Meeting Summary, New Containment Building Sump Strainer Design
ML023460135
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/06/2003
From: Hopkins J
NRC/NRR/DLPM/LPD3
To:
Hopkins J, DLPM/NRR, 415-3027
References
Download: ML023460135 (6)


Text

January 6, 2003 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - MEETING

SUMMARY

OF NOVEMBER 26, 2002, TO DISCUSS THE NEW CONTAINMENT BUILDING SUMP STRAINER DESIGN On November 26, 2002, Nuclear Regulatory Commission (NRC) management and staff conducted a public meeting in Rockville, Maryland, with representatives of FirstEnergy Nuclear Operating Company. The purpose of the meeting was to discuss the new Davis-Besse containment building emergency sump strainer design. The meeting was noticed on November 15, 2002. A telephone conference bridge was established for members of the public who were unable to attend.

The licensee presented a summary of the status of the containment emergency sump strainer modification. The original sump strainer design consisted of galvanized wire with 1/4 inch square openings. The new design consists of perforated stainless steel tubes with 3/16 inch diameter holes. The strainers are designed to American Society of Mechanical EngineersSection III to withstand 5 psi differential pressure. The new strainer design consists of an upper and lower strainer comprising approximately 1200 square feet of available surface area.

The licensee reviewed two pipe break scenarios as controlling the strainer design. The first scenario consisting of a hot-leg break at the top of the steam generator generates the largest amount of debris. The second case of a hot-leg break at the reactor vessel generates a smaller volume of debris, but could damage the lower strainer due to missile generation.

The strainers are being fabricated by a contractor. Modification completion is scheduled for January 2003.

The meeting attendees are included as Enclosure 1. The presentation slides used by the licensee are accessible on the portion of the NRC website (www.nrc.gov) established for the public meetings associated with the Davis-Besse reactor vessel head degradation issue and in the Agencywide Documents Access and Management System (ADAMS) under ADAMS accession number ML023530626, and are included as Enclosure 2.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosures:

1. Meeting Attendees
2. Meeting Slides cc w/encls: See next page

Davis-Besse Nuclear Power Station, Unit 1 cc:

Mary E. OReilly Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-2206 Manager - Regulatory Affairs Zack A. Clayton FirstEnergy Nuclear Operating Company DERR Davis-Besse Nuclear Power Station Ohio Environmental Protection Agency 5501 North State - Route 2 P.O. Box 1049 Oak Harbor, OH 43449-9760 Columbus, OH 43266-0149 Director, Ohio Department of Commerce State of Ohio Division of Industrial Compliance Public Utilities Commission Bureau of Operations & Maintenance 180 East Broad Street 6606 Tussing Road Columbus, OH 43266-0573 P.O. Box 4009 Reynoldsburg, OH 43068-9009 Attorney General Department of Attorney General Regional Administrator 30 East Broad Street U.S. Nuclear Regulatory Commission Columbus, OH 43216 801 Warrenville Road Lisle, IL 60523-4351 President, Board of County Commissioners of Ottawa County Michael A. Schoppman Port Clinton, OH 43252 Framatome ANP 1911 N. Ft. Myer Drive President, Board of County Rosslyn, VA 22209 Commissioners of Lucas County One Government Center, Suite 800 Resident Inspector Toledo, OH 43604-6506 U.S. Nuclear Regulatory Commission 5503 North State Route 2 Terry Lodge, Convenor and Chair Oak Harbor, OH 43449-9760 Toledo Coalition for Safe Energy 316 N. Michigan Street, Suite 520 Randel J. Fast, Plant Manager Toledo, OH 43624-1627 FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station David Lochbaum, Nuclear Safety Engineer 5501 North State - Route 2 Union of Concerned Scientists Oak Harbor, OH 43449-9760 1707 H Street NW, Suite 600 Washington, DC 20006 Dennis Clum Radiological Assistance Section Supervisor Mr. Lew W. Myers Bureau of Radiation Protection Chief Operating Officer Ohio Department of Health FirstEnergy Nuclear Operating Company P.O. Box 118 Davis-Besse Nuclear Power Station Columbus, OH 43266-0118 5501 North State Route 2 Oak Harbor, OH 43449-9760

The meeting attendees are included as Enclosure 1. The presentation slides used by the licensee are accessible on the portion of the NRC website (www.nrc.gov) established for the public meetings associated with the Davis-Besse reactor vessel head degradation issue and in the Agencywide Documents Access and Management System (ADAMS) under ADAMS accession number ML023530626, and are included as Enclosure 2.

/RA/

Jon B. Hopkins, Senior Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosures:

1. Meeting Attendees
2. Meeting Slides cc w/encls: See next page DISTRIBUTION:

PUBLIC RidsOgcRp VGaddy PDIII-2 Reading RidsAcrsAcnwMailCenter RArchitzel RidsNrrDlpm (JZwolinski/TMarsh) RidsRgn3MailCenter (GGrant) SWeerakkody RidsNrrDlpmLpdiii (KMcConnell) MKotzalas JHannon RidsNrrDlpmLpdiii-2 (AMendiola) BJain CLipa RidsNrrPMJHopkins MMarshall JGolla RidsNrrLATHarris JLehning JLamb Package No.: ML023540073 Meeting Notice No.: ML023180530 Slides No.: ML023530626 ADAMS Accession: ML023460135 NRC-001 OFFICE PM:LPD3-2 LA:PD3-2 SC:LPD3-2 NAME JHopkins:rkb THarris AMendiola DATE 1/6/03 12/31/02 01/06/03 DOCUMENT NAME: G:\PDIII-2\Davisbes\11-26-02 Morn Mtg Summary.wpd OFFICIAL RECORD COPY

MEETING ATTENDEES NRC AND FENOC DISCUSSION OF CONTAINMENT SUMP MODIFICATION NOVEMBER 26, 2002 NRC FENOC J. Hopkins G. Leidich A. Mendiola R. Schrauder J. Hannon J. Powers S. Weerakkody D. Blakely R. Architzel K. Spencer J. Lehning D. Wuokko M. Marshall T. Schneider B. Jain J. Lamb ENERCON J. Golla C. Lipa R. Bryan A. Smith Los Alamos National Laboratory ITS Corp.

B. Letellier G. Zigler J. Dallman SAT Consultants, Inc. Morgan Lewis S. Traiforos S. Frantz LIS, Scientech PCI D. Raleigh G. Hart Union of Concerned Scientists NEI D. Lochbaum J. Butler McGraw-Hill G. Twachtman ENCLOSURE 1