Letter Sequence Other |
---|
|
|
MONTHYEARML0226704222002-09-23023 September 2002 Summary of Telecon Regarding Steam Generator Inspection Results Project stage: Request ML0303500822003-02-0404 February 2003 (BVPS-1) - Upcoming Steam Generator Tube Inservice Inspection Project stage: Other ML0307700522003-03-18018 March 2003 Questions Faxed to the Licensee Beaver Valley Unit 1 (BVPS) Pre-Outage Steam Generator Conference Call Project stage: Other ML0315501962003-06-0404 June 2003 (BVOS-1 and 2), Request for Additional Information, Steam Generator Tube 2001-2002 Outages Inspection Report (TAC Nos. MB7010 and MB7011) and 1R15 Steam Generator Outage Summary Call Project stage: RAI ML0317100652003-06-20020 June 2003 (BVPS-1) Issuance of Steam Generator Conference Call Summary. Project stage: Approval ML0317404152003-06-20020 June 2003 Enclosure 2 - BVPS 1R15 - NRC Outage Phone Call Project stage: Other 2003-03-18
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML22019A2652022-01-27027 January 2022 Us NRC Staff Review of Documentation Provided by Firstenergy Nuclear Operating Co. for Beaver Valley, Units 1&2 Concerning Resolution of Generic Letter 2004-02 - Potential Impact of Debris Blockage on Emergency Recirculation During Design B ML20080J7892020-04-28028 April 2020 Relief Requests 2 TYP-3-B3.110-1, 2-TYP-3-C2.21-1, 2-TYP-3-C1.30-1, and 2-TYP-3-RA-1 Regarding Weld Examination Coverage for the Third Inservice Inspection Interval ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML19085A5132019-04-0101 April 2019 Review of Updated Final Safety Analysis Report, Revision 23 ML18099A0812018-04-0606 April 2018 Bv Annual Assessment Meeting Summary and Attendance List 2018 ML18067A1132018-03-0909 March 2018 Notice of Public Meeting on March 27, 2018 ML17061A2072017-03-0707 March 2017 Notice of Meeting with Firstenergy Nuclear Operating Co., to Discuss Nrc'S Assessment of Safety Performance at Beaver Valley Power Station, Units 1 and 2 for 2016 as Described in the Annual Assessment Letter Dated March 01, 2017 ML16224A7652016-10-20020 October 2016 Review of Updated Final Safety Analysis Report, Revision 22 ML15201A4812015-07-20020 July 2015 Notice of Forthcoming Closed Meeting to Discuss Basin-Wide Probable Maximum Flood Analysis for Beaver Valley Power Station, Units 1 and 2 ML15182A1912015-07-16016 July 2015 Annual Financial Test for a Parent Company Guarantee Given by Firstenergy Solutions Corporation and Firstenergy Corporation ML15135A2982015-05-21021 May 2015 Summary of April 28, 2015, Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station, ML15110A4062015-04-23023 April 2015 Notice of Closed Meeting with FENOC on Beaver Valley ML15016A4392015-01-20020 January 2015 Draft Request for Additional Information ML14195A0742014-07-14014 July 2014 Memoranda to S. Wastler Technical Assistance Request - Review of Physical Security Plan for the Beaver Valley Power Station (TAC No. L24936) IR 05000334/20004122014-07-0808 July 2014 NRC Staff'S Spot-Check Review of First Energy Nuclear Operating Company'S Ownership Interest in Beaver Valley, Units 1 and 2, Perry, and Davis-Besse, Docket No. 05000334, 05000412, 05000440, and 05000346, on June 10, 2014-Finding of No Pote ML14189A1212014-07-0808 July 2014 NRC Staff'S Spot-Check Review of Ohio Edison'S Ownership Interest in Beaver Valley, Unit 2 and Perry, Finding of No Potential Issues ML14189A1192014-07-0808 July 2014 NRC Staff'S Toledo Edison Spot-Check Review of Toledo Edison Company'S Ownership Interest in Beaver Valley Nuclear Power Station, Unit 2, Docket No. 50000412, on June 10, 2014-Finding of No Potential Issues ML14161A1482014-06-17017 June 2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Beaver Valley Power Station, Units 1 and 2 ML13186A0382013-07-0808 July 2013 Electronic Transmission, Draft Request for Additional Information Regarding the 2013 Decommissioning Funding Status Report ML13179A3182013-07-0101 July 2013 Electronic Transmission, Draft Request for Additional Information Regarding 2012 Steam Generator Tube Inspection Reports ML13154A4392013-06-0404 June 2013 Rai'S Following Ifib Analysis of Fenoc'S 2013 Decommissioning Funding Status Report for Beaver Valley 1 and 2 ML12265A2032012-10-0202 October 2012 Notice of Meeting with First Energy Nuclear Operating Company, to Discuss Upcoming License Amendment Request Relating to the Implementation of the Alternate Pressurized Thermal Shock Rule ML12263A4202012-09-20020 September 2012 Electronic Transmission, Draft Request for Additional Information Regarding Revision of Regulatory Commitment for Submittal of 10 CFR 50.48(c) License Amendment Request ML12207A5672012-07-26026 July 2012 Electronic Transmission, Draft Request for Additional Information Regarding Proposed Emergency Action Level Scheme Change Using Nuclear Energy Institute 99-01, Revision 5 ML12194A5622012-07-16016 July 2012 Notice of Forthcoming Pre-Submittal Meeting with Firstenergy Nuclear Operating Company, to Discuss Upcoming Beaver Valley Power Station National Fire Protection Association Standard 805 (NFPA 805) Submittal ML12158A4002012-06-0808 June 2012 6/26/2012 Forthcoming Meeting Firstenergy Nuclear Operating Company (FENOC) ML12123A7032012-05-17017 May 2012 Safety Evaluation by the Office of Nuclear Reactor Regulation Annual Financial Test for a Parent Company Guarantee Firstenergy Nuclear Operating Company Beaver Valley Power Station, Unit 1; Docket No. DPR-66 and Perry Nuclear Power Plant ML1014105172010-05-21021 May 2010 Summary of the May 2010 Annual Assessment Open-House Public Meeting ML1008407562010-03-31031 March 2010 Notice of Teleconference Meeting with Firstenergy Nuclear Operating Company Regarding Mutual Understanding of NRR Staff'S Request for Additional Information and to Discuss Generic Letter 2004-02 ML0932102822009-11-17017 November 2009 Verbal Authorization of Relief Request ML0926704712009-09-22022 September 2009 G20090544/EDATS: OEDO-2009-0574 - Edwin M. Hackett Memo, Letter from Citizen Power (Theodore S. Robinson) Concerning the License Renewal for the Beaver Valley Power Station ML0925200672009-09-0909 September 2009 Docketing of NRC Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 and 2 ML0925102262009-09-0808 September 2009 Docketing of U.S. Nuclear Regulatory Commission Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 & 2 ML0925102602009-09-0808 September 2009 Docketing of U.S. Nuclear Regulatory Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 and 2 ML0921800382009-08-0606 August 2009 Docketing of NRC Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 and 2 ML0920405122009-07-21021 July 2009 G20090418/EDATS: OEDO-2009-0458 - Edwin M. Hackett Memo, Letter from Citizen Power and Beyond Nuclear Concerning the License Renewal for the Beaver Valley Power Station ML0915602002009-06-0808 June 2009 Docketing of NRC Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 and 2 ML0914001662009-05-20020 May 2009 Docketing of NRC Teleconference Notes Pertaining to the License Renewal of the Beaver Valley Power Station, Units 1 and 2 ML0835003252009-01-21021 January 2009 Summary of Telephone Conf Call Held on Sept. 26, 2008 Between NRC and Firstenergy Nuclear Operating Company Concerning the RAI Pertaining to the Refurbishment Activities at the Bvps. Units 1&2 LRA ML0832504202008-12-19019 December 2008 Summary of Telephone Conference Call Held on 11/17/08, Between the NRC and FENOC, Concerning Requests for Additional Information Pertaining to the Beaver Valley Power Station, Units 1 and 2, LRA ML0833100872008-11-26026 November 2008 Forthcoming Meeting with Firstenergy Nuclear Operating Company (Fenoc), Beaver Valley Power Station, Unit No. 2. the Current Title in the Profile Is the Title to Another Document Not This on So Please Remove and Replace ML0830102492008-11-13013 November 2008 Summary of Telephone Conference Call Held on 10/8/08, Between the NRC and Firstenergy Nuclear Operating Company, Concerning Open Items Pertaining to the BVPS, Units 1 and 2, License Renewal SER ML0830202902008-11-13013 November 2008 Summary of Telephone Conference Call Held on 8/28/08, Between the NRC and FENOC, Concerning RAI Pertaining to the BVPS, Units 1 and 2, LRA ML0829107022008-10-20020 October 2008 10/30/08 Notice of Meeting to Discuss the Draft Supplemental Environmental Impact Statement for License Renewal of Beaver Valley, Units 1 and 2 ML0807301162008-03-21021 March 2008 Summary of Conference Call Between Us Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning the Impact of Table 8.0-1 Error on the Beaver Valley Severe Accident Mitigation Alternatives Request for Additional In ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0731005762007-11-0808 November 2007 11/27/2007 Notice of Meeting to Discuss the Safety Review Process and Environmental Scoping Process for Beaver Valley Power Station, Units 1 and 2, License Renewal Application Review ML0717103462007-06-21021 June 2007 Revised Notice of Meeting with Firstenergy to Discuss Response to Nrc'S 05/14/2007, Demand for Information Regarding Fenoc'S Re-analysis of the Timeline and Root Causes for the 2002 Davis-Besse Reactor Pressure Vessel Head Degradation Event ML0716202122007-06-13013 June 2007 Notice of Meeting with Firstenergy Regarding May 14, 2007 Demand for Information Davis-Besse ML0631104002006-11-0909 November 2006 Notice of Closed Meeting Between Fenco Security and NSIR to Discuss Fenco Fleet Security Matters 2022-01-27
[Table view] |
Text
March 18, 2003 MEMORANDUM TO: Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Timothy G. Colburn, Senior Project Manager, Section 1 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
QUESTIONS FAXED TO THE LICENSEE RE: BEAVER VALLEY POWER STATION, UNIT 1 (BVPS 1) PRE-OUTAGE STEAM GENERATOR CONFERENCE CALL (TAC NO. MB7271)
The attached questions have been faxed to the BVPS 1 licensee regarding the NRC staffs requested steam generator pre-outage telephone call. These questions were discussed with the licensee during a conference call held on March 5, 2003.
Docket No. 50-334
Attachment:
As stated
March 18, 2003 MEMORANDUM TO: Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Timothy G. Colburn, Senior Project Manager, Section 1 /RA/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
QUESTIONS FAXED TO THE LICENSEE RE: BEAVER VALLEY POWER STATION, UNIT 1 (BVPS 1) PRE-OUTAGE STEAM GENERATOR CONFERENCE CALL (TAC NO. MB7271)
The attached questions have been faxed to the BVPS 1 licensee regarding the NRC staffs requested steam generator pre-outage telephone call. These questions were discussed with the licensee during a conference call held on March 5, 2003.
Docket No. 50-334
Attachment:
As stated DISTRIBUTION:
PUBLIC PDI-1 Reading RLaufer MOBrien TColburn Accession Number: ML030770052 OFFICE PDI-1/PM PDI-1/LA PDI-1/SC NAME TColburn MOBrien RLaufer DATE 3/5/03 3/6/03 3/11/03 OFFICIAL RECORD COPY
QUESTIONS FOR BEAVER VALLEY POWER STATION, UNIT 1 PRE-OUTAGE STEAM GENERATOR CALL (TAC NO. MB7271)
Based on the recent findings at Diablo Canyon (circumferential cracking in the U-bend areas of higher row tubes; i.e., rows >4), the NRC staff would like to have a pre-outage call with the Beaver Valley Power Station (BVPS) licensee to:
- 1. Make sure the licensee is aware of the findings at Diablo Canyon.
- 2. Discuss the licensees plans to address this concern for the upcoming BVPS, Unit 1 outage early next month.
- 3. Discuss the implications of the Diablo Canyon findings on BVPS and, if there are none, to discuss why not.
It would also be helpful to know if BVPS, Unit 1 or BVPS Unit 2 has any operational primary-to-secondary leakage - and if so, how much.
Attachment