WAT-RETAKE EXAM-07/2002- Comment ResolutionML030350127 |
Person / Time |
---|
Site: |
Waterford |
---|
Issue date: |
09/06/2002 |
---|
From: |
NRC Region 4 |
---|
To: |
|
---|
References |
---|
50-382/02-302 50-382/02-302 |
Download: ML030350127 (3) |
|
|
---|
Category:License-Operator
MONTHYEARIR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML22075A3442022-03-16016 March 2022 Response to Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22108A2662022-03-0909 March 2022 WAT-2022-02 Public Forms W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis ML21117A2932021-04-28028 April 2021 Notification of NRC Initial Operator Licensing Examination 05000382/2022301 ML21106A1512021-04-16016 April 2021 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations W3F1-2020-0056, 08 Post Exam Analysis2020-09-10010 September 2020 08 Post Exam Analysis ML20267A2132020-08-26026 August 2020 08 Final Operating Test ML20267A2062020-08-26026 August 2020 05000382/202008 Draft Outline Comments ML20267A2092020-08-26026 August 2020 08 Draft Operating Test.Pdf ML20267A2102020-08-26026 August 2020 08 Draft Operating Test Comments ML20267A2082020-08-26026 August 2020 08 Draft Written Exam Comments ES-401-9 ML20267A2072020-08-26026 August 2020 08 Draft Written Exam ML20267A2052020-08-26026 August 2020 08 Draft Outlines ML20267A2122020-08-26026 August 2020 Examination Inspection Report 05000382/2020008 Final Written Exam IR 05000382/20200082020-08-26026 August 2020 Examination Inspection Report 05000382/2020008 Final Outlines ML20294A1372020-08-26026 August 2020 08 Public Forms ML20307A1742020-08-10010 August 2020 08 Exam Approval Letter ML20219A292 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20307A1732020-01-0707 January 2020 05000382/2020008 Corporate Notification Letter ML20007E607 ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19011A3712019-01-10010 January 2019 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2019 ML18304A4862018-10-30030 October 2018 NRC Initial Operator Licensing Examination Approval 05000382/2018301 ML18089A0412018-03-29029 March 2018 Notification of NRC Initial Operator Licensing Examination 05000382/2018301 ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17122A0502017-04-10010 April 2017 2017-03 Post Exam Comments ML17122A0482017-04-0505 April 2017 2017-03 Final Written Examination ML17137A1862017-04-0505 April 2017 WATERFORD-2017-03 Draft Written Examination - Do Not Release Until 4-30-19 ML17137A1842017-04-0505 April 2017 2017-03 Draft Outlines - Do Not Release Until 04/30/2019 ML17137A1852017-04-0505 April 2017 WATERFORD-2017-03 Draft Outline Comments - Do Not Release Until 4-30-19 ML17137A1902017-04-0505 April 2017 2017-03 Final Outlines ML17137A1882017-04-0505 April 2017 WATERFORD-2017-03 Draft Operating Test - Do Not Release Until 4-30-19 ML17137A1892017-04-0505 April 2017 2017-03 Draft Operting Test Comments - Do Not Release Until 04/30/2019 ML17137A1912017-04-0505 April 2017 WATERFORD-2017-03 Public Forms ML17137A1872017-04-0505 April 2017 WATERFORD-2017-03 Draft Written Exam Comments - Do Not Release Until 4-30-19 ML17122A0492017-03-27027 March 2017 2017-03 Final Operating Test - Do Not Release Until 4-30-19.pdf ML17075A3402017-03-14014 March 2017 NRC Initial Operator Licensing Examination Approval 05000382/2017301 ML17013A5482017-01-13013 January 2017 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2017 ML15351A0282015-12-17017 December 2015 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2016 ML15273A3322015-09-30030 September 2015 Generic Fundamentals Examination Results Sept 2015 ML15278A2222015-09-14014 September 2015 2015-09-FINAL Outlines ML15308A3802015-09-14014 September 2015 2015-09 Public Forms ML15278A2442015-09-14014 September 2015 WT-2015-09 Draft Written Exam Comments ML15278A2402015-09-14014 September 2015 WT - 2015 - 09 Draft Operating Test Comments ML15278A2372015-09-14014 September 2015 2015-09 Draft Outline Comments ML15278A2312015-09-14014 September 2015 2015-09 Final Operating Test ML15278A2282015-09-14014 September 2015 2015-09 Final Written Examination ML15273A4332015-09-14014 September 2015 2015-09 Post Exam Comments ML15225A5642015-09-14014 September 2015 2015-09 Draft Operating Test and Revised Outlines 2023-08-15
[Table view] Category:Part 55 Examination Related Material
MONTHYEARIR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML22075A3442022-03-16016 March 2022 Response to Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML22108A2662022-03-0909 March 2022 WAT-2022-02 Public Forms W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis ML21117A2932021-04-28028 April 2021 Notification of NRC Initial Operator Licensing Examination 05000382/2022301 ML21106A1512021-04-16016 April 2021 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations W3F1-2020-0056, 08 Post Exam Analysis2020-09-10010 September 2020 08 Post Exam Analysis IR 05000382/20200082020-08-26026 August 2020 Examination Inspection Report 05000382/2020008 Final Outlines ML20294A1372020-08-26026 August 2020 08 Public Forms ML20267A2132020-08-26026 August 2020 08 Final Operating Test ML20267A2122020-08-26026 August 2020 Examination Inspection Report 05000382/2020008 Final Written Exam ML20267A2052020-08-26026 August 2020 08 Draft Outlines ML20267A2072020-08-26026 August 2020 08 Draft Written Exam ML20267A2082020-08-26026 August 2020 08 Draft Written Exam Comments ES-401-9 ML20267A2102020-08-26026 August 2020 08 Draft Operating Test Comments ML20267A2092020-08-26026 August 2020 08 Draft Operating Test.Pdf ML20267A2062020-08-26026 August 2020 05000382/202008 Draft Outline Comments ML20307A1742020-08-10010 August 2020 08 Exam Approval Letter ML20219A292 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML20307A1732020-01-0707 January 2020 05000382/2020008 Corporate Notification Letter ML20007E607 ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML18304A4862018-10-30030 October 2018 NRC Initial Operator Licensing Examination Approval 05000382/2018301 ML18089A0412018-03-29029 March 2018 Notification of NRC Initial Operator Licensing Examination 05000382/2018301 ML18009A9852018-01-0808 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17122A0502017-04-10010 April 2017 2017-03 Post Exam Comments ML17137A1862017-04-0505 April 2017 WATERFORD-2017-03 Draft Written Examination - Do Not Release Until 4-30-19 ML17137A1882017-04-0505 April 2017 WATERFORD-2017-03 Draft Operating Test - Do Not Release Until 4-30-19 ML17137A1902017-04-0505 April 2017 2017-03 Final Outlines ML17137A1872017-04-0505 April 2017 WATERFORD-2017-03 Draft Written Exam Comments - Do Not Release Until 4-30-19 ML17137A1892017-04-0505 April 2017 2017-03 Draft Operting Test Comments - Do Not Release Until 04/30/2019 ML17122A0482017-04-0505 April 2017 2017-03 Final Written Examination ML17137A1912017-04-0505 April 2017 WATERFORD-2017-03 Public Forms ML17137A1842017-04-0505 April 2017 2017-03 Draft Outlines - Do Not Release Until 04/30/2019 ML17137A1852017-04-0505 April 2017 WATERFORD-2017-03 Draft Outline Comments - Do Not Release Until 4-30-19 ML17122A0492017-03-27027 March 2017 2017-03 Final Operating Test - Do Not Release Until 4-30-19.pdf ML17075A3402017-03-14014 March 2017 NRC Initial Operator Licensing Examination Approval 05000382/2017301 ML15351A0282015-12-17017 December 2015 Generic Fundamentals Section of the Written Operator Licensing Examination Scheduled for 2016 ML15273A3322015-09-30030 September 2015 Generic Fundamentals Examination Results Sept 2015 ML15308A3802015-09-14014 September 2015 2015-09 Public Forms ML15278A2442015-09-14014 September 2015 WT-2015-09 Draft Written Exam Comments ML15278A2402015-09-14014 September 2015 WT - 2015 - 09 Draft Operating Test Comments ML15278A2372015-09-14014 September 2015 2015-09 Draft Outline Comments ML15278A2312015-09-14014 September 2015 2015-09 Final Operating Test ML15278A2282015-09-14014 September 2015 2015-09 Final Written Examination ML15278A2222015-09-14014 September 2015 2015-09-FINAL Outlines ML15273A4332015-09-14014 September 2015 2015-09 Post Exam Comments ML15225A5642015-09-14014 September 2015 2015-09 Draft Operating Test and Revised Outlines ML15225A5222015-09-14014 September 2015 2015-09 Draft Written Exam and Revised Outlines ML15225A4902015-09-14014 September 2015 2015-09-DRAFT Outlines 2023-08-15
[Table view] |
Text
NRC Comments on 2002 Waterford 3 NRC Written Makeup Exam (31 July 2002)
"* Question 17 - Answer listed in key does not match choices listed above.
- Resolution: Typo. Corrected answer key to show correct answer.
"* Question 34- Reference supplied does not support answer.
- Resolution: Added other reference to make this clearer. OP-901-110, subsection E2, step 3, requires maintaining Pressurizer Level above the Minimum Level of Operation per Attachment 1, Pressurizer Level vs. Tave Curve. Plant Data Book Section 2.2.1, RCS Temperature Control Bands vs.
Power, is used to determine Tref for 95% power. Tavg is maintained by the Pressurizer Tavg Program to match Tref. The student would use this temperature (Tref) for Tavg. Using OP-901-110, Attachment 1, the student should determine that the minimum level for operation at 95% power is approximately 41%. Reworded question to remove initial condition of 100% since this was extraneous to the question.
"* Question 51 - Per reference, answer is true if SGFPs are being supplied with Reheat Steam.
Resolution: Added further reference from System Description for SG Feedpumps. Up until 39% power, steam is supplied to the Feedwater Pumps from the Main Steam System. Above 39% power, steam is supplied by the Moisture Seperator/Reheater (MSR) B. During startup, both the LP &
HP Stop valves are open. As plant load increases and steam pressure from the B MSR increases, the HP governor will slowly close. The HP governor will be fully closed at 39% power. Since the trip is not active unless the HP Governor valves are open, the question is correct as written. (See Attachment 1, Additional References)
"* Question 61 - Per NUREG guidance, this question's stem is negatively worded.
- Resolution: Changed question from determining which answer is false to determining which answer is true.
"* Question 67 - Stem should also require Tavg response. Use similar distractors in answers B & D.
- Resolution: Changed stem to require Tavg response. Changed all answers to have same format. Also, changed delta-T power to AT power which is the normally used designation.
1
NRC Comments on 2002 Waterford 3 NRC Written Makeup Exam (31 July 2002)
Question 68 - UNSAT. No credible distractors.
- Resolution: Rewrote question to have student determine what ensures adequate NPSH for the Containment Spray pumps following a LOCA. Also, changed lesson plant objective from #1 to #4 which asks for the interrelation between the Containment Spray System and the Containment/SI Sump. And added objective 18 of lesson plan for LOCA.
(see Attachment 1, Additional References).
" Question 69 - K/A number listed is different from K/A number in outline.
Resolution: Oversight. K/A was changed since question #96 already deals with Containment Pressure. Random selection process generated new K/A number. Updated Justification of K/A Changes document.
" Question 77 - Distractor C appears implausible in that auto closure does not happen unless key operated.
- Resolution: Changed distractor C to state BD-303 closes on Blowdown Radiation Monitor Alert Alarm. Similar to Distractor D for Circ Water Radiation Monitor.
" Question 78 - Reword last statement in stem. "Which of the following is a valid starting sequence for these pumps?"
0 Resolution: Reworded last statement as stated.
" Question 79 - References do not support a requirement to test CVAS for failure of Door 170.
- Resolution: Added page 40 of OP-100-014, Technical Specification and Technical Requirements Compliance, as a reference which requires this test.
" Question 88 - Reference provided does not justify the answer.
Resolution: Changed answer B to having the ability to removing equipment from service which only the SM can do (OP-1 00-001, section 5.1.3.5k) even if the NPO has Control Room Command function in Mode 5 (OP-1 00-001, section 5.1.6.1.4d & e). Changed answer A to match answer B terminology. (See Attachment 1, Additional References) 2
NRC Comments on 2002 Waterford 3 NRC Written Makeup Exam (31 July 2002)
"* Question 89 - Really valid if TS 3.0.3 is not provided.
- Resolution: Student is required to know TS 3.0.3 from memory and any requirements to use it. TS 3.0.3 is not provided as a reference for this question.
"* Question 92 - UNSAT. Distractors C & D invalid because plant is already in hot standby.
- Resolution: Changed all distractors to have plant go to Hot Shutdown.
Added contacting NRC to all answers.
"* Question 94 - K/A changed to from 2-3-1 to 2-3-10 without justification.
- Resolution: Typo. Corrected KIA number to 2-3-1.
"* Question 95 - Specify that entry is being made by HP tech or by personnel accompanied by HP Tech.
- Resolution: Changed question to state a NAO and RP tech entering to check piece of equipment. Changed HP tech to RP tech due to new designation of RP personnel.
3