Farley Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/04/2003 07:47:16 Report 22 1
EB2-ISI
- INSERVICE INSPECTION-U1 Baseline Inspections 04/07/2003 04/11/2003 Inservice Inspection Activities - PWR IP 7111108P 1
2 2515/150
- 2515/150 REV1 UNIT 1 Safety Issues 04/07/2003 04/11/2003 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 IP 2515/150 1
3 OL PREP
- INITIAL EXAM PREP Not Applicable 05/05/2003 05/09/2003 FARLEY/EXAMS AT POWER FACILITIES V23205 1
3 OL EXAM
- INITIAL EXAM Not Applicable 05/19/2003 05/27/2003 FARLEY/EXAMS AT POWER FACILITIES V23205 1
1 BR2-FP
- FLOOD PROTECTION Baseline Inspections 06/23/2003 06/26/2003 Flood Protection Measures IP 7111106 1, 2 1
- EP INSPECTION Baseline Inspections 08/04/2003 08/08/2003 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Performance Indicator Verification IP 71151 1, 2 4
EB2-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 08/11/2003 08/15/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 08/11/2003 08/15/2003 Permanent Plant Modifications IP 7111117B 1, 2 4
EB2-PIMR
- PI&R/MR Baseline Inspections 09/15/2003 09/19/2003 Maintenance Effectiveness IP 7111112B 1, 2 Baseline Inspections 09/15/2003 09/19/2003 Identification and Resolution of Problems IP 71152B 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Identification and Resolution of Problems IP 71152B 1, 2 1
PS-RP
- RADIATION PROTECTION @ ENV LAB Baseline Inspections 11/19/2003 11/21/2003 Radiological Environmental Monitoring Program IP 7112203 1, 2 3
PS-RP
- RADIATION PROTECTION Baseline Inspections 12/01/2003 12/05/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radiological Environmental Monitoring Program IP 7112203 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Performance Indicator Verification IP 71151 1, 2 2
EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 01/05/2004 01/09/2004 Safety System Design and Performance Capability IP 7111121 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Farley Inspection / Activity Plan 03/01/2003 - 03/31/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/04/2003 07:47:16 Report 22 5
EB1SSDPC - SAFETY SYS DESIGN & PERFORMANCE CAPABILI Baseline Inspections 01/26/2004 01/30/2004 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 02/09/2004 02/13/2004 Safety System Design and Performance Capability IP 7111121 1, 2 1
2515/150
- 2515/150 REV1 UNIT 2 Safety Issues 03/15/2004 03/19/2004 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 IP 2515/150 2
1 EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 03/15/2004 03/19/2004 Inservice Inspection Activities - PWR IP 7111108P 2
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.