.

If you have any questions, please contact Judy Mellody at (623) 393-6422.

Sincerely, 4,

DMS/JMM/mb

/.*f L-(-

Enclosures:

FEBRUARY 2003 Monthly Operating Reports cc:

E. W. Merschoff PVNGS Resident Inspector INPO Records Center Utility Data Institute (all w/enclosures)

Page Two NRC Monthly Operating Report Distribution List 219-02842-DMS/JMM February 13, 2003 bcc:

J. E. Orsborn D. M. Smith M. Van Dop J.

Simpkins D. L. Sills G. R. Overbeck File Copy C. D. Mauldin M. K. Banks C. R. Emmett D. G. Marks C. K. Seaman B. J. Hansen C. L. Jury J. E. McDonald S. M. Foote J. M. Levine W. L. Stewart (3146) (all w/enclosures)

(7294)

(7512)

(7512)

(7565)

(7602)

(7602)

(7605)

(7615)

(7615)

(7636)

(7636)

(7693)

(8983)

(8508)

(8508)

(9046)

(9082)

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-528 PVNGS-1 03111/03 J. M. Mellody (623) 393-6422 Reporting Period:

February 2003

1.

Design Electrical Rating (Net MWe):

1265

2.

Maximum Dependable Capacity (Net MWe):

1243 Unit I Generating Statistics This Month Yr. to Date Cumulative

3.

Hours Reactor was Critical 672.0 1,416.0 115,577.2

4.

Hours Generator was On-Line 672.0 1,416.0 114,199.4

5.

Unit Reserve Shutdown Hours 0.0 0.0 0.0

6.

Net Electrical Energy Generated (MWh) 832,620 1,754,904 137,423,488 UNIT SHUTDOWNS Outage Duration Method of Shutting Down No.

Date TypeI Hours Reason2 Rea4 No reactor shutdowns occurred during the month of February 2003.

ctor3 Cause and Corrective Action to Prevent Occurrence 2 Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

1F-Forced S-Scheduled

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-529 PVNGS-2 03111/03 J. M. Mellody (623) 393-6422 Reporting Period:

February 2003

1.

Design Electrical Rating (Net MWe):

1265

2.

Maximum Dependable Capacity (Net MWe):

'1243 Unit 2 Generating Statistics This Month Yr. To Date Cumulative

3.

Hours Reactor was Critical 672.0 1,416.0 115,327.5

4.

Hours Generator was On-Line 672.0 1,416.0 113,995.6

5.

Unit Reserve Shutdown Hours 0.0 0.0 0.0

6.

Net Electrical Energy Generated (MWh) 854,679 1,801,169 138,744,850 UNIT SHUTDOWNS Outage Duration Method of Shutting Down No.

Date Type 1 Hours Reason 2 Rea No reactor shutdowns occurred during the month of February 2003.

ctor 3 Cause and Corrective Action to Prevent Occurrence 2Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1-Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

1F-Forced S-Scheduled

NRC MONTHLY OPERATING DATA REPORT DOCKET NO.:

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

50-530 PVNGS-3 03/11/03 J. M. Mellody (623) 393-6422 Reporting Period:

February 2003

1.

Design Electrical Rating (Net MWe):

1269

2.

Maximum Dependable Capacity (Net MWe):

1247 Unit 3 Generating Statistics This Month Yr. to Date Cumulative

3.

Hours Reactor was Critical 672.0 1,416.0 111,599.7

4.

Hours Generator was On-Line 672.0 1,416.0 110,611.9

5.

Unit Reserve Shutdown Hours 0.0 0.0 0.0

6.

Net Electrical Energy Generated (MWh) 858,112 1,808,766 135,315,925 UNIT SHUTDOWNS Reason 2 Method of Shutting Down Reactor 3 Cause and Corrective Action to Prevent Occurrence No reactor shutdowns occurred during the month of February 2003.

2Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training / License Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain) 3Method:

1 -Manual 2-Manual Trip / Scram 3-Automatic Trip / Scram 4-Continuation 5-Other-(Explain)

SUMMARY

No.

Date Outage Duration Hours TypeI 1F-Forced S-Scheduled