Text

&

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGInIA 23261 January 28, 2003 United States Nuclear Regulatory Commission Serial No.:

03-085 Attention: Document Control Desk NLOS/RAB RO Washington, D.C. 20555 Docket Nos.:

50-280, 281 License Nos.: DPR-32, 37 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS I AND 2 CANCELLATION OF IMPROVED TECHNICAL SPECIFICATIONS PROJECT In an October 12, 2001 letter (Serial No.01-631), Virginia Electric and Power Company (Dominion) informed the NRC that we had decided to delay our conversion of the current Surry Power Station Technical Specifications to the Improved Standard Technical Specifications.

After evaluating the activities that are ongoing and planned for the next several years, Dominion does not expect to complete the Technical Specifications conversion project in the foreseeable future due to other more safety-significant projects, such as the reactor vessel head replacements and instrumentation upgrades. Therefore, Dominion has decided to cancel the project.

This decision was discussed with Mr. Robert Dennig of the NRC during a conference call on January 14, 2003.

If you have any questions, please contact us.

Very truly yours, David A. Christian Senior Vice President - Nuclear Operations and Chief Nuclear Officer Attachments Commitments made in this letter: None