November 26, 2002 Mr. Jeffrey S. Forbes Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - REVIEW OF RELIEF REQUESTS ASSOCIATED WITH THE FOURTH INTERVAL INSERVICE TESTING PROGRAM PLAN SUBMITTAL, DATED NOVEMBER 22, 2002 (TAC NO. MB6807)
Dear Mr. Forbes:
Nuclear Management Company, LLC (NMC) has submitted a request for review and approval of relief requests associated with the fourth 10-year interval inservice testing (IST) program plan at Monticello Nuclear Generating Plant. The submittal contains seven relief requests; two relief requests are first time submittals and five relief requests have been previously approved by the Nuclear Regulatory Commission (NRC) staff. The NRC staff received the relief requests associated with the fourth 10-year IST program plan submittal on November 25, 2002, via fax, but the letter was dated November 22, 2002, and NMC requested a completion date by March 9, 2003. This is a request to complete the relief requests associated with the fourth 10-year IST program plan submittal in 105 days, which is approximately three and a half months.
The NRC performance goals for licensing actions is to complete 95 percent in less than one year and 100 percent in less than two years. The NRC staff finds your proposed target date for completion of our review to be extremely aggressive, but the NRC staff will endeavor to complete its review consistent with the proposed schedule.
The NRC faces significant challenges to balance its work load, available resources, and budget constraints and achieve its performance goals. Accordingly, it is important that you plan your submittals to enable the NRC staff to perform its review in an efficient manner consistent with our performance goals and your schedule.
Sincerely,
/RA/
John G. Lamb, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-263 cc: See next page
ML023300465 OFFICE PM:PD3-1 LA:PD3-1 SC:PD3-1 NAME JLamb THarris LRaghavan DATE 11/26/02 11/26/02 11/26/02
Monticello Nuclear Generating Plant cc:
J. E. Silberg, Esquire Shaw, Pittman, Potts and Trowbridge 2300 N Street, N. W.
Washington, DC 20037 U.S. Nuclear Regulatory Commission Resident Inspectors Office 2807 W. County Road 75 Monticello, MN 55362 Site Licensing Manager Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637 Robert Nelson, President Minnesota Environmental Control Citizens Association (MECCA) 1051 South McKnight Road St. Paul, MN 55119 Commissioner Minnesota Pollution Control Agency 520 Lafayette Road St. Paul, MN 55155-4194 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Commissioner Minnesota Department of Health 717 Delaware Street, S. E.
Minneapolis, MN 55440 Douglas M. Gruber, Auditor/Treasurer Wright County Government Center 10 NW Second Street Buffalo, MN 55313 Commissioner Minnesota Department of Commerce 121 Seventh Place East Suite 200 St. Paul, MN 55101-2145 Adonis A. Neblett Assistant Attorney General Office of the Attorney General 445 Minnesota Street Suite 900 St. Paul, MN 55101-2127 Mr. Roy A. Anderson Executive Vice President and Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Xcel Energy, Inc.
414 Nicollet Mall Minneapolis, MN 55401