October 2002 Monthly Operating Report for McGuire Nuclear Station & Revision 1 of Monthly Refueling Information Page for McGuire Unit 1 for Month of September 2002
ML023250180
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 11/14/2002
From: Dimmery T
Duke Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML023250180 (11)


Text

MkDuke t

tPower A Duke Energy Company Duke Power 526 South Church Street P.O. Box 1006 Charlotte, NC 28201-1006 November 14, 2002 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C.

20555

Subject:

Duke Energy Corporation McGuire Nuclear Station, Units 1 and 2 Docket Numbers 50-369 and 50-370 Monthly Performance and Operation Status-October, 2002 Please find attached information concerning the performance and operation status of the McGuire Nuclear Station for the month of October, 2002 and REVISION 1 of the monthly refueling information page for McGuire unit 1 for the month of September, 2002.

Any questions or comments may be directed to Roger A. Williams at (704) 382-5346.

Sincerely, Terry Dimmery, Manager Nuclear Business Support Attachment XC:

L.

A. Reyes, Regional Administrator USNRC, Region II Frank Rinaldi, Project Manager

USNRC, ONRR INPO Records Center Ms. Margaret Aucoin Nuclear Assurance Corporation Dottie Sherman, ANI Library American Nuclear Insurers Scott Schaeffer, Senior Resident Inspector

Document Control Desk U.S. NRC -

McGuire bxc:

C.

J.

Thomas (MG01RC)

RGC Site Licensing File ELL (EC050)

Operating Data Report Docket No.

Date Completed By

  • ,Telephone Operating Status
1. Unit Name:

McGuire 1

2. Reporting Period:

October 1, 2002-October 31, 2002

3. Licensed Thermal Power (MWt):

3411

4. Nameplate Rating (Gross MWe):

1305 *

5. Design Electrical Rating (Net Mwe):

1180

6. Maximum Dependable Capacity (Gross MWe):

1144

7. Maximum Dependable Capacity(Net MWe):

1100

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:

50-369 November 14,2002 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.

9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month

11. Hours in Reporting Period 745.0
12. Number of Hours Reactor was Critical 550.5
13. Reactor Reserve Shutdown Hours 0.0
14. Hours Generator On-Line 506.4
15. Unit Reserve Shutdown Hours 0.0
16. Gross Thermal Energy Generated (MWH) 1616089
17. Gross Electrical Energy Generated (MWH) 555424
18. Net Electrical Energy Generated (MWH) 528700
19. Unit Service Factor 68.0
20. Unit Availability Factor 68.0 2 1. Unit Capacity Factor (Using MDC Net) 64.5
22. Unit Capacity Factor (Using DER Net) 60.1
23. Unit Forced Outage Rate 3.2
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Initial Criticality Initial Electricity Commercial Operation YTD 7296.0 6630.5 0.0 6579.9 0.0 74559857

,7697549 7409895 90.2 90.2 92.3 86.1 1.3 Cumulative 183360.0 141561.5 0.0 140260.5 0.0 504211603 155751299 149224905 76.5 76.5 71.7 69.0 9.5 Achieved 3A - 11/14/2002

)

Page: 1 of 2 UNIT SHUTDOWNS DOCKET NO. 50-369 UNIT NAME: McGuire 1 DATE: November 14, 2002 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: October, 2002 (1) Reason A - Equipment failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)

H - Other (Explain)

(2) Method I - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C - 11/14/2002 No.

Date:

Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

2 10/01/02*

S 142.80 C

4 END OF CYCLE 15 REFUELING OUTAGE OUTAGE DELAY OF 1.17 DAYS DUE TO DIESEL GENERATOR

,3 10/06/02 S

28.00 A

GOVERNOR MODULE MODIFICATION 4-,

OUTAGE DELAY OF 0.46 DAYS DUE TO REACTOR COOLANT LEVEL 4

10/08/02 S

11.00 A

4 INDICATION MISMATCH 10 0

1OUTAGE DELAY OF 0.58 DAYS DUE TO CONTROL ROD DRIVE 5

10/08/02 S

14.00 A

4MECHANISM LATCHING TOOL MALFUNCTION "6

1 91OUTAGE DELAY OF 0.63 DAYS DUE TO TURBINE DRIVEN FEEDWATER

-6 :

10/09/02 S

15.00 A

4PUMP ISOLATION VALVE OUTAGE DELAY OF 0.43 DAYS DUE TO MISCELLANEOUS REFUELING 7

10/09/02 S

10.23 C

4 OUTAGE ACTIVITIES Summary:

McGuire unit 1 began the month in end-of-cycle 15 refueling outage. The end-of-cycle 15 refueling outage spanned 26.26 days. The outage was delayed for the following; 1.17 days due to diesel generator governor module modification, 0.46 days due to reactor coolant level indication mismatch, 0.58 days due to control rod drive mechanism latching tool malfunction, 0.63 days due to turbine driven feedwater pump isolation valve, 0.43 days due to miscellaneous refueling activities. The unit was placed on-line 10/10/02 at 0502. The unit increased to approximately 17% power and held from 0700 to 1000 when the unit began decreasing power and was taken off-line 10/10/02 at 1229 to perform the turbine overspeed trip test and to repair a flange leak on main steam piping. The unit remained critical at approximately 13% power. The unit was placed on-line 10/11/02 at 0604. During power escalation, the unit held at 30% power from 10/11/02 at 1200 to 1758 due to initial flux mapping. On 10/13/02 at 0000 to 0521 the unit held at (Cont'd)

Page: 2 of 2 UNIT SHUTDOWNS DOCKET NO. 50-369 UNIT NAME: McGuire 1 DATE: November 14, 2002 COMPLETED BY: Roper Williams TELEPHONE: 704-382-5346 REPORT MONTH: October. 2002 (1) Reason A - Equipment failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C-11/14/2002 No.

Date:

Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

8 10/10/021 S

1.00 B

TURBINE OVERSPEED TRIP TEST 9

10/10/02 F

16.58 A

FLANGE LEAK ON MAIN STEAM PIPING Summary:

78% power due to flux mapping. The unit resumed power escalation, and held at approximately 90% power from 1200 to 1227 for normalized delta T adjustments. The unit returned to 100% full power on 10/14/02 at 1445 and operated at or near 100% full power the remainder of the month.

MONTHLY REFUELING INFORMATION REQUEST

1.

Facility name:

McGuire Unit 1

2.

Scheduled next refueling shutdown: March 2004

3.

Scheduled restart following refueling: April 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1107

8.

Present licensed fuel pool capacity: 1463 Size of requested or planned increase:

9.

Projected date of last refueling which can be accommodated by present license capacity:

November 2005 DUKE POWER COMPANY DATE: November 14,2002 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

Operating Data Report Docket No.

Date Completed By Telephone Operating Status

1. Unit Name:

McGuire 2

2. Reporting Period:

October 1, 2002-October 31, 2002

3. Licensed Thermal Power (MWt):

3411

4. Nameplate Rating (Gross MWe):

1305 *

5. Design Electrical Rating (Net Mwe):

1180

6. Maximum Dependable Capacity (Gross MWe):

1144

7. Maximum Dependable Capacity(Net MWe):

1100

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:

50-370 November 14,2002 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMNVe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.

9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month

11. Hours in Reporting Period 745.0
12. Number of Hours Reactor was Critical 745.0
13. Reactor Reserve Shutdown Hours

ý 0.0

14. Hours Generator On-Line 745.0
15. Unit Reserve Shutdown Hours 0.0
16. Gross Thermal Energy Generated (MWH) 2539239
17. Gross Electrical Energy Generated (MWH) 873834
18. Net Electrical Energy Generated (MWH) 841142
19. Unit Service Factor 100.0
20. Unit Availability Factor 100.0
21. Unit Capacity Factor (Using MDC Net) 102.6
22. Unit Capacity Factor (Using DER Net) 95.7
23. Unit Forced Outage Rate 0.0
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Initial Criticality Initial Electricity Commercial Operation YTD 7296.0 6504.0 0.0 6477.1 0.0 96429304 7537482 7253719 88.8 88.8 90.4 84.3 2.6 Cumulative 163656.0 134322.8 0.0 133069.0 0.0 513820295

-152834021 146722998 81.3 81.3 79.4 76.0 5.6 Achieved 3A - 11/14/2002

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-370 UNIT NAME: McGuire 2 DATE: November 14, 2002 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: October, 2002 No.

Date:

Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Sch le HSEd No.

No Outages for the Month Summary:

(1) Reason A - Equipment failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Traimng/License Examination F - Administrative G - Operator Error (Explain)

H - Other (Explain)

(2) Method 1 - Manual 2 - Manual Tnp/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C-11/14/2002

MONTHLY REFUELING INFORMATION REQUEST

1.

Facility name:

McGuire Unit 2

2.

Scheduled next refueling shutdown: September 2003

3.

Scheduled restart following refueling: October 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1041 (c) in the ISFSI: 160

8.

Present licensed fuel pool capacity: 1463 Size of requested or planned increase: -

9.

Projected date of last refueling which can be accommodated by present license capacity:

June 2003 DUKE POWER COMPANY DATE: November 14,2002 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT SEPTEMBER 2002

1.

Personnel Exposure The total station liquid release for SEPTEMBER has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for SEPTEMBER has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

REVISION 1 MONTHLY REFUELING INFORMATION REQUEST

1.

Facility name:

McGuire Unit 1

2.

Scheduled next refueling shutdown: Currently Refueling

3.

Scheduled restart following refueling: October 2002 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4.

Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

6.

Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).

7.

Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1107

8.

Present licensed fuel pool capacity: 1463 Size of requested or planned increase: -

9.

Projected date of last refueling which can be accommodated by present license capacity:

November 2005 DUKE POWER COMPANY DATE: October 15, 2002 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346