Category:E-Mail
MONTHYEARML24026A2802024-01-25025 January 2024 Acceptance Review for Virgil C. Summer Relief Requests RR-5-V1, RR-5-V2, and RR-5-V3 (EPIDs L-2023-LLR-0067, L-2023-LLR-0068, and L-2023-LLR-0069) (Email) ML23270B8712023-09-27027 September 2023 NRR E-mail Capture - Draft RAIs for License Amendment Request (LAR) to Revise the Virgil C. Summer Nuclear Station (VCSNS) Unit 1 Emergency Plan (L-2023-LLA-0083) ML23193A9552023-07-12012 July 2023 NRR E-mail Capture - Acceptance Review for VC Summer and Surry Relief Request (L-2023-LLR-0029) ML23186A1392023-07-0505 July 2023 NRR E-mail Capture - Acceptance Review for VC Summer Emergency Plan (EP) License Amendment Request (LAR) (L-2023-LLA-0083) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request ML23044A3392023-02-13013 February 2023 NRR E-mail Capture - Acceptance Review for Change to Reactor Vessel Surveillance Capsule Schedule (L-2023-LLL-0002) ML23027A0122023-01-26026 January 2023 002 Radiation Safety Baseline Inspection Information Request ML23026A0152023-01-23023 January 2023 NRR E-mail Capture - Feb 14, 2023 Public Meeting with the Dominion Energy to Discuss a Planned Emergency Preparedness Submittal to Relocate the Emergency Operations Facility for the VC Summer Power Station - Dominion Slides ML22263A0502022-09-19019 September 2022 NRR E-mail Capture - Draft Request for Additional Information for Proposed Alternative Request RR-4-26 Extension of Steam Generator Primary Inlet Nozzle Dissimilar Metal Weld Inspection Interval V.C. Summer Unit 1 ML22194A9422022-07-13013 July 2022 NRC 50.59 Inspection (IP 71111.17T) Information Request ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22173A0292022-06-17017 June 2022 NRR E-mail Capture - Acceptance Review for Summer to Defer Weld Examinations (L-2022-LLR-0052) ML22139A2302022-05-19019 May 2022 NRR E-mail Capture - Acceptance Review for Summer TS 4.6.2.1.d LAR (L-2022-LLR-0060) ML22139A2322022-05-19019 May 2022 NRR E-mail Capture - Acceptance Review for Summer TSTF-491 LAR (L-2022-LLR-0059) ML22084A4052022-03-25025 March 2022 NRR E-mail Capture - Acceptance Review for Summer Dissimilar Metal Weld Inspection Interval (L-2022-LLR-0033) ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21333A1892021-11-29029 November 2021 NRR E-mail Capture - Draft RAI for Summer LAR Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b, (TSTF-425) ML21253A1352021-09-0808 September 2021 Document Request for VC Summer Nuclear Station - Radiation Protection Inspection - Inspection Report 2021-04 ML21197A0432021-07-15015 July 2021 VCS ISI 2021004 RFI - Combined ML21187A1242021-06-28028 June 2021 10CFR Part 21 Update - Deviation Identified in the Bolting Utilized to Maintain Seismic Qualification ML21173A1782021-06-22022 June 2021 NRR E-mail Capture - Acceptance Review - Summer LAR Unit Staff Qualification Relocation TS to Quality Assurance Program Description (QAPD) ML21145A0222021-05-24024 May 2021 003 Radiation Safety Baseline Inspection Information Request ML21131A0402021-05-11011 May 2021 NRR E-mail Capture - V.C. Summer, Unit 1 - Final RAI for the Spring 2020 RFO Sgtir Review ML21125A1942021-05-0505 May 2021 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2021-LLA-0064) ML21020A0562021-01-20020 January 2021 Email Capture Upcoming V.C. Summer POV Inspection (IP71111.21N.02) Information Request ML20342A1822020-12-0707 December 2020 NRR E-mail Capture - Final RAI for Summer LAR - TS 3.6.4 ML20342A3822020-12-0707 December 2020 NRR E-mail Capture - Final RAIs for Summer Fs LOCA LAR ML20321A2112020-11-16016 November 2020 NRR E-mail Capture - Summer, Unit 1 - Final RAIs for the SG Tube Inspection Report Review ML20316A0122020-11-0404 November 2020 NRR E-mail Capture - V.C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2020-LLR-0141) ML20302A2032020-10-28028 October 2020 NRR E-mail Capture - V.C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2020-LLR-0141) ML20260H4262020-09-0303 September 2020 NRR E-mail Capture - Acceptance Review for Fleet Relief Request for Code Case N-885 ML20178A5892020-06-26026 June 2020 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit 1 - Acceptance Review of the Fsloca LAR (L-2020-LLA-0124) ML20178A5932020-06-23023 June 2020 NRR E-mail Capture - VC Summer Unit Alternate Request RR-4-19 ML20178A5912020-06-23023 June 2020 NRR E-mail Capture - VC Summer Unit Alternate Request RR-4-21 ML20149K4262020-05-21021 May 2020 NRR E-mail Capture - V. C. Summer, Unit 1 - Acceptance of License Amendment Request (LAR-20-142) Related to TS 3.6.4, Containment Isolation Valves (L-2020-LLA-0092) ML19218A3742019-08-0606 August 2019 NRR E-mail Capture - Virgil C. Summer, Unit 1 -Acceptance of Relief Request (RR-4-20), Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML19214A2732019-08-0202 August 2019 NRR E-mail Capture - Virgil C. Summer, Unit 1 - Acceptance of License Amendment Request to Change Company Name ML19211D5102019-07-30030 July 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 (Supplement to PRA RAI 03) ML19179A1262019-06-27027 June 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request ML19140A2692019-05-17017 May 2019 Acceptance of Alternative Request (RR-4-23)to Utilize Code Case N-513-4 ML19105B1652019-04-15015 April 2019 NRR E-mail Capture - VC Summer SPRA Review - Clarification Questions on Credit for the Abeyance RCP Seals ML19102A0702019-04-11011 April 2019 NRR E-mail Capture - V.C. Summer, Unit 1: Relief Request (RR-4-22) Verbal Authorization Script ML19095A6532019-04-0404 April 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information NFPA-805 Program Revisions LAR ML19072A1442019-03-13013 March 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions ML19095A6582019-03-0404 March 2019 NRR E-mail Capture - VC Summer SPRA Review - Clarification Questions on Peer Review Findings and Plant Modifications ML19095A6672019-01-30030 January 2019 NRR E-mail Capture - VC Summer SPRA Clarification Questions on Circuit Analysis and Relay Replacement ML19031B4332019-01-29029 January 2019 Email Regarding VC Summer Units 2 & 3 Letter from Santee Cooper on Termination of COL ML19009A1052019-01-0909 January 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-10-02395, TS 3.8.2, D.C. Sources - Operating ML19009A5362019-01-0909 January 2019 NRR E-mail Capture - VC Summer Clarification Question on Fussell-Vesely Values 2024-01-25
[Table view] |
Text
From: Karen Cotton To: internet: WILLYSILVERA@aol.com Date: 10/10/02 3:00PM
Subject:
NRC - Response to your concern
Dear Mr. Silvera,
Your e-mail dated September 2, 2002, was forwarded to the U.S. Nuclear Regulatory Commission (NRC) for action. The NRC is responsible for regulating and overseeing commercial nuclear power plant operation and other uses of nuclear material.
We are sorry for the loss that your family has experienced over the years. We are not aware of any scientific studies to demonstrate an increased risk of cancer due to living near the vicinity of a commercial nuclear power plant.
In your e-mail you requested information about 1) the environmental changes caused by the operation of Virgil C. Summer Nuclear Station (VCSNS) and 2) (any) accident reports associated with an experimental reactor from the 1950s.
Commercial nuclear power plants licensed by the NRC are required to comply with statutes and regulations concerning radiological and non-radiological releases to the environment.
Operations controlling non-radiological releases from VCSNS are conducted in compliance with statutes and regulations designed to control and minimize adverse impacts to the environment.
The NRC and many other State and Federal agencies require through their regulations that South Carolina Electric & Gas Company operate VCSNS in a manner that protects human health and the environment. For example, the NRC requires VCSNS to maintain compliance with its Clean Water Act 316(b) determination. The 316(b) determination is a document used to verify that the cooling water intake structure at the plant is operated in a manner such that adverse impacts to shellfish, fish, fish eggs, and larvae are minimized. Additionally, the State of South Carolina is responsible for protecting the environment around the plant through its National Pollution Discharge Elimination System (NPDES) permit process. The NPDES permit sets standards on chemical and thermal discharges from the plant. VCSNS is also required to comply with the Endangered Species Act that is administered by the South Carolina Department of Natural Resources and the U.S. Fish and Wildlife Service. Since nuclear power plants do not produce appreciable gaseous effluents, the impact on air quality is minimal. Together, these regulations provide a measure of assurance that operations at VCSNS are conducted in a manner that protects the environment.
With respect to radiological releases, operators are required to monitor and sample the environment around the plant for any potential release of radionuclides and ensure that the allowable dose limits are not exceeded [Title 10, Code of Federal Regulations, Part 10, § 20.1301]. The NRC regulations also require the operators to report the quantity of each of the principles radionuclides released to unrestricted areas in liquid or gaseous effluents during the past six months of operations [Title 10, Code of Federal Regulations, Part 10, § 70.59]. This information for VCSNS is publicly available. Documents may be examined, and/or copied for a
fee, at the NRCs Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records are accessible electronically from the Agencywide Documents Access and Management System (ADAMS)
Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to pdr@nrc.gov.
We regret that we cannot respond to your questions regarding any accident reports at an experimental power plant from the 1950s. We suggest that you contact the Office of Public Affairs at the U.S. Department of Energy at www.energy.gov.
From the desk of . . . .
Karen Cotton Nuclear Regulatory Commission Project Manager Virgil C. Summer Nuclear Power Station 301-415-1438 krc@nrc.gov