MONTHYEARIR 05000369/20240032024-11-0404 November 2024 Integrated Inspection Report 05000369/2024003 and 05000370/2024003 IR 05000413/20240032024-11-0404 November 2024 Integrated Inspection Report 05000413/2024003 and 05000414/2024003 IR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24303A4212024-10-30030 October 2024 Mcguire Nuclear Station, Units 1 & 2, Notification of an NRC Fire Protection Team Inspection FPTI NRC 05000369/2025010, 05000370/2025010 and Request for Information RFI ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24297A6222024-10-11011 October 2024 PCA Letter to NRC Catawba Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure IR 05000369/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000369/2024402 05000370/2024402 IR 05000413/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000413/2024011 and 05000414/2024011 ML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) IR 05000369/20240052024-08-26026 August 2024 Updated Inspection Plan for McGuire Nuclear Station, Units 1 and 2, (Report 05000369-2024005 and 05000370-2024005) ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 IR 05000369/20244042024-08-0101 August 2024 Cover Letter Security Baseline Inspection Report 05000369/2024404 and 05000370/2024404 IR 05000369/20253012024-07-29029 July 2024 Notification of Licensed Operator Initial Examination 05000369/2025301 and 05000370/2025301 IR 05000369/20244032024-07-25025 July 2024 – Cyber Security Inspection Report 05000369/2024403 and 05000370/2024403 Rev IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 IR 05000369/20240022024-07-24024 July 2024 Integrated Inspection Report 05000369/2024002 and 05000370/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000369/20244012024-07-0303 July 2024 – Security Baseline Inspection Report 05000369/2024401 and 05000370/2024401 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station ML24176A2802024-06-26026 June 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000369-2024404 and 05000370-2024404) IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing IR 05000369/20240112024-06-0404 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000369/2024011 and 05000370/2024011 ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation IR 05000369/20240012024-05-0808 May 2024 Integrated Inspection Report 05000369-2024001 and 05000370-2024001 and 07200038-2024001 IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 ML24110A0382024-04-30030 April 2024 – Correction to Issuance of Amendment Nos. 330 and 309, Regarding Implementation of Technical Specifications Task Force (TSTF) Traveler TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24100A8742024-04-10010 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000369/2024403; and 05000370/2024403 ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) ML24052A3062024-04-0808 April 2024 Issuance of Amendment Nos. 331 & 310, Regarding Adoption of Title 10 of Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24031A5402024-03-26026 March 2024 Issuance of Amendment Nos. 330 and 309 Regarding Implementation of TSTF 505,Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B 2024-09-05
[Table view] |
Text
February 4, 2003 Mr. Michael S. Tuckman Executive Vice President Duke Energy Corporation 526 South Church St Charlotte, NC 28201-1006
SUBJECT:
DUKE ENERGY CORPORATION NUCLEAR QUALITY ASSURANCE PROGRAM
Dear Mr. Tuckman:
By letter dated December 18, 2002, the Duke Energy Corporation submitted Amendment number 32 to its Duke Energy Corporation Topical Report, Duke-1-A, on the Quality Assurance (QA) Program for the Oconee, McGuire and Catawba Nuclear Stations. Your letter states that you have determined that the changes constitute a reduction in commitment to the QA program and, therefore, these changes must be submitted to and approved by the Nuclear Regulatory Commission staff prior to implementation in accordance with Title 10 of the Code of Federal Regulations, Part 50.54(4).
Your letter dated December 18, 2002, was actually received by our staff on or after January 2, 2003. As we discussed with J. M. Frye on January 27, 2003, we anticipate preparing a request for additional information, if necessary, by March 30, 2003, and we anticipate completing the review within sixty (60) days after receiving your response.
Please contact Bob Martin at (301) 415-1493, if you have any other questions on these issues.
Sincerely,
/RA/
Robert E. Martin, Senior Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, 50-287, 50-413, 50-414, 50-369 and 50-370 cc: See next page
ML030350017 OFFICE PDII-1PM DIPM/IEHB PDII-1/LA PDII-1/SC NAME RMartin: DThatcher CHawes JNakoski DATE 1/27/03 1/28/03 1/29/03 1/31/03 McGuire Nuclear Station cc:
Ms. Lisa F. Vaughn Ms. Karen E. Long Legal Department (PBO5E) Assistant Attorney General Duke Energy Corporation North Carolina Department of 422 South Church Street Justice Charlotte, North Carolina 28201-1006 P. O. Box 629 Raleigh, North Carolina 27602 County Manager of Mecklenburg County Mr. C. Jeffrey Thomas 720 East Fourth Street Manager - Nuclear Regulatory Charlotte, North Carolina 28202 Licensing Duke Energy Corporation Michael T. Cash 526 South Church Street Regulatory Compliance Manager Charlotte, North Carolina 28201-1006 Duke Energy Corporation McGuire Nuclear Site NCEM REP Program Manager 12700 Hagers Ferry Road 4713 Mail Service Center Huntersville, North Carolina 28078 Raleigh, North Carolina 27699-4713 Anne Cottingham, Esquire Mr. Richard M. Fry, Director Winston and Strawn Division of Radiation Protection 1400 L Street, NW. North Carolina Department of Washington, DC 20005 Environment, Health and Natural Resources Senior Resident Inspector 3825 Barrett Drive c/o U.S. Nuclear Regulatory Raleigh, North Carolina 27609-7721 Commission 12700 Hagers Ferry Road Mr. T. Richard Puryear Huntersville, North Carolina 28078 Owners Group (NCEMC)
Duke Energy Corporation Dr. John M. Barry 4800 Concord Road Mecklenburg County York, South Carolina 29745 Department of Environmental Protection 700 N. Tryon Street Charlotte, North Carolina 28202 Mr. Peter R. Harden, IV VP-Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road 12th Floor Charlotte, North Carolina 28210