March 10, 2003 Mr. Gregory M. Rueger Senior Vice President, Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant P.O. Box 3 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNIT NO. 2 - REVIEW OF EMERGENCY LICENSE AMENDMENT REQUEST REGARDING ALTERNATE METHOD OF DETERMINING PROBABILITY OF DETECTION FOR STEAM GENERATOR TUBE INDICATION (TAC NO. MB7875)
Dear Mr. Rueger:
By letter dated March 3, 2003 (DCL-03-026), and as supplemented on March 5, 2003 (DCL-03-027), you requested an emergency license amendment under 10 CFR 50.91(a)(5).
The proposed amendment would authorize revisions to the Final Safety Analysis Report (FSAR) Update to incorporate the NRC approval of a probability of detection (POD) of 1.0 for one bobbin indication contained in the Diablo Canyon Power Plant (DCPP), Unit 2 steam generator 4, tube at row 44, column 45, at the second tube support plate on the hot leg side (R44C45-2H), for the beginning-of-cycle voltage distribution for the DCPP Unit 2 Cycle 12 operational assessment.
In your application, you requested that the staff issue the amendment on an emergency basis before DCPP Unit 2 restart from the current refueling outage. Based upon our review of your application, we have concluded that the proposed amendment is not needed prior to restart of the plant, and therefore, does not meet the emergency requirements of 10 CFR 50.91(a)(5).
Therefore, the license amendment application will be processed as a normal license amendment request. If you have any questions, please contact me at (301) 415-8439.
Sincerely,
/RA/
Girija S. Shukla, Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-323 cc: See next page
- See previous concurrences NRR-106 OFFICE PDIV-2/PM PDIV-2/LA EMCB/SC OGC PDIV-2/SC NAME GShukla
- EPeyton
- LLund
- RWeisman JDonohew for SDembek DATE 3/10/03 3/10/03 3/10/03 10 March 2003 3/10/03 DOCUMENT NAME: G:\\PDIV-2\\DiabloCanyon\\Letter on Emergency S-G amendment.wpd
Diablo Canyon Power Plant, Units 1 and 2 cc:
NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P.O. Box 369 Avila Beach, CA 93424 Dr. Richard Ferguson, Energy Chair Sierra Club California 1100 11th Street, Suite 311 Sacramento, CA 95814 Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, CA 93448 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, CA 93408 Mr. Truman Burns Mr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Room 4102 San Francisco, CA 94102 Diablo Canyon Independent Safety Committee ATTN: Robert R. Wellington, Esq.
Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavillion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Christopher J. Warner, Esq.
Pacific Gas & Electric Company P.O. Box 7442 San Francisco, CA 94120 Mr. David H. Oatley, Vice President and General Manager Diablo Canyon Nuclear Power Plant P.O. Box 56 Avila Beach, CA 93424 City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, CA 93406-0112 Mr. Ed Bailey, Radiation Program Director Radiologic Health Branch State Department of Health Services P.O. Box 942732 (MS 178)
Sacramento, CA 94234-7320 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)
Sacramento, CA 95814 Mr. James R. Becker, Vice President Diablo Canyon Operations and Station Director Diablo Canyon Nuclear Power Plant P.O. Box 3 Avila Beach, CA 93424