October 31, 2002 Mr. Glen A. Watford, Manager Fuel Engineering Services Global Nuclear Fuel - Americas, LLC Castle Hayne Road, Mailcode A16 Wilmington, NC 28401
SUBJECT:
GLOBAL NUCLEAR FUEL - AMERICAS, LLC, REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR QUAD CITIES NUCLEAR POWER STATION, UNIT 1 (TAC NO. MB5209)
Dear Mr. Watford:
By letter dated October 18, 2002, Exelon Generation Company, LLC, submitted an affidavit dated October 17, 2002, executed by Jens G. Andersen on behalf of Global Nuclear Fuel -
Americas, LLC (GNF-A), requesting that the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790:
Attachment A (Response to Request for Additional Information Relating to Amendment Request for Cycle 18 Safety Limit Minimum Critical Power Ratio).
Attachment B, a nonproprietary version of Attachment A, has been placed in the Nuclear Regulatory Commissions (NRCs) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
The information identified in Attachment A is classified as proprietary because it contains details of GNF-As fuel design and licensing methodology. The development of the methods used in these analyses, along with the testing, development, and approval of the supporting methodology was achieved at a significant cost, on the order of several million dollars, to GNF-A or its licensor.
Public disclosure of the information sought to be withheld is likely to cause substantial harm to GNF-As competitive position and foreclose or reduce the availability of profit-making opportunities. The fuel design and licensing methodology is part of GNF-As comprehensive boiling-water reactor safety and technology base, and its commercial value extends beyond the original development cost. The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation process. In addition, the technology base includes the value derived from providing analyses done with NRC-approved methods.
The research, development, engineering, analytical, and NRC review costs comprise a substantial investment of time and money by GNF-A or its licensor.
The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial.
GNF-As competitive advantage will be lost if its competitors are able to use the results of the GNF-A experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of the information to GNF-A would be lost if the information were disclosed to the public. Making such information available to competitors without their having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall, and deprive GNF-A of the opportunity to exercise its competitive advantage to seek an adequate return on its large investment in developing these very valuable analytical tools.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, Attachment A of the submitted information, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2296.
Sincerely,
/RA/
Carl F. Lyon, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-254 cc: See next page
Quad Cities Nuclear Power Station Units 1 and 2 cc:
Site Vice President - Quad Cities Nuclear Power Station Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Quad Cities Nuclear Power Station Plant Manager Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Regulatory Assurance Manager - Quad Cities Exelon Generation Company, LLC 22710 206th Avenue N.
Cordova, IL 61242-9740 Quad Cities Resident Inspectors Office U.S. Nuclear Regulatory Commission 22712 206th Avenue N.
Cordova, IL 61242 William D. Leech Manager - Nuclear MidAmerican Energy Company P.O. Box 657 Des Moines, IA 50303 Vice President - Law and Regulatory Affairs MidAmerican Energy Company One River Center Place 106 E. Second Street P.O. Box 4350 Davenport, IA 52808 Chairman Rock Island County Board of Supervisors 1504 3rd Avenue Rock Island County Office Bldg.
Rock Island, IL 61201 Regional Administrator U.S. NRC, Region III 801 Warrenville Road Lisle, IL 60532-4351 Illinois Department of Nuclear Safety Office of Nuclear Facility Safety 1035 Outer Park Drive Springfield, IL 62704 Document Control Desk-Licensing Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President - Nuclear Services Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President Mid-West Operations Support Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Senior Vice President Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President - Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Director - Licensing Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
Quad Cities Nuclear Power Station Units 1 and 2 Senior Counsel, Nuclear Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Dresden and Quad Cities Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial.
GNF-As competitive advantage will be lost if its competitors are able to use the results of the GNF-A experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of the information to GNF-A would be lost if the information were disclosed to the public. Making such information available to competitors without their having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall, and deprive GNF-A of the opportunity to exercise its competitive advantage to seek an adequate return on its large investment in developing these very valuable analytical tools.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, Attachment A of the submitted information, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You should also understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2296.
Sincerely,
/RA/
Carl F. Lyon, Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-254 cc: See next page DISTRIBUTION:
PUBLIC A. Mendiola R. Caruso T. Huang OGC ACRS PD3-2 r/f F. Lyon C. Rosenberg M. Siemien M. Ring, RIII ADAMS Accession Number: ML022950052 OFFICE PDIII-2/PM PDIII-2/LA OGC PDIII-2/SC NAME FLyon CRosenberg MPSiemien AMendiola DATE 10/22/02 10/22/02 10/29/02 10/29/02 OFFICIAL RECORD COPY