January 2003 Monthly Operating Report for McGuire Nuclear Station Units 1 & 2
ML030550684
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 02/13/2003
From: Dimmery T
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML030550684 (9)


Text

Duke Energy Corporation P Duke 526 South Church Street 9 Energy. P.O. Box 1006 Charlotte, NC 28201-1006 February 13, 2003 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

Subject:

Duke Energy Corporation McGuire Nuclear Station, Units 1 and 2 Docket Numbers 50-369 and 50-370 Monthly Performance and Operation Status-January, 2003 Please find attached information concerning the performance and operation status of the McGuire Nuclear Station for the month of January, 2003.

Any questions or comments may be directed to Roger A. Williams at (704) 382-5346.

Sincerely, Terry Dimmey, Manager Nuclear Business Support Attachment XC:

L. A. Reyes, Regional Administrator USNRC, Region II Frank Rinaldi, Project Manager USNRC, ONRR INPO Records Center Ms. Margaret Aucoin Nuclear Assurance Corporation Dottie Sherman, ANI Library American Nuclear Insurers Scott Schaeffer, Senior Resident Inspector

Document Control Desk U.S. NRC - McGuire bxc:

C. J. Thomas (MG01RC)

RGC Site Licensing File ELL (EC050)

Operating Data Report Docket No. 50-369 Date February 13,2003 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: McGuire 1
2. Reporting Period: January 1, 2003 - January 31, 2003
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1180 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1144 MVA * .90 power factor per Page iii,
7. Maximum Dependable Capacity(Net MWe): 1100 NUREG-0020.
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 744.0 185568.0
12. Number of Hours Reactor was Critical 744.0 744.0 143769.5
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 744.0 142468.5
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2489866 8219177 465124432
17. Gross Electrical Energy Generated (MWH) 874432 874432 158377090
18. Net Electrical Energy Generated (MWH) 844406 844406 151760249
19. Unit Service Factor 100.0 100.0 76.8
20. Unit Availability Factor 1000 1000 76.8
21. Unit Capacity Factor (Using MDC Net) 103.2 103.2 72.1
22. Unit Capacity Factor (Using DER Net) 96.2 96.2 69.3
23. Unit Forced Outage Rate 0.0 0.0 9.3
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 2/13/2003

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-369 UNIT NAME: McGuire 1 DATE: February 13,2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: January. 2003 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C - 2/13/2003

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: McGuire Unit I
2. Scheduled next refueling shutdown: March 2004
3. Scheduled restart following refueling: April 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1107
8. Present licensed fuel pool capacity: 1463 Size of requested or planned increase: =
9. Projected date of last refueling which can be accommodated by present license capacity:

November 2005 DUKE POWER COMPANY DATE: February 13, 2003 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

Operating Data Report Docket No. 50-370 Date February 13,2003 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: McGuire 2
2. Reporting Period: January 1, 2003- January 31, 2003
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1180 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1144 MVA * .90 power factor per Page iii,
7. Maximum Dependable Capacity(Net MWe): 1100 NUREG-0020.
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 744.0 165864.0
12. Number of Hours Reactor was Critical 744.0 744.0 136530.8
13. Reactor Reserve Shutdown Hours 0.0 00 0.0
14. Hours Generator On-Line 744.0 7440 135277.0
15. Unit Reserve Shutdown Hours 0.0 0.0 00
16. Gross Thermal Energy Generated (MWH) 2463007 10682184 454870544
17. Gross Electrical Energy Generated (MWH) 863537 863537 155419642
18. Net Electrical Energy Generated (MWH) 832889 832889 149215683
19. Unit Service Factor 100.0 100.0 81.6
20. Unit Availability Factor 100.0 100.0 81.6
21. Unit Capacity Factor (Using MDC Net) 101.8 101.8 79.7
22. Unit Capacity Factor (Using DER Net) 94.9 94.9 76.2
23. Unit Forced Outage Rate 0.0 0.0 5.5
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 2/13/2003

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-370 UNIT NAME: McGuire 2 DATE: February 13, 2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: Januarv, 2003 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown RMX Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C - 2/13/2003

MONTHLY REFUELING INFORMATION RPQUEST

1. Facility name: McGuire Unit 2
2. Scheduled next refueling shutdown: September 2003
3. Scheduled restart following refueling: October 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1093 (c) in the ISFSI: 192
8. Present licensed fuel pool capacity: 1463 Size of requested or planned increase: =
9. Projected date of last refueling which can be accommodated by present license capacity:

June 2003 DUKE POWER COMPANY DATE: February 13, 2003 Name of

Contact:

R. A Williams Phone: (704) - 382-5346

McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT DECEMBER 2002

1. Personnel Exposure The total station liquid release for DECEMBER has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for DECEMBER has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.