November 27, 2002 Mr. Harold W. Keiser Chief Nuclear Officer & President PSEG Nuclear LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, EVALUATION OF RELIEF REQUEST SC-RR-E01 AND SC-RR-L01 (TAC NOS.
MB6096, MB6097, MB6101 AND MB6102)
Dear Mr. Keiser:
By letter dated July 8, 2002, PSEG Nuclear, LLC submitted twelve requests for relief from Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code under the provisions of 10 CFR 50.55a(a)(3)(i). Among the requested reliefs were SC-RR-E01, a request to invoke the 1998 Edition including 1998 Addenda of IWE for class MC components, and SC-RR-L01, a request to invoke the 1998 Edition including 1998 Addenda of IWL for class CC components.
On September 26, 2002, the Nuclear Regulatory Commission (NRC) issued in the Federal Register (67 FR 60520) a final rule to amend its regulations in 10 CFR 50.55a. In part, the final rule incorporates by reference the 1998 Edition including the 1998 Addenda to Section XI, Subsections IWE and IWL. The rule is effective on October 28, 2002. Pursuant to 10 CFR 50.55a(g)(4)(iv), the use of the 1998 Edition including the 1998 Addenda of Subsections IWE and IWL are approved subject to the limitations and modifications listed in paragraph (b) of 10 CFR 50.55a. In a telephone call on or about October 4, 2002, Mr. Howard Berrick of your staff informed us that as a result of this rule change you will not be needing the relief requested in either SC-RR-E01 or SC-RR-L01. The NRC staff, therefore, will not evaluate these relief requests. This completes the NRC staffs efforts on TAC Nos. MB6096, MB6097, MB6101, and MB6102.
Sincerely,
/RA/
James W. Andersen, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 cc: See next page
November 27, 2002 Mr. Harold W. Keiser Chief Nuclear Officer & President PSEG Nuclear LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, EVALUATION OF RELIEF REQUEST SC-RR-E01 AND SC-RR-L01 (TAC NOS.
MB6096, MB6097, MB6101 AND MB6102)
Dear Mr. Keiser:
By letter dated July 8, 2002, PSEG Nuclear, LLC submitted twelve requests for relief from Section XI of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code under the provisions of 10 CFR 50.55a(a)(3)(i). Among the requested reliefs were SC-RR-E01, a request to invoke the 1998 Edition including 1998 Addenda of IWE for class MC components, and SC-RR-L01, a request to invoke the 1998 Edition including 1998 Addenda of IWL for class CC components.
On September 26, 2002, the Nuclear Regulatory Commission (NRC) issued in the Federal Register (67 FR 60520) a final rule to amend its regulations in 10 CFR 50.55a. In part, the final rule incorporates by reference the 1998 Edition including the 1998 Addenda to Section XI, Subsections IWE and IWL. The rule is effective on October 28, 2002. Pursuant to 10 CFR 50.55a(g)(4)(iv), the use of the 1998 Edition including the 1998 Addenda of Subsections IWE and IWL are approved subject to the limitations and modifications listed in paragraph (b) of 10 CFR 50.55a. In a telephone call on or about October 4, 2002, Mr. Howard Berrick of your staff informed us that as a result of this rule change you will not be needing the relief requested in either SC-RR-E01 or SC-RR-L01. The NRC staff, therefore, will not evaluate these relief requests. This completes the NRC staffs efforts on TAC Nos. MB6096, MB6097, MB6101, and MB6102.
Sincerely,
/RA/
James W. Andersen, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 cc: See next page DISTRIBUTION:
PUBLIC RGN1 JPulsipher PDI-2 R/F OGC TCheng RFretz GHill (2)
Rfretz SLittle WBeckner JAndersen ACRS SRichards MSnodderly ADAMS Accession Number: ML022810540 OFFICE PDI-2/PM PDI-2/LA OGC PDI-2/SC EMEB/SC NAME RFretz SLittle RHoefling JAndersen DTerao DATE 11/08/02 11/8/02 11/26/02 11/26/02 11/12/02 OFFICIAL RECORD COPY
PSEG Nuclear LLC Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Mr. David F. Garchow Vice President - Operations PSEG Nuclear - X04 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. John T. Carlin Vice President - Nuclear Reliability and Technical Support PSEG Nuclear - N10 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Gabor Salamon Manager - Nuclear Safety and Licensing PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Ms. R. A. Kankus Joint Owner Affairs PECO Energy Company Nuclear Group Headquarters KSA1-E 200 Exelon Way Kennett Square, PA 19348 Lower Alloways Creek Township c/o Mary O. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy CN 415 Trenton, NJ 08625-0415 Richard Hartung Electric Service Evaluation Board of Regulatory Commissioners 2 Gateway Center, Tenth Floor Newark, NJ 07102 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector Salem Nuclear Generating Station U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, NJ 08038