Text
Nuclear Management Company, LLC NM C Point Beach Nuclear Plant Committed to Nuclear Ecellence 6610 Nuclear Road Two Rivers, WI 54241 NRC 2002-0100 GL 97-02 November 15, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:
Dockets 50-266 And 50-301 Point Beach Nuclear Plant, Units 1 And 2 Monthly Operating Reports Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of October 2002.
Sincerely,
.J ia Sit
- e 1dent KYML Attachment cc:
J. D. Loock, PSCW NRC Region 11I NRC Senior Resident Inspector NRC Project Manager
Docket 50-266 and 50-301 NRC-2002-0100 Bcc:
R.A. Abdoo (WE)
R. A. Anderson(NMC)
INPO Records Center D. E. Day K. Kretzer A. J. Cayia Companies R. R. Grigg (WE)
J. E. Horvath E. J. Weinkam III (NMC) T. W. Hanna D. A. Weaver (WE)
B. Day T.H. Taylor File M. E. Reddemann G. A. Charnoff J. Freels C. S. Smoker (NMC)
G. D. Strharsky RSL File (3)
K. E. Peveler C. B. Jilek McGraw-Hill T. E. Ruiz R. R. Winget B. D. Kemp A-2
Docket 50-266 and 50-301 NRC-2002-0100 ATTACHMENT 1 Letter from Thomas J. Webb (NMC)
To Document Control Desk (NRC)
Dated November 8, 2002 Re: Monthly Operating Report - October 2002
OPERATING DATA REPORT DOCKET NO.
50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 11/08/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD October - 2002 DESIGN ELECTRICAL RATING (MWE-NET)
MAXIMUM DEPENDABLE CAPACITY (MWE-NET)
YEAR TO DATE CUMULATIVE, NUMBER OF HOURS REACTOR WAS CRITICAL NUMBER OF HOURS THE GENERATOR WAS ON LINE UNIT RESERVER SHUTDOWN HOURS NET ELECTRICAL ENERGY (MWH) 380.1 355.5 0.0 151,508.0 6,525.6 6,500.5 0.0 3,237,889.0 230,135.4 226,594.5 846.9 104,813,409.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997
- 1.
2.
515.0 510.0
- 3.
- 4.
- 5.
6.
MONTH
UNIT SHUTDOWNS DOCKET NO.
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
REPORTING PERIOD:
50-266 Point Beach, Unit 1 11/08/2002 Kim M. Locke 755-6420 (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction
- 4. Continuation E. Operator Training/license Examination F.Administrative
- 5. Other (Explain)
G. Operational Error (Explain) H.Other (Explain)
SUMMARY
Unit 1 average daily power for the month of October was 203.3 MWe.
Licensee Event Reports (LERs) submitted to the NRC in October:
LER 266/2002-001-01, Steam Generator Blowdown Valve Analyzed as Not Able to Close Against Full Differential Pressure.
Operating Events: AFW Recirc Orifice Flow Restriction October 2002 (Month/Year)
NO.
DATE TYPE DURATION REASON (1)
METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN (2)
COMMENTS 1
09/14/02 S
364.9 C
U1R27 REFUELING OUTAGE I
- -v OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIOD 50-301 POINT BEACH NUCLEAR PLANT - UNIT 2 11/08/02 Kim M. Locke 920-755-6420 October - 2002
- 1. DESIGN ELECTRICAL RATING (MWE-NET)
- 2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET)
YEAR TO DATE CUMULATIVE
- 3.
NUMBER OF HOURS REACTOR WAS CRITICAL
- 4. NUMBER OF HOURS THE GENERATOR WAS ON LINE
- 5.
UNIT RESERVER SHUTDOWN HOURS
- 6. NET ELECTRICAL ENERGY (MWH) 380,915.0 3,253,185.0 104,036,693.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997 515.0 512.0 MONTH 745.0 745.0 0.0 6,507.4 6,471.6 0.0 224,289.1 221,301.7 302.2
I UNIT SHUTDOWNS DOCKET NO.
UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
50-301 Point Beach, Unit 2 11/08/2002 Kim M. Locke 755-6420 REPORTING PERIOD: October 2002 (Month/Year)
(1) Reason A. Equipment Failure (Explain)
B. Maintenance or Test C. Refueling D. Regulatory Restriction E. Operator Training/license Examination F.Administrative G.Operational Error (Explain) H.Other (Explain)
(2) Method I Manual 2 Manual Trip/Scram 3 Automatic Trip/Scram
- 4. Continuation
- 5. Other (Explain)
SUMMARY
Unit 2 average daily power for the month of October was 511.3 MWe.
Licensee Event Reports (LERs) submitted to the NRC in October:
301/2002-002-01 Supplemental, Pressurizer Safety Valve Failed to Lift at Pressure.
Operating Events: AFW Recirc Orifice Flow Restriction NO.
DATE TYPE DURATION REASON (1)
METHOD OF CAUSE/CORRECTIVE°ACTIONS F:
FORCED (HOURS)
SHUTTING S:
SCHEDULED DOWN (2)
COMMENTS N/A N/A N/A N/A N/A N/A