Text
"Exeln.
Exelon Nuclear Limerick Generating Station PO Box 2300 Sanatoga, PA 19464 wwwexeloncorp corn Nuclear T.S. 6.9.1.6 December 13, 2002 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
- Limerick Generating Station,-Units J and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353
Subject:
Monthly Operating Report for November 2002 Attached is the monthly operating report for Limerick Units 1 and 2 for the month of November 2002 forwarded pursuant to Technical Specification 6.9.1.6 and the guidance of NRC Generic Letter 97-02.
If you have any questions or require additional information, please do not hesitate to contact us.
Sincerely, Robert C. Braun Plant Manager Attachments cc:
H. J. Miller, Administrator, Region I, USNRC A. L. Burritt, LGS USNRC Senior Resident Inspector
/-_1 R. C.
Unit:
Docket No:
Date:
Completed by:
Telephone:
Limerick 1 50-352 12/13/02 Greg Lee (610) 718-3707 A.
OPERATING DATA REPORT REPORTING PERIOD-November 2002 IDesign Electrical Rating (MWe-Net)
I1191 i
Maximum Dependable Capacity (MWe-Net) 1134 Monnh Ye.ar to Date Cumulative Hours Reactor Critical (Hours) 720.0 7,569.2 129,124.4 Hours Generator On-Line (Hours) 720.0 7,501.0 127,165.1 Unit Reserve Shutdown Hours (Hours) 0.0 0.0 0.0 Net Electrical Energy (MWh) 846,674,
8,407,256 130,889,255 P
iiNiT.HiITflOWN No.
Date Type Generator Reason Method Corrective Actions/Comments (yymmdd)
Off-line Duration (hrs)
None During November 1 12002 11
SUMMARY
Unit 1 began the month of November 2002 at 100% of rated thermal power (RTP).
There were no changes in reactor power on Unit 1 in November 2002.
Unit 1 ended the month of November 2002 at 100% RTP.
Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other (Explain)
F-Administrative G-Operational Error (Explain)
H-Other (Explain)
C. -
SAFETY/RELIEF VALVE OPERATION 1'
Date Valves Actuated No. & Type of Actuation Plant Condition
.escription ot Event None During November 2002
Unit:
Docket No:
Date:
Completed by:
Telephone:
Limerick 2 50-353 12/13/02 Greg Lee (610)718-3707 A.
OPERATING DATA REPORT REPORTING PERIOD-November 2002 I Design Electrical Rating (MWe-Net) 1191 Maximum Dependable Capacity (MWe-Net) 1134 Mnnth IYear to Date ICumulative Hours Reactor Critical (Hours) 720.0 7,950.5 105,383.5
-'------i IJt-utr
nrrntrr fln.i me (Hniir
-
4---- -720.0-I------
"7:92. -
1u0j.t,1i.0-i-Unit Reserve Shutdown Hours (Hours) 0.0 0.0 0.0 Net Electrical Energy (MWh) 844,504 9,135,251 110,759,975 B.
UNIT SHUTDOWN No.
Date Type Generator Reason Method Corrective Actions/Comments (yymmdd)
Off-line Duration (hrs)
None during November 2002
SUMMARY
Unit 2 began the month of November 2002 at 100% of rated thermal power (RTP).
On November 12 1 at 23:01 hours, reactor power was reduced to 97% RTP for a deep shallow rod pull.
On November 13'n at 01:29 hours, reactor power was restored to 100% RTP.
Unit 2 ended the month of November 2002 at 100% RTP.
Type Reason Method F-Forced A-Equipment Failure (Explain) 1-Manual S-Scheduled B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other (Explain)
-- F-Administrative-G-Operational Error (Explain)
H-Other (Explain)
C. SAFETY/RELIEF VALVE OPERATION Date Valves Actuated No. & Type of Actuation Plant Condition Description of Event None During November 2002 I