Review of 2002

  • May 2002 Meeting with NRR

+ Review of Unit 2 Cycle 11

  • CENTS Implementation
  • Clad Performance Strategy
  • CEA Investigation
  • Dry Cask Storage Update 2

I

Agenda Today

  • Reactivity Management
  • CENTS & RSG/Power Uprate
  • Fuel Performance
  • CPC Replacement

+ CEA Replacement

+ Dry Cask Storage Update Reactivity Management

+ Overview of INPO AFI

+ Palo Verde Actions

  1. Results 2

Overview

+ INPO Identified

  • 2001 Plant Evaluation

- Reactivity Management AFI

"*REACTOR ENGINEERING

"*OPERATIONS 5

a M-ý LJkIýL Palo Verde Actions

+ NFM/Operations/Training Interface

+ Operations Single Point of Contact

+ Xenon Program

  • Maneuvering Box
  • Procedure Enhancement

+ Training 6

3

Results

  • NO REACTIVITY EVENTS
  • Standardized Game Plans
  • Improved Inter-Departmental Relationships
  • Improved Tools CENTS, RSG, U2 Uprate
  • CENTS Implementation Status

CENTS Implementation Status

+ U1, U2 Complete - U3 April 2003

+ SABD Revision 20% Complete

+ Two Events Await U2 SER

- SGTR + LOP + SF

- Long Term FWLB (PSV Operability)

U2 RSG & Power Uprate

  • Draft SER 3131 -- Final SER 6130
  • SABD Supplement In Progress
  • U2C12 Reload Safety Analyses Begun
  1. Actively Participating in Development of SG Startup Test Program 10 5

Fuel Performance

  • Integrated Fuel Clad Strategy:

- Advanced Clad Alloys

- Primary Chemistry

- CRUD/Oxide Software

- Low Duty Core Designs

+ Long Range Fuel Inspection Plan N'I Advanced Clad Alloys

  • Westinghouse Decision: Low Tin Zirlo

- Alloy A LTA in U3C1O (Spring 2003)

  1. First Batches of Standard Zirlo &

Columbia Fuel Rod

- U2Cll, UICll (2002)

- U3ClI In April 2003

+ Fuel Handling Accident Rod Pressure 12 \

  • 6

Primary Chemistry

+ Additional RCS Cleaning at EOC Shutdown

+ Early Lithium Injection During Startups

+ Elevated-Coordinated Lithium Strategy

- Currently 7.1 pH

- Hold Until Inconel Corrosion Issue Resolved CRUD/Oxide Software

+ Steaming Rate in Core Design Tools

- Screen Patterns Against U3C9 Benchmark

+ APS CRUD/Oxide Model

- Nodal Level/High Duty Ass'y Rod Level

+ Vendor Fuel Duty Model

- Safety Grade Oxide and FDI Calculations 7

Low Duty Core Designs

+ Increase Feed Batch Size

- 104 vs 96 Assemblies

  • Minimal Feed-Face-Feed

- UlCIO Visuals of P1M316

  • U2 Uprate Corrosion Strategy

- Zirlo Clad

- Re-design Lattice Pattern IU, Re-Designed Lattice

+ Current Lattice

- 2 Enrichments

- 12 High Enrichment Rods on Each Face

+ New Lattice

- 3 Enrichments

- Same Assembly Average Enrichment

- All Peripheral Rods Low Enrichment

+ Extensive Design Review 16 8

Long Range Fuel Inspection Plan

+ Unit 2, Beginning Fall 2003

  1. Zirlo Oxidation (R11, R12, R13)

+ Lithium 3.5 PPM (R11, R12)

  • New Lattice (R12, R13)
  • Assembly Bow (R11)
  • Higher Burnup Leakers CPC Replacement
  • Overview of Changes
  • Licensing Schedule 9

CPC Replacement Overview

+ Upgrade to Modern Hardware

- 8 CEA Calculators

  • Concurrent Software Language Change
  • Preserve Original Functionality & Timing

+ First Installation - Fall 2003 Outage 19 CPC Replacement Licensing

  • SER on Westinghouse Common-Q

+ Schedule for Formal RA! on PVNGS

  • U2C12 Reload Engineering

- No Impact to Safety &Uncertainty Analyses

  • PVNGS Supports Joint Meeting 20 10

CEA Replacement

  • Review CEA History
  • Determination of New, Conservative Lifetime i
  • Design of New Replacement CEAs

+ Replacement of PLCEAs Review of CEA History

  • CEA Finger Failures Observed - 2001

- Cracks in High Fluence CEA Tips

- Root Cause - IASCC, Inadequate Testing

- U21U3 With Small Pellet Less Severe

+ All Full Length CEAs Replaced

- Replaced by Design with Smallest Pellet

+ Lifetime Software Abandoned 22 1I

Determination of New Lifetime

  • Investigating Various Options

+ Monitoring YGN Inspections

. Vendor Has Adjusted Software 23 Design of New CEAs

+ Now: Unique Feltmetal Design

+ Want: Industry Standard AgInCd Tips

+ Tip Region Extended 4 Inches

  • Hollow AgInCd Slugs 24, 12

Replacement of PLCEAs

  • Original Equipment

- Part Length, Part Strength

- Not Subject to Same Failure Mode

- Reviewing Design Bases

  • Replacements

- Full Length, Part Strength

- Transparent to Safety Analysis

- Tech Spec Change Required 25 Dry Cask Storage Update 26 13

Dry Cask Storage Update SCurrent status Unit 2

- Loaded 24 assemblies in first canister March 3

- Shield lid welded March 6

- Completed first vacuum drying period March 8

- March 10 will start 2nd vacuum drying period

.apturing lessons learned from first loading 26

Fuel Loading Schedule

  • Complete first canister loading in March, 2003
  • Time out for Unit 3 Refueling outage, ends early May, 2003
  • Complete Unit 2 campaign in June
  • Load 5 casks in Unit 1 later in 2003

+ Plan to load 10 casks per year 27

UMS Amendment 3

  • Palo Verde benefits

- Extended vacuum drying times

- Action statements won't require submersion of Transfer Cask and Canister for cooling

- Increased seismic limit

- Increased PWR fuel enrichment limit

+ Anticipate issuance early May 2003 28