Text

November 27, 2002 Mr. Harold W. Keiser Chief Nuclear Officer & President PSEG Nuclear LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, EVALUATION OF RELIEF REQUEST SC-RR-E01 AND SC-RR-L01 (TAC NOS.

MB6096, MB6097, MB6101 AND MB6102)

Dear Mr. Keiser:

By letter dated July 8, 2002, PSEG Nuclear, LLC submitted twelve requests for relief from Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code under the provisions of 10 CFR 50.55a(a)(3)(i). Among the requested reliefs were SC-RR-E01, a request to invoke the 1998 Edition including 1998 Addenda of IWE for class MC components, and SC-RR-L01, a request to invoke the 1998 Edition including 1998 Addenda of IWL for class CC components.

On September 26, 2002, the Nuclear Regulatory Commission (NRC) issued in the Federal Register (67 FR 60520) a final rule to amend its regulations in 10 CFR 50.55a. In part, the final rule incorporates by reference the 1998 Edition including the 1998 Addenda to Section XI, Subsections IWE and IWL. The rule is effective on October 28, 2002. Pursuant to 10 CFR 50.55a(g)(4)(iv), the use of the 1998 Edition including the 1998 Addenda of Subsections IWE and IWL are approved subject to the limitations and modifications listed in paragraph (b) of 10 CFR 50.55a. In a telephone call on or about October 4, 2002, Mr. Howard Berrick of your staff informed us that as a result of this rule change you will not be needing the relief requested in either SC-RR-E01 or SC-RR-L01. The NRC staff, therefore, will not evaluate these relief requests. This completes the NRC staffs efforts on TAC Nos. MB6096, MB6097, MB6101, and MB6102.

Sincerely,

/RA/

James W. Andersen, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 cc: See next page

November 27, 2002 Mr. Harold W. Keiser Chief Nuclear Officer & President PSEG Nuclear LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, EVALUATION OF RELIEF REQUEST SC-RR-E01 AND SC-RR-L01 (TAC NOS.

MB6096, MB6097, MB6101 AND MB6102)

Dear Mr. Keiser:

By letter dated July 8, 2002, PSEG Nuclear, LLC submitted twelve requests for relief from Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code under the provisions of 10 CFR 50.55a(a)(3)(i). Among the requested reliefs were SC-RR-E01, a request to invoke the 1998 Edition including 1998 Addenda of IWE for class MC components, and SC-RR-L01, a request to invoke the 1998 Edition including 1998 Addenda of IWL for class CC components.

On September 26, 2002, the Nuclear Regulatory Commission (NRC) issued in the Federal Register (67 FR 60520) a final rule to amend its regulations in 10 CFR 50.55a. In part, the final rule incorporates by reference the 1998 Edition including the 1998 Addenda to Section XI, Subsections IWE and IWL. The rule is effective on October 28, 2002. Pursuant to 10 CFR 50.55a(g)(4)(iv), the use of the 1998 Edition including the 1998 Addenda of Subsections IWE and IWL are approved subject to the limitations and modifications listed in paragraph (b) of 10 CFR 50.55a. In a telephone call on or about October 4, 2002, Mr. Howard Berrick of your staff informed us that as a result of this rule change you will not be needing the relief requested in either SC-RR-E01 or SC-RR-L01. The NRC staff, therefore, will not evaluate these relief requests. This completes the NRC staffs efforts on TAC Nos. MB6096, MB6097, MB6101, and MB6102.

Sincerely,

/RA/

James W. Andersen, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 cc: See next page DISTRIBUTION:

PUBLIC RGN1 JPulsipher PDI-2 R/F OGC TCheng RFretz GHill (2) Rfretz SLittle WBeckner JAndersen ACRS SRichards MSnodderly ADAMS Accession Number: ML022810540 OFFICE PDI-2/PM PDI-2/LA OGC PDI-2/SC EMEB/SC NAME RFretz SLittle RHoefling JAndersen DTerao DATE 11/08/02 11/8/02 11/26/02 11/26/02 11/12/02 OFFICIAL RECORD COPY

PSEG Nuclear LLC Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:

Mr. David F. Garchow Lower Alloways Creek Township Vice President - Operations c/o Mary O. Henderson, Clerk PSEG Nuclear - X04 Municipal Building, P.O. Box 157 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Mr. John T. Carlin Radiation Protection Programs Vice President - Nuclear Reliability and NJ Department of Environmental Technical Support Protection and Energy PSEG Nuclear - N10 CN 415 P.O. Box 236 Trenton, NJ 08625-0415 Hancocks Bridge, NJ 08038 Richard Hartung Mr. Gabor Salamon Electric Service Evaluation Manager - Nuclear Safety and Licensing Board of Regulatory Commissioners PSEG Nuclear - N21 2 Gateway Center, Tenth Floor P.O. Box 236 Newark, NJ 07102 Hancocks Bridge, NJ 08038 Regional Administrator, Region I Jeffrie J. Keenan, Esquire U.S. Nuclear Regulatory Commission PSEG Nuclear - N21 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Ms. R. A. Kankus Salem Nuclear Generating Station Joint Owner Affairs U.S. Nuclear Regulatory Commission PECO Energy Company Drawer 0509 Nuclear Group Headquarters KSA1-E Hancocks Bridge, NJ 08038 200 Exelon Way Kennett Square, PA 19348