ML022670082

From kanterella
Jump to navigation Jump to search
Response to NRC Bulletin 2002-02, Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs
ML022670082
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 09/11/2002
From: Fader G
Wolf Creek
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BL-02-002, ET 02-0037
Download: ML022670082 (13)


Text

WkLF-CREEK

'NUCLEAR OPERATING CORPORATION Gary B. Fader Vice President Technical Services

-SEP

. EP-11 2002 ET 02-0037 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

Subject:

-Docket No. 50-482: Response to NRC Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs" Gentlemen:

Attachment I contains WCNOC's response to NRC Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs" dated August 9, 2002. NRC Bulletin 2002-02 Required Response item (1) in conjunction with Requested information items (1)A and (1)B require, within-30 days, a summary of the supplemental inspections to be implemented or a justification for continued reliance on visual examinations as the primary method to detect degradation. Requested Information item (2) requires, within 30 days after plant restart following the next-inspection of the-RPV head and/or RPV head penetration nozzles to identify the presence of any degradation, the licensee to provide the inspection scope, results, corrective actions taken and the root cause determinations for any degradation found.

In accordance with a conversation with Mr. Jack Donohew, NRC Project Manager for Wolf Creek, a response date on or before September 12, 2002, is acceptable.

Wolf Creek Nuclear Operating Corporation (WCNOC) agrees that issues discussed in the subject bulletin deserve and are-receiving appropriate attention at-Wolf Creek Generating Station. In April 2002, WCNOC completed a bare metal visual inspection of our reactor vessel head -with no leakage or degradation identified.

This inspection meets the near term recommendations of both the Nuclear Regulatory Commission's (NRC) and Electric Power Research Institute (EPRI) Material Reliability Program's (MRP) inspection plans. WCNOC will continue to follow industry inspection results and support efforts to develop improved inspection and leak detection technologies.

Attachment I lists WCNOC's commitments contained in this correspondence.

RO Box 411 Burlington, KS 66839 /Phone (620) 364-8831 An Equal Opportunity Employer M/F/HICNET

ET 02-0037 Page 2 of 2 If you should have any questions regarding this submittal,- please,contact -me at 4034, or Mr. Tony Harris, Manager Regulatory Affairs at (620) 364-4038.-

7-Very-truly yours, Gary.B. Fader-GBF/rlr Attachments: -

I Response to NRC Bulletin -2002-02:

S--_

II-List of Commitments cc:-

J. N. Donohew (NRC), wla

-D. N. Graves (NRC),w/a E. W. Merschoff (NRC), wla Senior Resident Inspector (NRC), wla -

(620) 364-

ET 02-0037 STATE OF KANSAS COUNTY OF COFFEY

) ) ss

)

Gary B. Fader, of lawful age, being first duly sworn upon oath says that he is Vice President Technical Services of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.

SUBSCRIBED and sworn to before me this 10 day of Sc.-It.

,2002.

CINDY NOVINGER Nota bi STU~MyA MAPPtEXP.AW//O.

0 Expiration Date "I-.

  • J &OO (,&

=

l Ný

Attachment I to. ET 02-0037 Page 1 6f 9 Response to NRC Bulletin 2002-02 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs Below is the Wolf Creek Nuclear Operating Corporation (WCNOC) response to Nuclear Regulatory Commission (NRC)Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs," dated August 9, 2002.

Portions of this response are based on information developed by Electric Power Research Institute (EPRI)

Material Reliability Program (MRP) for the industry (Ref. 1).

The bulletin's "Required Information" and "Requested Information" is shown in bold.

Requested Information (1)

Within 30 days of the date of this bulletin:

A.

PWR addressees who plan to supplement their inspection programs with non-visual NDE methods are requested to provide a summary discussion of the supplemental inspections to be implemented. The summary discussion should include EDY, methods, scope, coverage, frequencies, qualification requirements, and acceptance criteria.

-B.

PWR addressees who do not plan to supplement their inspection programs with non-visual NDE methods are requested to provide a justification for continued reliance on visual examinations as the primary method to detect degradation (i.e., cracking, leakage, or wastage). In your justification, include a discussion that addresses the reliability and effectiveness of the inspections to ensure that all regulatory and technical specification requirements are met during the operating cycle, and that addresses the six concerns identified in the Discussion Section of this bulletin. Also, include in your justification a discussion of your basis for concluding that unacceptable vessel head wastage will not occur between inspection cycles that rely on qualified visual inspections. You should provide all applicable data to support your understanding of the wastage phenomenon and wastage rates.

Required Information In accordance with 10 CFR 50.54(f), PWR addressees are required to submit written responses to this bulletin. There are two options available to the addressees:

(1)

Addressees may choose to submit written responses providing the information requested above within the requested time periods.

Response

Wolf Creek Generating Station (WCGS) is categorized as having low susceptibility to primary water stress corrosion cracking (PWSCC) using the industry model developed by EPRI MRP.

WCNOC has determined the accrued Effective Degradation Years (EDY) for WCGS in accordance with EPRI MRP report MRP-48 (Equation 2.2) (Ref. 15). As of September 9, 2002, WCGS's accrued EDY is 2.4. The accrual rate is 0.17 EDY per effective full power year.

Attachment I to, ET 02-0037 Page 2 6f 9 WCNOC completed a bare metal visual inspection of the reactor pressure vessel (RPV) head in April 2002, during Refueling Outage #12.

One hundred percent of the carbon steel surface area of the RPV head was visually examined.

Additionally, 100% of the interface areas between the RPV head penetrations and the carbon steel on top of the head were visually examined.

No indications of primary coolant leakage through the penetrations, and no indications of head degradation were identified (Ref. 13).

An industry inspection plan has been developed for PWR power plants by EPRI MRP (Ref. 2).

WCNOC will begin implementing the MRP inspection plan recommendations for low susceptibility plants by conducting a MRP inspection plan "supplemental visual examination" in Refueling Outage #14, currently scheduled for Spring 2005. The completed bare metal visual inspection and the MRP "supplemental visual examination" meet the basic requirements of both the MRP inspection plan and the NRC's "Example Supplemental Inspection" plan for two operating cycles following the current operating cycle. Implementation of the MRP inspection plan is also consistent with the inspection commitments made in WCNOC's response to Bulletin 2002-01 (Ref. 14).

Even though there is currently good agreement between industry experience and the MRP model, WCNOC recognizes that industry inspections, tests and analyses are ongoing that continue to validate the MRP model.

In addition to inspections during refueling outages, WCNOC's administrative controls implementing boric acid corrosion programs usemonitoring, evaluation, and prediction techniques to detect plant conditions that may indicate potential reactor coolant system (RCS) leaks, including leaks from the RPV head penetration nozzles.

Based on good agreement between industry experience and the MRP model to date, WCNOC believes that following the MRP recommended inspection plan provides adequate assurance that the structural integrity of the control rod drive mechanism (CRDM) penetration nozzles and the RPV head will be maintained. WCNOC continues to monitor industry events relative to these issues. If future events, analyses, tests or inspections, either at WCGS or elsewhere in the industry, affect our confidence in the adequacy of the MRP model, WCNOC will take the actions necessary to re-establish adequate assurance of RPV head and penetration nozzle structural integrity. Actions could include additional inspections as well as additional or modified examination techniques.

WCNOC has reviewed its response to NRC Bulletin 2002-01 relative to the applicable regulatory requirements discussed in Bulletin 2002-02. WCNOC's response to Bulletin 2002-01 remains valid relative to continued conformance to applicable regulatory requirements.

Implementation of the MRP inspection plan, as well as continued implementation of administrative controls associated with inspection activities and correction of identified issues, assures continued compliance with the regulatory requirements described in NRC Bulletin 2002-02.

WCNOC provides the following additional information as justification for continued reliance on visual examinations as the primary method to detect degradation in the RPV head. Included are discussions on the reliability and effectiveness of visual examinations as they relate to the six concerns cited in Bulletin 2002-02 and the basis for concluding that unacceptable wastage will not occur between examination cycles.

Attachment I to. ET 02-0037 Page 3 bf 9 Concern 1:

Circumferential cracking of CRDM nozzles was identified by the presence of relatively small amounts of boric acid deposits.

This finding increases the need for more effective visual and non-visual NDE inspection methods to detect the presence of degradation in CRDM nozzles before nozzle integrity is compromised.

Response

Since the initial discovery of circumferential cracks above the J-groove weld in 2001, visual inspection techniques and approaches employed have dramatically improved.

Non-visual examination techniques continue to evolve to more effectively examine the penetration tube and associated welds for evidence of cracks. Nothing in the recent events at Davis-Besse has altered the fundamental inspection capability requirements previously established as necessary to identify the presence of PWSCC and potential associated wastage.

The effectiveness of inspection techniques continues to be evaluated and improved.

EPRI MRP has published detailed guidance for performing visual examinations of RPV heads (Ref. 3). A utility workshop was also conducted to discuss this guidance and lessons learned from recent field experience (including Davis-Besse).

The RPV head bare metal visual inspection completed at Wolf Creek Generating Station (WCGS) in April 2002 (Ref. 13) was performed and documented in accordance with written procedures and included acceptance criteria consistent with the guidance of the MRP inspection plan.

No RPV head nozzle degradation (leakage) or RPV head degradation (wastage) was identified.

In order for outside diameter (OD) circumferential cracks above the J-groove weld to initiate and grow, a leak path must first be established to the CRDM annulus region from the inner wetted.surface of the RPV head.

If primary water does not leak to the annulus region, the environment does not exist to cause circumferential OD cracking. Axial cracks in the CRDM, nozzles or cracks in J-groove welds must first initiate and grow through wall. Experience has shown that through-wall axial cracks will result in observable leakage at the base of the penetration on the topside surface of the RPV head, even with penetration nozzle interference fits. Alloy 600 steam generator drain pipes at Shearon Harris (1988) and pressurizer instrument nozzles at Nogent 1 and Cattenom 2 (1989) were all roll expanded but still developed leaks during operation (Ref. 4). Plant specific top head gap analyses have been performed for a large number of plants, with nozzle initial interference fits ranging from 0 to 0.0034 inches.

These analyses have confirmed the presence of a physical leak path in essentially all nozzles under normal operating pressure and temperature conditions (Ref. 4).

Visual inspections of the reactor coolant system pressure boundary have been proven to be an effective method for identifying leakage from PWSCC cracks in Alloy 600 base metal and Alloy 82/182 weld metal. Specifically, visual inspections have detected leaks in RPV head CRDM nozzles, RPV head thermocouple nozzles, pressurizer heater sleeves, pressurizer instrument nozzles, hot leg instrument nozzles, steam generator drain lines, a RPV hot leg nozzle weld, a power operated relief valve safe end and a pressurizer manway diaphragm plate (Ref. 5). To date, with the exception of the three nozzles at Davis Besse, all leaking RPV penetration nozzles have been detected by visual examinations, and none have been detected by non visual NDE examinations alone. Based on current industry experience, nozzle leakage at Davis Besse would have been detected visually had there been good access for visual examinations and the head cleaned of pre-existing boric acid deposits from other sources (Ref. 4).

Finally, as described under Concern 3 below, detailed probabilistic fracture mechanics (PFM) analyses have been performed to demonstrate the effectiveness of visual inspections above the RPV head in protecting the CRDM nozzles against failure due to circumferential cracking (Ref. 6).

Even though the above discussion illustrates that visual inspections performed in accordance with MRP recommendations have a high probability of detecting through-wall

Attachment I tQ ET 02-0037 Page 4 of 9 leakage, a very low probability of detection was assumed in the PFM analyses. The PFM analyses assume only a 60% probability that leakage will be detected if a CRDM nozzle is leaking at the time a visual inspection is performed.

Furthermore, if a nozzle has been inspected previously, and leakage was missed, subsequent visual inspections are assumed to have only a 12% probability of detecting the leak. Even with these conservative assumptions relative to probability of detection, the PFM analyses show that visual inspection above the RPV head every outage reduces the probability of a nozzle failure to an acceptable level for plants with 18 or more EDY. Visual inspections of plants with fewer than 18 EDY in accordance with the MRP Inspection Plan will significantly reduce the probability of nozzle failure.

In summary, small amounts of leakage from RPV nozzle penetrations can be detected by visual examination from above the RPV head and it has been shown that timely detection and repair of leakage will ensure the structural integrity of the RPV head penetrations with respect to circumferential cracking.

Concern 2: Cracking of 82/182 weld metal has been identified in CRDM nozzle J-groove welds for the first time and can precede cracking of the base metal. This finding raises concerns because examination of weld metal material is more difficult than base metal.

Response: Cracks in the J-groove weld do not pose an increased risk regarding nozzle failure as compared to penetration base metal cracks. J-groove weld cracks that initiate and grow through-wall will leak the same as cracks in the penetration base metal. Therefore, weld cracks pose a similar risk as cracks in the base material and subsequent leakage is equally detectable by visual examination. Although higher crack growth rates have been observed in laboratory testing of weld metal, the industry model of time-to-leakage includes plants that have had weld metal cracking as well as base metal cracking. The visual examination frequencies from the MRP Inspection Plan (Ref. 2) have been conservatively established based on the risk informed analyses considering leakage due to both weld metal and base metal cracking.

Concern 3:

Through-wall circumferential cracking from the outside diameter of the CRDM nozzle has been identified for the first time. This raises concerns about the potential for failure of CRDM nozzles and control rod ejection, causing a LOCA.

Response

Probabilistic fracture mechanics analyses, using a Monte-Carlo simulation algorithm, were performed to estimate the probability of nozzle failure and nozzle ejection due to through wall circumferential cracking (Ref. 6). The PFM analyses conservatively assume that, once a leak path has extended to the annulus region, an OD circumferential crack develops instantaneously, with a length encompassing 30° of the nozzle circumference.

Fracture mechanics crack growth calculations are then performed for this initially assumed crack, using material crack growth rate data from EPRI Report MRP-55 (Ref. 7).

The parameters used in the PFM model were benchmarked against the most severe cracking found to date in the industry (B&W Plants) and produced results that are in agreement with experience to date. The analyses were used to determine probability of nozzle failure versus effective full power years (EFPY) for various head operating temperatures. Analyses were then performed to estimate the effect of visual and non-visual (NDE) inspections of the plants in the highest susceptibility category, using the conservative assumption discussed above (see Concern #1 response) for probability of leakage detection by visual inspection. These analyses demonstrate that performing visual inspections significantly reduces the probability of nozzle failure, and that performing such examinations on a regular basis (in accordance with the inspection schedule prescribed in the MRP inspection plan) effectively maintains the probability of nozzle failure at an acceptably low level indefinitely.

Attachment I tq ET 02-0037 Page 5 bf 9 In the extremely unlikely event that nozzle failure/ejection were to occur due to an undetected circumferential crack, an acceptable margin of safety to the public would still be maintained (Ref. 8). The consequences of such an event are similar to that of a small-break LOCA, which is a design-basis event. The probability of core damage given a nozzle failure (assuming that failure leads to ejection of the nozzle from the head) is approximately 4 x 103 for WCGS. The PFM analyses demonstrate that periodic visual inspections are capable of maintaining the probability of nozzle failure due to circumferential cracking less than I x 10"4. Therefore, the PFM analyses demonstrate that the resulting incremental change in core damage frequency due to RPV head penetration nozzle cracking can be maintained at less than 1 x 106 (i.e.,

4 x 103 times 1 x 10"4 is less than 1 x 106) per plant year, through a program of periodic visual examinations performed in accordance with the MRP inspection plan. This result is consistent with NRC Regulatory Guide 1.174 that defines an acceptable change in core damage frequency (1 x 106 per plant year) for changes such as plant design parameters and technical specifications.

Concern 4: The environment in the CRDM housing/RPV head annulus will likely be more aggressive after any through-wall leakage because potentially highly concentrated borated primary water may become oxygenated. This raises concerns about the technical basis for current crack growth rate models.

Response

The MRP panel of international experts on stress corrosion cracking (SSC)

(including representatives from ANL/NRC Research), prior to the Davis-Besse incident, gave extensive consideration to the likely environment in the annulus between a leaking CRDM nozzle and the RPV head and revisited this issue subsequent to the Davis-Besse incident (Ref. 7). When revisited, the relevant arguments remain valid for leak rates that are less than 1 liter/hour or 0.004 gallons/minute (gpm), which plant experience has shown to be the usual case. The conclusions were:

1. An oxygenated crevice environment is highly unlikely because:

"* Back diffusion of oxygen is too low compared to counterflow of escaping steam (two independent assessments based on molecular diffusion models were examined).

"* Oxygen consumption by the metal walls would further reduce its concentration.

"* Presence of hydrogen from leaking water and diffusion through the upper head results in a reducing environment.

"* Even if the concentration of hydrogen was depleted by local boiling, coupling between low alloy steel and Alloy 600 would keep the electrochemical potential low.

"* Corrosion potential will be close to the Ni/NiO equilibrium, resulting in PWSCC susceptibility similar to normal primary water.

2. The most likely crevice environments are either hydrogenated steam or PWR primary water within normal chemistry specifications and both would result in similar (i.e. non-accelerated) susceptibility of the Alloy 600 penetration material to PWSCC.
3.

If the boiling interface happens to be close to the topside of the J-weld, itself a low probability occurrence, concentration of PWR primary water solutes, lithium hydroxide and boric acid, can in principle occur. Of most concern here would be the accelerating effect of elevated pH on SCC, but calculations and experiments show that any changes are expected to be small, in part because of the buffering effects of precipitates. A factor of 2x on the crack growth rate (CGR) conservatively covers possible acceleration of PWSCC, even up to

Attachment I to ET 02-0037 Page 6of 9 a high-temperature pH of around 9.

For larger leakage rates, which could lead to local cooling of the head, concentration of boric acid, and development of a sizeable wastage cavity adjacent to the penetration, the above arguments no longer directly apply. However, limited data (Berge et al., 1997) on SCC in concentrated boric acid solutions indicate that:

"* Alloy 600 is very resistant to transgranular SCC (material design basis).

"* High levels of oxygen and chloride are necessary for intergranular cracking to occur at all.

"* The effects are worse at intermediate temperatures, suggesting that the mechanism is different from PWSCC.

The above considerations show that there is no basis for assuming that any post-leakage, crevice environment in the CRDM housing/RPV head annulus would be significantly more aggressive with regard to SCC of the Alloy 600 penetration material than normal PWR primary water, irrespective of the assumed leakage rate and/or annulus geometry. The current industry model (Ref. 7), which includes a factor of 2x on CGR to cover residual uncertainty in the composition of the annulus environment, remains valid.

Concern 5: The presence of boron deposits or residue on the RPV head, due to leakage from mechanical joints, could mask pressure boundary leakage.

This raises concerns that a through-wall crack may go undetected for years.

Response: The experience at Davis-Besse has clearly demonstrated that effective visual inspection for leakage from CRDM nozzle and weld PWSCC requires unobstructed inspection access and that the RPV head surface must be free of pre-existing boric acid deposits.

Accumulations of debris and boric acid deposits from other sources can interfere with a determination of the presence or absence of boric acid deposits originating from the tube-to head annulus. Therefore, to effectively perform a visual examination of the RPV head outer surface for penetration leakage, such deposits and debris accumulations must be carefully inspected, removed, and the area re-inspected for corrosion.

Each inspection at WCGS is conducted in accordance with administrative controls that include removal of any boric acid that would interfere with determining the source or the potential effects of the boric acid. These administrative controls are consistent with the bare metal visual inspection guidance contained in the MRP inspection plan and will preclude the condition of a through-wall crack remaining undetected for years.

Concern 6: The causative conditions surrounding the degradation of the RPV head at Davis Besse have not been definitively determined. The staff is unaware of any data applicable to the geometries of interest that support accurate predictions of corrosion mechanisms and rates.

Response: The causes of the Davis-Besse degradation are sufficiently well known to avoid significant wastage. The root cause evaluation performed by the utility (Ref. 9) clearly identifies the root cause as PWSCC of CRDM nozzles followed by boric acid corrosion. The large extent of degradation has been attributed to failure of the utility to address evidence that had been accumulating over a five-year period of time (Figure 26 of Ref. 9).

Attachment I to ET 02-0037 Page 7fof 9 Visual inspection guidelines have been provided (Ref. 3) to ensure that conditions approaching that which existed at Davis-Besse will not occur. A workshop was conducted to thoroughly review industry experience, 'r6egulatory requirements, leakage detection, and analytical work performed to understand the causes of high wastage rates (Ref. 10).

Subsequent to significant wastage being discovered on the Davis-Besse RPV head, the industry has performed analytical work to determine how a small leak such as seen at several plants can progress to the significant amounts of wastage discovered at Davis-Besse. This work is referenced within the basis for the MRP Inspection Plan (Ref. 11) and was previously presented to the NRC (Ref. 12).

The analytical work shows that the corrosion rate is a strong function of the leakage rate. Finite element thermal analyses show that leak rates must reach approximately 0.1 gpm for there to be sufficient cooling of the RPV top head surface to support concentrated liquid boric acid that will produce high corrosion rates. The leak rate is in turn a strong function of the crack length.

The effect of crack length above the J-groove weld on crack opening displacement and area has been confirmed by finite element modeling of nozzles including the effects of welding residual stresses and axial cracks.

Leak rates have been calculated using crack opening displacements and areas determined by the finite element analyses and leak rate models based on PWSCC cracks in steam generator tubes.

Cracks that just reach the annulus through the base metal or weld metal will result in small leaks such as those that produced small volumes of boric acid deposits on several vessel heads at locations where the CRDM nozzles Penetrate the RPV head outside surface. These leaks are typically on the order of 10-6 to 10' gpm. There is no reported industry experience where any of these leaks resulted in significant corrosion. A leak rate of 103 gpm will result in the release of about 500 in3 of boric acid deposits in an 18-month operating cycle, which will be detectable by visual inspections.

The time for a crack to grow from a length that will produce a leak rate of 103 gpm to a length that will produce a leak rate of 0.1 gpm has been estimated by deterministic analyses based on the MRP crack growth models to be 1.7 years for plants with 602°F head temperatures.

Probabilistic analyses show that there is less than a 1x10- probability that corrosion will proceed to the point that the inside surface cladding of the head would be uncovered over a significant area before the wastage would be detected by supplemental visual inspections as required under the MRP inspection plan. During the transition from leak rates of 10-3 gpm to 0.1 gpm, loss of material will be by relatively slow processes (Ref. 11).

The ability to detect leakage prior to the risk of structural failure is illustrated by Figure 26 of the Davis-Besse root cause analysis report (Ref. 9).

There was visual evidence of boric acid deposits on the vessel head for five years prior to the degradation being detected. Guidance provided in the MRP inspection plan would not permit these conditions to exist without determining the source of the leak, including nondestructive examinations if necessary.

Therefore, while the exact timing of the event progression at Davis-Besse cannot be definitively established, the probable durations can be predicted with sufficient certainty to conclude that periodic visual inspections can ensure continued structural integrity of the RCS pressure boundary.

Attachment I to ET 02-0037 Page 8*of 9 Requested Information (2)

Within 30 days after plant restart following the next inspection of the RPV head and VHP nozzles to identify the presence of any degradation, all PWR addressees are requested to provide:

A.

the inspection scope and results, including the location, size, extent, and nature of any degradation (e.g., cracking, leakage, and wastage) that was detected; details of the NDE used (i.e., method, number, type, and frequency of transducers or transducer packages, essential variables, equipment, procedure and personnel qualification requirements, including personnel passlfail criteria); and criteria used to determine whether an indication, "shadow," or "backwall anomaly" is acceptable or rejectable.

B.

the corrective actions taken and the root cause determinations for any degradation found.

Required Information In accordance with 10 CFR 50.54(f), PWR addressees are required to submit written responses to this bulletin. There are two options available to the addressees:

(1)

Addressees may choose to submit written responses providing the information requested above within the requested time periods.

Response

Within 30 days after plant restart following the next inspection of the RPV head and/or RPV head penetration nozzles to identify the presence of any degradation, WCNOC will provide the inspection scope, results, the corrective actions taken, and the root cause determinations for any degradation found.

Attachment I to ET 02-0037 i

Page 9 of 9 REFERENCES

1. EPRI Letter MRP 2002-p90, "Industry Material for Use in' Responding to NRC Bulletin 2002-02", from Leslie Hartz, Chair, MRP Senior Representatives, August 22, 2002
2. PWR Reactor Pressure Vessel (RPV) Upper Head Penetrations Inspection Plan, Revision 1, (MRP-75), EPRI, Palo Alto, CA, September 2002. 1007337
3. Visual Examination for Leakage of PWR Reactor Head Penetrations on Top of the RPV Head: Revision 1 of 1006296, Includes Fall 2001 Inspection Results, EPRI, Palo Alto, CA: 2002. 1006899
4. Probability of Detecting Leaks in RPV Top Head Nozzles, (MRP-75, Appendix B), EPRI, Palo Alto, CA, September 2002. 1007337
5. PWSCC of Alloy 600 Materials in PWR Primary System Penetrations, EPRI, Palo Alto, CA, July 1994. 103696
6. Technical Basis for CRDM Top Head Penetration Inspection Plan, (MRP-75, Appendix A), EPRI, Palo Alto, CA, September 2002. 1007337
7. Crack Growth Rates for Evaluating Primary Water Stress Corrosion Cracking (PWSCC) of Thick-Wall Alloy 600 Material, (MRP-55), EPRI, Palo Alto, CA, July 2002
8. Walton Jensen, NRC, Reactor Systems Branch, Division of Systems Safety and Analysis (DSSA), Sensitivity Study of PWR Reactor Vessel Breaks, memo to Gary Holahan, NRC, DSSA, May 10, 2002
9. Davis-Besse Nuclear Power Station Report CR2002-0891, "Root Cause Analysis Report

- Significant Degradation of the Reactor Pressure Vessel Head," April 2002

10. Proceedings of the EPRI Boric Acid Corrosion Workshop, July 25-26, 2002, (MRP-77),

EPRI, Palo Alto, CA, September 2002. 1007336

11. Supplemental Visual Inspection Intervals to Ensure RPV Closure Head Structural Integrity, (MRP-75, Appendix C), EPRI, Palo Alto, CA, September 2002. 1007337
12. Glenn White, Chuck Marks and Steve Hunt, Technical Assessment of Davis-Besse Degradation, Presentation to NRC Technical Staff, May 22, 2002
13. Letter CT 02-0029, dated May 24, 2002, from Mark S. Larson, WCNOC, to USNRC
14. Letter ET 02-0018, dated April 3, 2002, from Richard A. Muench, WCNOC, to USNRC
15. PWR Materials Reliability Program Response to NRC Bulletin 2001-01 (MRP-48), EPRI, Palo Alto, CA, 2001. 1006284

Attachrment II-to ET 02-0037 Page 1 of I LIST OF COMMITMENTS The following table identifies those actions committed to by Wolf Creek Nuclear Operating Corporation (WCNOC) in this document. Any other statements in this submittal are provided for information purposes-and are not considered to be commitments. Please direct questions regarding these commitments to Mr. Tony Harris, Manager Regulatory Affairs at Wolf Creek Generating Station, (620) 364-4038.

COMMITMENT Due Date/Event WCNOC will conduct a MRP inspection plan "supplemental visual End of Refueling examination" in Refueling Outage #14, currently scheduled for Outage 14 Spring 2005.

Within 30 days after plant restart following the next inspection of 30 days after end the RPV head and/or RPV head penetration nozzles to identify of Refueling the presence of any degradation, WCNOC will provide the Outage 14 inspection scope, results, the corrective actions taken, and the root cause determinations for any degradation found.

I r

ý

,I -