ML023100283
| ML023100283 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 11/01/2002 |
| From: | Stramback G General Electric Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| MFN-02-084, TAC MB5603 | |
| Download: ML023100283 (2) | |
Text
GE Nuclear Energy Nuclear Services 175 Curtner Ave M/C 747 San Jose, CA 95125 (408) 925-1913, Fax (408) 925-6710 E-mail george stramback@gene ge com MFN 02-084 November 1, 2002 U.S Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20852-2738 Attention:
Chief, Information Management Branch Program Management Policy Development and Analysis Staff
Subject:
Request for Withholding Information from Public Disclosure Pilgrim Nuclear Power Station (TAC No. MB5603)
By Reference 1, the NRC denied GE's request to withhold from public disclosure the Pilgrim Safety Analysis Report for Thermal Power Optimization (TSAR) NEDC-33050P, Revision 0. Entergy Nuclear Operations, Inc (ENOI) submitted the TSAR to the NRC by Reference 2. The TSAR was provided to support a requested license amendment by ENOI and was not submitted in a rule making proceeding. GE hereby requests, pursuant to 10 CFR 2.790(c) that the referenced Pilgrim TSAR be withdrawn.
GE provided ENOI with a revision of the TSAR, which revises the identification of the proprietary information in the TSAR, as well as revising the basis for the proprietary protection. The proprietary information is protected by a simple redaction as requested by your letter (Reference 1). A proprietary and a non-proprietary version of the TSAR were provided. GE, as the owner of Revision 0 of this information, requests that Revision 0 of both of the TSARs be withdrawn. ENOI will be submitting the revised TSAR shortly to support its license application.
If you have any questions about the information provided here please contact, Ed Schrull at (408) 925-2224 or myself.
Sincerely, George Stramback Regulatory Services, Project Manager GE Nuclear Energy (408) 925-1913 george.stramback@ gene.ge.com
\\
MFN-02-084 Page 2
References:
- 1. NRC Letter, TL Tate (NRC) to GB Stramback (GE), Request for Withholding Information From Public Disclosure Pilgrim Nuclear Power Station (TAC No.
MB5603), dated October 2, 2002.
- 2. ENOI Letter, Licensing Amendment Request, Appendix K Measurement Uncertainty Recovery - Power Uprate Request, dated July 5, 2002 cc:
Mr. TL Tate NRR Project Manager Region I U.S. Nuclear Regulatory Commission Mail Stop 0-8 B1A One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. Bryan Ford ENOI Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 MJ Dick (GE/San Jose)
JF Klapproth (GE/San Jose)
MA Lalor (GE/San Jose)
ED Schrull (GE/San Jose)