Approval to Use More Recent Pressure Relief Device Test Requirements
ML030230742
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 01/23/2003
From: Chandu Patel
NRC/NRR/DLPM/LPD2
To: Scarola J
Carolina Power & Light Co
Patel C P, NRR/DLPM, 415-3025
References
TAC MB6966
Download: ML030230742 (4)


Text

January 23, 2003 Mr. James Scarola, Vice President Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - APPROVAL TO USE MORE RECENT PRESSURE RELIEF DEVICE TEST REQUIREMENTS (TAC NO.

MB6966)

Dear Mr. Scarola:

By letter dated December 4, 2002, Carolina Power & Light Company (CP&L) requested the Nuclear Regulatory Commissions (NRCs) approval to use a more recent edition and addenda of the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code) for testing pressure relief devices in the Harris Nuclear Plant (HNP) inservice testing (IST) program. The current Code of record for the HNP IST program is the 1987 Edition and 1988 Addenda of the ASME OM Code. CP&L requested approval to use the portions of the 1998 Edition up to and including the 2000 Addenda of the ASME OM Code related to inservice testing of pressure relief devices for the remainder of its second 10-year IST interval. CP&L stated that it would apply all the related requirements in Mandatory Appendix I, Inservice Testing of Pressure Relief Devices in Light-Water Reactor Nuclear Power Plants, of the 1998 Edition up to and including the 2000 Addenda of the ASME OM Code. CP&L committed to full implementation of Mandatory Appendix I within 60 days of NRC approval.

Section 50.55a(f)(4)(iv) states that IST of pumps and valves may meet the requirements set forth in subsequent editions and addenda that are incorporated by reference in 10 CFR 50.55a(b), subject to NRC approval. Portions of editions or addenda may be used provided that all related requirements of the respective editions and addenda are met. The 1998 Edition up to and including the 2000 Addenda of the ASME OM Code were incorporated by reference in 10 CFR 50.55a(b) on September 26, 2002 (67 FR 60520), with no modifications or limitations placed on Mandatory Appendix I requirements. Therefore, the request to use the portions of a later Code and Addenda associated with the IST of pressure relief devices at HNP, submitted by CP&L in its letter dated December 4, 2002, is approved pursuant to 10 CFR 50.55a(f)(4)(iv) for the remainder of the second IST interval.

Sincerely,

/RA/

Chandu P. Patel, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-400 cc: See next page

ML030230742

  • See previous concurrence OFFICE PM:PDII/S2 LA:PDII/S2 SC:PDII/S2 OGC*

NAME CPatel EDunnington JNakoski for AHowe RHoefling DATE 1/21/03 1/22/03 1/22/03 1/21/03 COPY Yes/No Yes/No Yes/No Yes/No

Mr. James Scarola Shearon Harris Nuclear Power Plant Carolina Power & Light Company Unit 1 cc:

Mr. William D. Johnson Vice President and Corporate Secretary Carolina Power & Light Company Post Office Box 1551 Raleigh, North Carolina 27602 Resident Inspector/ Harris NPS c/o U. S. Nuclear Regulatory Commission 5421 Shearon Harris Road New Hill, North Carolina 27562-9998 Ms. Karen E. Long Assistant Attorney General State of North Carolina Post Office Box 629 Raleigh, North Carolina 27602 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, South Carolina 29211 Ms. Beverly Hall, Acting Director Division of Radiation Protection N.C. Department of Environment and Natural Resources 3825 Barrett Drive Raleigh, North Carolina 27609-7721 Mr. Terry C. Morton Manager Performance Evaluation and Regulatory Affairs CPB 7 Carolina Power & Light Company Post Office Box 1551 Raleigh, North Carolina 27602-1551 Mr. Benjamin C. Waldrep Plant General Manager - Harris Plant Carolina Power & Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 3 New Hill, North Carolina 27562-0165 Mr. John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW.

Washington, DC 20037-1128 Mr. Robert J. Duncan II Director - Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Post Office Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 Mr. Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, North Carolina 27699-4326 Chairman of the North Carolina Utilities Commission Post Office Box 29510 Raleigh, North Carolina 27626-0510 Ms. Linda Coleman, Chairperson Board of County Commissioners of Wake County P. O. Box 550 Raleigh, North Carolina 27602 Mr. Gary Phillips, Chairman Board of County Commissioners of Chatham County P. O. Box 87 Pittsboro, North Carolina 27312 Mr. James W. Holt, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 1 New Hill, North Carolina 27562-0165 Mr. John R. Caves, Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165