ML030100026

From kanterella
Jump to navigation Jump to search
NRC Examination Report 05000321/02-301 & 05000366/02-301, on October 16-24, 2002
ML030100026
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/09/2003
From: Ernstes M
Operator Licensing and Human Performance Branch
To: Sumner H
Southern Nuclear Operating Co
References
50-321/02-301, 50-366/02-301 50-321/02-301, 50-366/02-301
Download: ML030100026 (15)


See also: IR 05000321/2002301

Text

January 9, 2003

Southern Nuclear Operating Company, Inc.

ATTN: Mr. H. L. Sumner, Jr.

Vice President

P. O. Box 1295

Birmingham, AL 35201-1295

SUBJECT:

EDWIN I. HATCH NUCLEAR PLANT - NRC EXAMINATION REPORT

50-321/02-301 AND 50-366/02-301

Dear: Sumner:

During the period October 16-24, 2002, the Nuclear Regulatory Commission (NRC)

administered operating examinations to employees of your company who had applied for

licenses to operate the Edwin I. Hatch Point Nuclear Plant. At the conclusion of the

examination, the examiners discussed the examination questions and preliminary findings with

those members of your staff identified in the enclosed report. The written examination was

administered by your staff on October 30, 2002.

All eleven applicants passed the operating examination, all but one SRO passed the written

examination. There were six post examination written comments and one post examination

operating examination comment which are identified in Enclosure 2.

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its

enclosures will be available electronically for public inspection in the NRC Public Document Room

or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

Michael E. Ernstes, Chief

Operator Licensing and

Human Performance Branch

Division of Reactor Safety

Docket Nos. 50-321, 50-366

License Nos. DPR-57, NPF-5

Enclosures: (See page 2)

SNC

2

Enclosures:

1. Report Details

2. Post Examination Comment Resolution

cc w/encls:

J. D. Woodard

Executive Vice President

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

P. H. Wells

General Manager, Plant Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

Raymond D. Baker

Manager Licensing - Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

Ernest L. Blake, Esq.

Shaw, Pittman, Potts and

Trowbridge

2300 N Street, NW

Washington, D. C. 20037

Office of Planning and Budget

Room 610

270 Washington Street, SW

Atlanta, GA 30334

Director

Department of Natural Resources

205 Butler Street, SE, Suite 1252

Atlanta, GA 30334

Manager, Radioactive Materials Program

Department of Natural Resources

Electronic Mail Distribution

Chairman

Appling County Commissioners

County Courthouse

Baxley, GA 31513

Resident Manager

Oglethorpe Power Corporation

Edwin I. Hatch Nuclear Plant

Electronic Mail Distribution

Charles A. Patrizia, Esq.

Paul, Hastings, Janofsky & Walker

10th Floor

1299 Pennsylvania Avenue

Washington, D. C. 20004-9500

Senior Engineer - Power Supply

Municipal Electric Authority

of Georgia

Electronic Mail Distribution

John C. Lewis

Training Manager

E. I. Hatch Nuclear Plant

U. S. Highway 1 North

P. O. Box 2010

Baxley, GA 31513

SNC

3

Distribution w/encls:

L. Olshan, NRR

J. Munday, SRI

RIDSNRRDIPMLIPB

PUBLIC

OFFICE

RII:DRS

RII:DRS

RII:DRS

RII:DRS

RII:DRP

SIGNATURE

/RA/

/RA By Rbaldwin For/

/RA/

/RA By RBaldwin For/ /RA/

/RA/

NAME

RBaldwin:pmd

TKolb

GLaska

LVick

MErnstes

BBoser

DATE

1/9/03

1/9/03

1/9/03

1/9/03

1/9/03

1/9/03

E-MAIL COPY?

YES

NO YES

NO YES NO YES

NO YES

NO YES

NO

PUBLIC DOCUMENT

YES

NO

OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML030100026.WPD

Enclosure 1

NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos.:

50-321, 50-366

License Nos.:

DPR-57, NPF-5

Report Nos.:

50-321/02-301, 50-366/02-301

Licensee:

Southern Nuclear Operating Company, Inc. (SNC)

Facility:

Edwin I. Hatch Nuclear Plant

Location:

P.O. Box 2010

Baxley, Georgia 31515

Dates:

Operating Tests - October 16-24, 2002

Written Examination - October 30 , 2002

Examiners:

R. Baldwin, Chief Examiner

G. Laska, Operations Engineer

L. Vick, Senior Reactor Engineer

T. Kolb, Operations Engineer (Under Instruction)

Approved by:

M. Ernstes, Chief

Operator Licensing and Human Performance Branch

Division of Reactor Safety

SUMMARY OF FINDINGS

ER 05000321-2002-301, ER 05000366-2002-301, on 10/16-24/2002, Southern Nuclear

Operating Company, Inc., Edwin I. Hatch Nuclear Plant, Units 1 and 2, licensed operator

examinations.

The NRC examiners conducted operator licensing initial examinations in accordance with the

guidance of Examiner Standards, NUREG-1021, Revision 8, Supplement 1. This examination

implemented the operator licensing requirements of 10 CFR §55.41, §55.43, and §55.45.

The NRC administered the operating tests during the period October 16- 24, 2002. Members of

the Edwin I. Hatch Nuclear Plant training staff administered the written examination on

October 30, 2002. The operator licensing initial written examinations were developed by the

NRC. The operating tests were developed by the Edwin I. Hatch staff from an outline submitted

by the NRC. All applicants, one Reactor Operator (RO) and ten Senior Reactor Operators

(SRO) passed the operating examination. All applicants except one SRO passed the written

examination. Those applicants that passed both examinations were issued operator licenses

commensurate with the level of examination administered.

No significant issues were identified.

Report Details

4.

OTHER ACTIVITIES (OA)

4OA5 Operator Licensing Initial Examinations

a.

Inspection Scope

The examiners developed the written and operating examinations in accordance with

the guidelines specified in NUREG-1021, Revision 8, Supplement 1.

The examiners reviewed the licensees examination security measures while preparing

and administering the examinations to ensure examination security and integrity

complied with 10 CFR 55.49, Integrity of examinations and tests.

The examiners evaluated one RO and ten SRO applicants who were being assessed

under the guidelines specified in NUREG-1021. They administered the operating tests

during the period October 16-24, 2002. Members of the Edwin I. Hatch Nuclear Plant

training staff administered the written examination on October 30, 2002. The

evaluations of the applicants and review of documentation were performed to determine

if the applicants, who applied for licensees to operate the Edwin I. Hatch Nuclear Plant,

met requirements specified in 10 CFR Part 55.

b.

Findings

No findings of significance were identified.

The licensee submitted six post examination comments concerning the written

examination and one post examination operating examination comment (ADAMS

Accession Number ML 023290002). The RO and SRO written examinations and

answer keys may be accessed in the ADAMS system (ADAMS Accession Number

ML02329003 and ML02329006).

4OA6 Meetings

Exit Meeting Summary

On October 25, 2002, the Chief Examiner discussed generic applicant performance and

examination development issues with members of licensee management.

The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary. No proprietary information was identified.

2

PARTIAL LIST OF PERSONS CONTACTED

Licensee

J. Betsill, Assistant, General Manager-Support

R. Diedrickson, Manager, Operations

S. Grantham, Supervisor, Operations Training

G. Johnson, Supervisor, Safety Audit & Engineering Review

J. Lewis, Manager, Training & EP

S. Tipps, Manager, Nuclear Safety & Compliance

P. Wells, General Manager

NRC

J. Munday, Senior Resident Inspector

N. Garrett, Resident Inspector

Enclosure 2

Hatch Exam 2002-301

Facility Comments and NRC Resolutions

Question:

  1. 7, SRO Exam

Comment:

The licensee recommends accepting answer B as a correct answer in addition to

the key answer D. Supporting documentation was submitted, Hatch Licensee

Event Report (LER) 2002-001, in which the E. I. Hatch Nuclear Safety and

Compliance department determined that HPCI was declared INOPERABLE with

the vacuum breakers isolated.

Resolution: Recommendation partially accepted. The licensee provided LER stated that the

HPCI System is rendered INOPERABLE with the HPCI Exhaust Line Vacuum

Breaker isolated. This LER is considered to represent the licensees official

determination of the systems OPERABILITY concerning the isolation of these

valves. Therefore, answer D which declared the HPCI system to OPERABLE

under these conditions will not be considered as a correct response.

The answer key will be changed to reflect that B is the only correct answer.

Question:

  1. 15, SRO Exam
  1. 21, RO Exam

Comment:

The licensee recommends deleting this question due to not having a correct

answer. The APRM UPSC TRIP/INOP SYS B alarm was replaced with

APRM/OPRM TRIP and only a ROD OUT BLOCK will be initiated.

Resolution: Recommendation accepted. The alarm identified in the answer no longer exists.

The answer should have identified that the ROD OUT BLOCK annunciator is in

alarm. The reference material provided to develop the examination was not

updated in this area.

The answer key will be changed to reflect the deletion of this question.

Question:

  1. 57, SRO Exam
  1. 66, RO Exam

Comment:

The licensee recommends deleting this question in that it does not meet the intent

of the K/A. The licensee contends that the question does not test the knowledge

of the reasons for a scram but it tests the reason for two steps in a procedure to

provide a Reactor scram.

Resolution: Recommendation not accepted.

The question was developed from K/A 295016 AK 3.01 which is:

2

Knowledge of the reasons for the following responses as they apply to

control room abandonment: Reactor scram.

The question asks why the procedure also provides additional methods for

scramming the reactor (provided in the stem) when the control room is being

abandoned. The distractors provide the governing document where this

requirement is identified. In this situation the FSAR requires that the ability for

prompt hot shutdown of the reactor from locations outside the control room must

be maintained.

The answer key will remain unchanged.

Question:

  1. 66, SRO Exam
  1. 74, RO Exam

Comment:

The facility recommends this question be deleted since it exceeds the learning

objective and the bounds of the K/A by testing the number of valid inputs for

SPDS indication.

Resolution: Recommendation not accepted.

The question was developed from K/A 295026 EK 2.04 which is:

Knowledge of the interrelationship between suppression pool high water

temperature and the following: SPDS.

The question stem states the average Suppression Pool temperature is 102 F.

and identifies how many signals are operable for each group. An SPDS display

will turn Yellow if there are less than two inputs from any group. The number of

operable readings per group would allow the operator to determine this condition

was not met. The stem indicates that each group has at least four operable

signals. Since there was only one inoperable signal in two of the groups, the

question did not test the specific logic required for an operable signal (2/5) but the

applicant only needed to recognize that you can have one invalid signal and still

have a valid SPDS indication. The question was a valid test of the K/A.

The answer key will remain unchanged.

Question:

  1. 72, SRO Exam
  1. 78 RO Exam

Comment:

The facility recommended accepting distractor D as an additional correct answer.

Since a primary system discharging into secondary containment would be

considered a substantial degradation. Also, performing an Emergency

Depressurization places the plant in the safest possible condition as quickly as

possible since the 100 F cooldown rate can be exceeded. Additionally, the

3

licensee contends that the question is not within the bounds of the K/A, but does

not request it be deleted as in previous contested questions.

Resolution: Recommendation accepted. The fact that the primary system is causing two

areas within Secondary Containment to exceed maximum safe operating

temperatures implies the leak is substantial. While distractor D is a true

statement it is not the reason for emergency depressurization based on lesson

plan material. Since the stem of the question did not clearly identify where the

basis for this question came from an additional answer D will be also allowed.

The K/A states Knowledge of the reasons for the following responses as they

apply to high secondary containment area temperature: Isolating affected

systems. The NRC maintains the question meets the K/A due to the fact that it

addresses the reason for emergency depressurization if the affected system

cannot be isolated. If the system could be isolated this would not be an issue.

The answer key will be changed to reflect that answer D will be allowed as an

additional correct answer.

Question:

  1. 98, SRO Exam
  1. 99, RO Exam

Comment:

The question requires the applicant to determine how the Shift Supervisor

maintains communications with the Fire Brigade from the main control room. The

facility recommends this question be deleted since the radio system has been

upgraded per DCR 01-004 and therefore has no correct answer.

Resolution: Recommendation accepted. Since a new system has been installed there is no

correct answer. The reference material provided for examination development

was not updated in this area.

The answer key will be changed to reflect the deletion of this question.

Question:

  1. 53, SRO Exam
  1. 54, SRO Exam

Comment:

The licensee contends that an applicant while transposing answers for the above

two questions the applicant marked E for the answers. The licensee contends

that the applicant intended to answer D for the above questions. The licensee

provided a copy of the applicants examination where the applicant circled D for

these two questions. The licensee recommends amending the applicants answer

sheet to reflect D for both questions.

Resolution: Recommendation not accepted. Since the applicant elected to place his answers

on the examination in stead of the answer sheet directly, the applicant is

responsible for ensuring accuracy when transcribing answers from the

4

examination to the answer sheet. NUREG-1021, Revision 8, Supplement 1,

Appendix E, Part B, Step 6 provides guidance for marking the answer sheets.

Once an applicants answer sheet is handed in to the proctor, the examination

responses are considered final, no changes can be made to the answer sheet

after that event. Handing in the examination signifies the completion of the

examination.

JPM Admin A.2 (SRO Only)

Comment:

The JPM required the individual to review a surveillance for the Scram Discharge

Volume Isolation Valves in which 3 of the valves had stroke times outside the

Acceptance Criteria times. Two of the valves exceeded the Tech Spec maximum

stroke time of 60 seconds and one of the valves only exceeded the surveillance

Acceptance Criteria of 56 seconds but was within the Technical Specifications

time of 60 seconds. The facility recommends accepting the actions for all 3

valves being inoperable by Tech Specs and also accepting the Tech Spec actions

for only 2 of the valves being Tech Spec inoperable.

Resolution: Recommendation not accepted. The facility states that Tested components

which do NOT meet the criteria specified in the surveillance procedure are

considered inoperable. A discussion with the Operations Manager and Licensing

Manager at the time the JPM was administered resulted in the same conclusion.

The NRC will grade the JPM as it was originally intended. The 3 valves that did

not meet the acceptance criteria of the surveillance are considered inoperable.

No change to the answer key will be made.