October 29, 2002 MEMORANDUM TO:
Davis-Besse Nuclear Power Station IMC 0350 Panel FROM:
John A. Grobe, Chairman, Davis-Besse Oversight Panel /RA/
SUBJECT:
MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE OVERSIGHT PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held October 15, 2002. Attached for your information are the minutes from the internal meeting of the Davis-Besse Oversight Panel and the Open Action Items List.
Attachments: As stated cc w/att:
S. Rosenberg, OEDO W. Dean, NRR A. Mendiola, NRR D. Pickett, NRR S. Bloom, NRR J. Dyer, RIII J. Caldwell, RIII G. Grant, RIII S. Reynolds, RIII C. Lipa, RIII D. Hills, RIII D. Passehl, RIII D. Simpkins, RIII J. Jacobson, RIII S. Burgess, RIII R. Lickus, RIII S. Thomas, RIII M. Holmberg, RIII J. Collins, RIII DB0350
MEMORANDUM TO:
Davis-Besse Nuclear Power Station IMC 0350 Panel FROM:
John A. Grobe, Chairman, Davis-Besse Oversight Panel
SUBJECT:
MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE OVERSIGHT PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held October 15, 2002. Attached for your information are the minutes from the internal meeting of the Davis-Besse Oversight Panel and the Open Action Items List.
Attachments: As stated cc w/att:
S. Rosenberg, OEDO W. Dean, NRR A. Mendiola, NRR D. Pickett, NRR S. Bloom, NRR J. Dyer, RIII J. Caldwell, RIII G. Grant, RIII S. Reynolds, RIII C. Lipa, RIII D. Hills, RIII D. Simpkins, RIII J. Jacobson, RIII K. Riemer S. Burgess, RIII R. Lickus, RIII S. Thomas, RIII M. Holmberg, RIII J. Collins, RIII DB0350 DOCUMENT NAME: G:\\Davis-Besse 0350\\internalmtgminutes\\internalmtgminutes1015.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII RIII NAME DPassehl/klg CLipa JGrobe DATE 10/ 16/02 10/20/02 10/29/02 OFFICIAL RECORD COPY
MEETING MINUTES:
Internal IMC 0350 Oversight Panel Meeting Davis-Besse Nuclear Power Station DATE:
October 15, 2002 TIME:
10:30 a.m. Central ATTENDEES:
J. Grobe C. Lipa W. Dean S. Thomas M. Farber K. OBrien J. Hopkins D. Passehl B. Jorgensen V. Mitlyng J. Collins Agenda Items:
1.
Reports from Staff Marty Farber reported on the status of his activities under the System Health building block, indicating that licensee findings have continued to expand the scope, and a total of 15 common problem areas have been identified. These involve such things as calculation errors, USAR, HELB, and EQ deficiencies. The findings were described as not surprising to the team. Marty indicated that two more weeks of onsite inspection are tentatively targeted for the weeks of 10/21 and 11/4. Marty said Bruce Bartletts team inspection findings (calculation errors, legalistic rationales to avoid or minimize work, and related engineering support concerns) need to be evaluated and factored into the system health arena. Marty indicated the licensees work on latent issues reviews had led to declaring AFW, SW and EDGs inoperable which reflected a proper conservative approach to the findings.
Marty also briefly indicated the re-start testing building block is in an uncertain condition as to when activities will be completed and ready for inspection. The ILRT now appears likely to occur in December, and integrated testing for MODE changes and certain post-maintenance/post-modification testing has not been scheduled yet, either.
Ken OBrien reported on the status of inspection in the Program Compliance building block. His schedule has also been impacted by delays in licensee completion of several program reviews. Ken indicated that he now tentatively plans on a week on site in early November, and another in early December, when licensee progress may be adequate to justify resuming inspection work. The licensees decision-making on the first two areas examined (boric acid control and corrective action) were characterized as hitting the mark, so further NRC inspection in those two areas is not needed. In the area of Quality Assurance, the licensee has decided to do a Phase II review.
Christine Lipa announced, in light of the continuing scheduling uncertainties, a meeting will be arranged for early next week and the entire proposed inspection schedule will be re-examined. Some inspections may be stopped and the results documented, rather
than continue to await developments from the licensee. This includes the system health and program compliance team inspections discussed above.
Site activities (RIO)
Scott Thomas briefed the Davis-Besse Oversight Panel on current site activities noting the following:
The case studies he (Scott) observed both included senior management characterizing the facility status as being beyond the discovery phase and turning the corner to recovery. This does not square entirely with the feedback from inspection teams that discovery is continuing, and the scope of work activities is still expanding.
Some among licensee senior management have also begun to express some frustration about NRC needs not being fully defined, such that the licensee does not know the type and quantity of resources necessary to address those needs.
The research project on the vessel head specimens was an example.
A licensee evaluation of issues identified during the shutdown is being displayed around the plant. It shows 90% are being self-identified and 10% are being NRC-identified.
Work to restore the startup transformer is continuing with a target completion date of 11/17.
Both emergency diesel-generators remain inoperable but available with exhaust system upgrades to provide tornado missile protection targeted to be complete by 10/23.
Review of action items (panel)
The panel reviewed the list of open action items, with discussions and actions as follows:
Item 71 was discussed. NRR forwarded a draft report with the results of the review of the licensees Revision 1 to the Technical Root Cause. The draft report is being reviewed, with some discussion regarding whether it is conclusionary enough. The report will be made final once any comments are received and considered.
Item 72 was discussed. The LLTF report has been received and is being reviewed so as to extract any observations impacting the Oversight Panel. Christine Lipa will attend the LLTF public meeting at the plant on November 6, then plans to meet with the LLTF personnel present the following day to ensure a full understanding of the observations, so they can be addressed in an appropriate manner.
Item 74 was discussed. The subject matrix document remains incomplete/unofficial, but it is getting pretty close.
Item 82 was discussed. This is related to Item 72 and ensuring the Panel understands the observations and context of the LLTF.
Item 85 was discussed. The Office of Research continues to evaluate the need for additional study of additional specimens from the old vessel head. The continuing open status of this item is impacting our plan to update the CAL and remove the line item related to the quarantine.
Item 99 was discussed. Work on this item is expected to be completed soon.
Item 112 was discussed. The monthly public meeting date for December (10 or 11) is still being finalized. Jack Grobe expressed a preference for Tuesdays, both in December (the 10th) and in the months thereafter. Christine Lipa also has the action to pursue the scheduling of dates for possible additional meetings in January, February and March 2003.
Item 114 was discussed. No new news on a potential site visit by Brian Sheron - Jon Hopkins will continue to follow developments.
Item 120 was added. Jon Hopkins will follow up on a request from the ACRS for an update (reportedly in early November), to determine what the needs of the Committee are and what their exact schedule is. He will report this information back at a future meeting of the Panel.
Licensing Issues/Actions (DLPM) - status sheet The status of Davis-Besse licensing activities and ticket tracking was presented by Jon Hopkins:
The 2.206 petition response letter remains in management concurrence; it could be signed out as early as today (10/15) or tomorrow.
Work on the code relief and license amendments relating to use of the Midland reactor vessel head has continued with no significant issues identified so far.
No new green ticket activity of note.
2.
IMC 0350 Panel Business Inspection Schedule The Panel once again had extensive discussions of inspection scheduling, since the schedules for several inspections remain unsettled. The date(s) when the licensee will have sufficient information to justify further inspection activities remains unclear. The Oversight Panel expects to have a special meeting early next week to consider how to manage resources and scheduling in light of limited licensee information.
Process Plan Dave Passehl has updated and distributed a revised Process Plan, requesting any comments or other feedback preparatory to a detailed discussion of the Plan at the Panel meeting scheduled for 10/22.
Restart Checklist - Investigations Two proposed additions to the NRC restart checklist were discussed. These were an item on the radiation protection program and one on containment sump issues. The focus in radiation protection was characterized as being on occupational exposure control and related work planning - derived from the special inspection of potential over-exposures from intake of alpha-emitting isotopes. The Panel will look to approve the revised checklist next week.
Licensee Return to Service Plan No new discussions.
3.
NRC/Licensee weekly calls No call this week, due to monthly public meetings at the site on Wednesday, 10/16.
4.
Utilization of the Web Page Jon Hopkins will post items on the Web Page this week, in Steve Blooms absence. A couple of sets of meeting transcripts have been entered into ADAMS and sent to NRR to be posted.
5.
Future Activities/Plans/Meetings Next panel meeting: Tuesday 10/22 at 2:00 p.m. EDT, 1:00 CDT Monthly allegations briefing to be added to agenda.
6.
Discuss how to handle public or staff comments, questions, allegations, and concerns received by phone, fax, letter, email, or at public meetings.
Potential issues which may arise at tomorrows meetings, either with the licensee or with the public, were discussed. The issues could include: concrete spalling and associated repairs; stains on the reactor vessel bottom head; scheduling (FENOCs and NRCs);
and Congressional (2.206 Petition, Sen. Voinovich) interest and developments.
IMC 0350 Oversight Panel Action Items Item Number Action Item (Date generated)
Assigned to Comments 24a Discuss making information related to HQ/licensee calls publicly available Panel Discuss by June 30, after safety significance assessment complete.
6/27 - Invite Bateman to panel mtg.
To discuss what else is needed to closeout the CAL (i.e. quarantine plan). 7/2 - NRR not yet ready to discuss. 7/16 - See if procedures have changed on CAL closeout -
does JD need to send letter? 7/18
- Discussed - is there an applicable regional procedure? 8/6 -
Discussed. Need to determine the final approach on the core removed from the head and the final approach on the head before the quarantine can be lifted. 8/22 -
Revisit action item after letter sent to licensee confirming plans with old vessel head (head may be onsite longer than originally anticipated) 8/29 - Memo to be sent to Region, with a letter to go out next week. 10/01-Discussed.
- 1) Conduct NRC staff survey-due 10/7 2)Memo to NRR - due 10/11
- 3) Region to issue letter 26 Provide licensee with inspection schedule Panel 7/16 - pending 7/18 - J. Jacobson working - will follow issuance of restart checklist. Est due date 8/2 to include scheduled and TBD inspections. 8/22 - System health dates now set - will likely send out schedule next week. 8/27 -
Discussed - on track to send out next week. 8/29 - discussed, on track. 10/1 - Discussed. Issue schedule
Item Number Action Item (Date generated)
Assigned to Comments 54a Review TSP amendment and advise the panel on the need for a TIA on Davis-Besse (7/2)
D. Pickett 7/9 - Discussed. Will wait for response from licensee. 7/16 -
Discussed - added action item 54b.
8/6 - Sent to the licensee on7/22 and a response is due by 8/22.
8/22 - Discussed - need to check if response has been received. 8/27
- Received response - DRS is reviewing - will fax to NRR for 54b.
8/29 - Discussed, DRS report of response to be issued to panel prior to item 54b. 10/1-Discussed.
DRS coordinating with NRR 54b Initiate correspondence w/NRR to evaluate generic implications (7/16)
T. Mendiola 7/18 - Memo will be sent to Hannons group. 8/6 - Discussed -
not yet issued. 8/13 - Discussed -
need info from 54a first. 10/1 -
Discussed. Forward to B. Bateman
- due 10/18.
71 Discuss review and documentation of the Technical Root Cause and determine if the action is in NRRs work management system. (8/6)
Sands Dean Panel Lipa 8/6 - Invite to 8/13 mtg. 8/13 -
Discussed. S. Coffin to provide feeder to Lipa regarding conclusions due 8/30 draft. 8/22 -
Discussed - NRR will email draft for review/ need to determine how final input should be sent from NRR to RIII. 8/27 - Discussed draft input and process for formal transmittal from NRR to RIII. 8/29
- Deferred to 9/5 meeting. 9/18 -
On hold due to crack 10/1 -
Discussed. Recd and under review 10/8 - NRR to forward Revision 1 to Region III 10/15-Discussed.
Item Number Action Item (Date generated)
Assigned to Comments 72 Review LLTF observations and determine appropriate closeout. (8/6) Review for safety issue/ AMS/OI/new items.
Lipa/Collins 8/13 - Discussed. Items reviewed for allegations. No new allegations identified. Info related to ongoing investigations will be forwarded to OI. 8/22 - Discussed - need to keep this item open as a reminder to consider outstanding LLTF items. 8/29 - Discussed - leave open. 10/1 - Discussed. 10/8 -
Discussed. Report to be discussed 10/9, schedule public meeting 11/6 10/15 - Discussed. Lipa to attend public meeting 73 Send feedback form on IMC 0350 procedure to IIPB (8/6)
Lipa Mendiola 8/6 - Generate feedback after panel meetings reduced to once per week. 8/29 - Discussed - no change. 10/1 - Discussed.
74 Matrix strategy for UCS and other requests. (8/8)
Lipa 8/13 - Discussed. 8/22 -
Discussed - matrix is being developed will send out for review when ready. 8/29 - Discussed -
matrix has been started. 10/1&
10/15 Discussed.
82 Circle back with LLTF to put their observations into context (8/8)
Grobe 10/1& 10/15 - Discussed. Related to Item 72.
83 Verify results of ongoing research related to the technical root cause evaluation has not changed NRC/DE conclusions (8/13)
Panel Coffin 85 Send letter/action plan to the licensee regarding actions required to be completed to close CAL item related to quarantine (8/20)
Dean (DE)
Hopkins 8/22 - Discussed - NRR will send draft to RIII by 8/30. 8/27 -
Discussed - letter being drafted and should be ready next week.
9/19-On hold due to crack - get letter out to licensee re: from Mode 3 to Mode 2. 10/8 - Discussed.
Memo is with Mendiola at the start of concurrence review. 10/15 -
Discussed.
Item Number Action Item (Date generated)
Assigned to Comments 88 Develop draft proposal on how to assess significance/respond to TIA (8/20)
Burgess 8/27 - Working to a due date of 8/30 to present to the panel next week. 10/1 - Discussed.
89 Provide report input on Framatome inspection of records for the new vessel head (8/27)
R. McIntyre M. Holmberg Will be feeder to Mels need for 9/17 public mtg. 9/17 - Plan to send this week to Mel. 9/24 -
Report expected out next week.
10/8 - Discussed. Feeder report had been received, Mendiola to review.
90 Response to feedback form from 8/20 Public Meeting (8/29)
J. Strasma 91 Call McClosky to discuss docketing Return to Service Plans (9/3)
Lipa 9/17 - Called - need to check back.
10/1 - Discussed. Jack to discuss with L. Myers 95 Interpret CAL & TS and define which mode change needs approved (9/5)
Lipa Thomas 10/1 - Discussed.
96 Ongoing phase 3 observations of management and human performance following restart (9/5)
Lipa 97 Bulletins 2002-01 and 2002-02 response and acceptance (9/5)
NRR 98 Poll staff for differing opinions (9/5)
Panel Incorporate into Process Plan 10/1 - Discussed.
99 Bring to panel all 95002/95003 attributes (9/5)
Jacobson/
Lipa 9/24 - Decision for C. Lipa to discuss item with J. Jacobson.
10/1 - Discussed. Due 10/11.
10/15 - Discussed.
102 NRR Approval of Concern 3 for Licensee Investigation Report for Allegation No. RIII-02-A-0110 (9/12)
Mendiola 10/1 - Discussed. TSP calculations under 54a and 54b address this concern.
Item Number Action Item (Date generated)
Assigned to Comments 103 Issue 3 memos to staff -
forward emails to DB0350/RES/NRR/RIII (9/17)
Dean/Grobe 10/8 - Complete.
104 Add UCS to service lists in RIII and NRR (9/17)
Lipa/
Mendiola 10/8 -Complete 107 When AIT F/U IR is issued, consider item on records& communication accuracy (9/17)
Panel 10/1-Discussed 110 Determine when licensee will docket technical root cause and determine when the safety analysis will be delivered to the NRC (9/19)
J. Hopkins 10/1-Discussed 111 Coordinate with LLTF to brief state and county officials (9/19)
R. Lickus 10/8 - Complete 112 Contact Nora (Myers secretary) to explain feedback and establish future ROP dates(9/19)
C. Lipa 10/1-Discussed. 10/8 - Dates for Oct. 16 & Nov. 13 final, working on December, January, February &
March. 10/15-Discussed. Grobe prefers Tuesdays for the months ahead.
113 Remove UCS representative from service lists 90 days after DD is issued (9/24)
C. Lipa/
A.Mendiola 10/1-Discussed 114 Details of expected visit to site (9/24)
Hopkins/
Sheron 10/1 - Discussed. 10/8 -
Discussed, Due 10/15. 10/15 -
Discussed.
116 Inform licensee that completeness and accuracy of records issue may be added to restart checklist (9/24)
Grobe 10/1-Discussed
Item Number Action Item (Date generated)
Assigned to Comments 117 Provide a report on all licensing actions for DB to the DB Oversight Panel (9/24)
Hopkins 10/1-Discussed 118 Produce a photo view book that would have before and after photos of corrective maintenance items. (9/24)
Jorgensen 10/1 Discussed 119 Discuss with OI, need to bring to ARB (10/01)
Passehl Due 10/15 120 Request from ACRS for an update to determine the Committee needs and exact schedule. (10/15)
Hopkins