October 2, 2002 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

Dear Mr. Skolds:

In response to your facility management letter dated August 23, 2002, and as augmented by discussions with Paul Hippely, Initial Licensee Group Lead of your staff on September 26, 2002, we have tentatively scheduled an initial licensing examination for your operator license applicants at the Braidwood Station during the weeks of July 5 and July 12, 2004. Validation of the examination will occur at the station during the week of June 14, 2004. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date.

As stated in your letter and agreed upon in a telephone conversation on September 26, 2002, your staff will develop the examination. To support the examination administration date, we have tentatively scheduled the date of May 17, 2004, to begin our review of your submitted examination.

Your letter dated July 18, 2002, indicated you are training approximately 12 candidates for the examination. Please inform us if the number of candidates declines below 10 as this will impact the examination schedule. Please also inform us at your earliest opportunity if you discover you are unable to support the examination on the scheduled dates.

Once your staff has determined a schedule for examination development, please have them contact the Chief Examiner to arrange for a suitable examination outline submittal date for NRC review. The intent is for the examination outline to be submitted early in the examination development process. This is to preclude the need to make significant changes to developed examination material as a result of the NRC review of the outline.

Dell R. McNeil has been tentatively assigned as the Chief Examiner and can be reached at 630-829-9737.

A supplementary letter will be sent to the training department approximately 120 days prior to the examination outlining examination security expectations, listing the materials required by the NRC to conduct the examination, reconfirming the examination dates, and reconfirming the number of candidates you have in the training program. If you have any questions concerning this information, please contact Hironori Peterson of my staff at 630-829-9707.

J. Skolds In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

David L. Pelton, Acting Branch Chief Operations Branch Division of Reactor Safety Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77 cc:

Site Vice President - Braidwood Braidwood Station Plant Manager Regulatory Assurance Manager - Braidwood Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission D. J. Myers, Training Department R. G. Coon, Department of Training for the Midwest ROG DOCUMENT NAME: G:\\DRS\\BRA09__02DRSHP.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS RIII:DRS NAME HPeterson:aa DPelton DATE 09/30/02 10/02/02 OFFICIAL RECORD COPY

J. Skolds ADAMS Distribution AJM DCT DFT MLC RidsNrrDipmIipb GEG HBC SPR DRPIII DRSIII PLB1 JRK M. A. Bies, DRS

J. Skolds In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

David L. Pelton, Acting Branch Chief Operations Branch Division of Reactor Safety Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77 cc:

Site Vice President - Braidwood Braidwood Station Plant Manager Regulatory Assurance Manager - Braidwood Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission D. J. Myers, Training Department R. G. Coon, Department of Training for the Midwest ROG