MONTHYEARML0224002952002-08-27027 August 2002 Draft Ltr from s Sands, NRR to G Campbell, Regarding Davis Besse Documentation of Conference Call of November 15, 2001 Concerning Response to Bulletin 2001-01 Project stage: Draft Other ML0224002942002-08-27027 August 2002 Letter Regarding Response to NRC Bulletin 2001-01, Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles. Project stage: Other ML0224002902002-08-27027 August 2002 Letter Regarding Request for Additional Information Concerning Response to Bulletin 2001-01 Project stage: RAI ML0224202392002-08-29029 August 2002 Draft Ltr from Samuel Collins Re Davis-Besse Nuclear Power Station, Unit 1 - Issuance of Order for Responses to Bulletin 2001-01 Project stage: Draft Approval ML0224202382002-08-29029 August 2002 Draft Ltr from Samuel Collins Re Davis-Besse Nuclear Power Station, Unit 1 - Issuance of Order for Responses to Bulletin 2001-01 Project stage: Draft Approval ML0224202352002-08-29029 August 2002 Draft Ltr from Samuel Collins Re Davis-Besse Nuclear Power Station, Unit 1 - Issuance of Order for Responses to Bulletin 2001-01 Project stage: Draft Approval ML0224202262002-08-29029 August 2002 Draft Ltr from Samuel Collins Re Davis-Besse, Unit 1, Issuance of Order Re Responses to Bulletin 2001-01 Project stage: Draft Approval ML0233005392002-12-0303 December 2002 Response to Nuclear Regulatory Commission Bulletin 2001-01, Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles Project stage: Other 2002-08-27
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) ML23178A2742023-08-0101 August 2023 Letter to the Honorable Marcy Kaptur from Chair Hanson Responds to Letter Regarding the License Transfer Application for the Davis-Besse Nuclear Power Station L-23-175, Submittal of Fifth Ten Year Inservice Testing Program2023-08-0101 August 2023 Submittal of Fifth Ten Year Inservice Testing Program IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23160A2342023-06-13013 June 2023 Confirmation of Initial License Examination L-23-034, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-13013 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 L-23-135, Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-31031 May 2023 Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information L-23-101, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 20222023-05-12012 May 2023 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 2022 L-23-131, Readiness for Resumption of NRC Supplemental Inspection2023-05-12012 May 2023 Readiness for Resumption of NRC Supplemental Inspection IR 05000346/20230102023-05-0909 May 2023 Commercial Grade Dedication Inspection Report 05000346/2023010 ML23123A1272023-05-0303 May 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Davis-Besse Nuclear Power Station IR 05000346/20230012023-05-0101 May 2023 Integrated Inspection Report 05000346/2023001 and 07200014/2022001 L-23-092, Occupational Radiation Exposure Report for Year 20222023-04-27027 April 2023 Occupational Radiation Exposure Report for Year 2022 ML23111A1972023-04-26026 April 2023 Information Meeting with Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Davis-Besse Nuclear Power Plant Station ML23114A1062023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23096A1382023-04-11011 April 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-037, and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 and Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage ML23066A2892023-03-14014 March 2023 Request for Threshold Determination Under 10 CFR 50.80 and 10 CFR 72.50 for an Amendment to the Voting Agreement ML23066A2592023-03-14014 March 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2, Davis Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 2024-02-02
[Table view] |
Text
E -* UNITED STATES 0 *NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Guy G. Campbell, Vice President - Nuclear FirstEnergy Nuclear Operating Company 5501 North State, Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - ISSUANCE OF ORDER RE: RESPONSES TO BULLETIN 2001-01, "CIRCUMFERENTIAL CRACKING OF REACTOR PRESSURE VESSEL HEAD PENETRATION NOZZLES," (TAC NO.
MB2626)
Dear Mr. Campbell:
The Nuclear Regulatory Commission (NRC) staff issued Bulletin 2001-01, Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles," on August 3, 2001, to address the generic safety implications of pressure boundary leakage recently observed at several facilities due to circumferential cracking of vessel head penetration (VHP) nozzles resulting from primary water stress corrosion cracking. In the Bulletin, the NRC staff recommended timely performance of a qualified visual examination of 100 percent of the VHP nozzles for those plants that either already have identified the existence of, or are considered to have high susceptibility to, primary water stress corrosion cracking of VHP nozzles. To assess the prevalence and severity of VHP nozzle cracking and determine plant-specific compliance with NRC regulations, the NRC staff requested that addressees submit information regarding the scope, timing, and results of completed inspections and the scope and schedule of future inspections of their VHP nozzles. The Bulletin requested that licensees not planning to perform inspections prior to December 31, 2001, provide a technical basis for their planned inspection schedules. When the Bulletin was issued, the staff considered that performance of the recommended inspections by December 31, 2001, was a timely action given the very limited knowledge, experience, and observations regarding this cracking phenomenon and the associated safety implications. December 31, 2001, was chosen based on the need to acquire additional information in a timely manner and to allow licensees time to plan and perform the recommended inspections, and to make needed repairs.
Since issuance of the Bulletin, the importance of performing the recommended inspections by this date to support continued operation has been reinforced by the identification of VHP nozzle cracking, including circumferential cracking, at several facilities. While the results of these inspections have not revealed conditions of incipient failure, the inspections have identified conditions supporting the need to perform inspections in the near term to verify the absence of conditions worse than those found to date. In light of these results, the staff believes that operation of facilities, that are considered to be highly susceptible to this cracking phenomenon or that have already experienced VHP nozzle cracking, beyond December 31, 2001, is unacceptable unless the recommended inspections to identify this potentially hazardous condition are completed and found acceptable by the NRC staff.
You provided your response to the Bulletin by letters dated September 4, October 17, October 30, and November 1, 2001. These letters documented the "high susceptibility" ranking of the Davis-Besse Nuclear Power Station, Unit No. 1. (DBNPS), and described your basis for deferral
"-Z) of performance of the VHP inspections until you shutdown for the next refueling outage on March 31, 2002.
Based on the information provided in your responses, you have not, at any time, performed a qualified visual examination of 100 percent of the VHP nozzles at DBNPS. In addition, the plant is ranked as having a high susceptibility to cracking in the VHP nozzles. Due to this high susceptibility and the extent of cracking found in other plants, it is reasonable to expect that DBNPS could have significant cracking, which would violate the reactor coolant pressure boundary and result in a loss-of-coolant accident. You have not provided an adequate basis to operate beyond December 31, 2001, without performing inspections to verify the integrity of the reactor coolant pressure boundary. Consequently, I find that a potentially hazardous condition exists and warrants the issuance of the attached Order that modifies the operating license for DBNPS, to require (1) that the facility be shut down by December 31, 2001, and proceed to the cold shutdown or lower mode, and (2) the performance of inspections to demonstrate to the NRC staff that there is reasonable assurance that the VHP nozzles are free of significant defects prior to subsequent plant operation. I further find that the assurance of public health and safety requires that this Order be effective immediately.
Sincerely, Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosures:
Order Modifying License No. NPF-3 cc w/encls: See next page
Mr. Guy G. Campbell Davis-Besse Nuclear Power Station, Unit 1 F.
FirstEnergy Nuclear Operating Company cc:
Mary E. O'Reilly Harvey B. Brugger, Supervisor FirstEnergy Radiological Assistance Section 76 South Main Street Bureau of Radiation Protection Akron, OH 44308 Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company Carol O'Claire, Chief, Radiological Branch Davis-Besse Nuclear Power Station Ohio Emergency Management Agency 5501 North State - Route 2 2855 West Dublin Granville Road Oak Harbor, OH 43449-9760 Columbus, OH 43235-2206 Jay E. Silberg, Esq. Director Shaw, Pittman, Potts Ohio Department of Commerce and Trowbridge Division of Industrial Compliance 2300 N Street, NW. Bureau of Operations & Maintenance Washington, DC 20037 6606 Tussing Road P.O. Box 4009 Regional Administrator Reynoldsburg, OH 43068-9009 U.S. Nuclear Regulatory Commission 801 Warrenville Road Ohio Environmental Protection Agency Lisle, IL 60523-4351 DERR--Compliance Unit ATTN: Zack A. Clayton Michael A. Schoppman P.O. Box 1049 Framatome Technologies Incorporated Columbus, OH 43266-0149 1700 Rockville Pike, Suite 525 Rockville, MD 20852 State of Ohio Public Utilities Commission Resident Inspector 180 East Broad Street U.S. Nuclear Regulatory Commission Columbus, OH 43266-0573 5503 North State Route 2 Oak Harbor, OH 43449-9760 Attomey General Department of Attorney Plant Manager 30 East Broad Street FirstEnergy Nuclear Operating Company Columbus, OH 43216 Davis-Besse Nuclear Power Station 5501 North State - Route 2 President, Board of County Oak Harbor, OH 43449-9760 Commissioners of Ottawa County Port Clinton, OH 43252
ML013 OFFICE LPM:DE PM:PD3-2 LA:PDIII-1 SC:PDIII-2 PD:PDIII D: DE NAME JZimmerman/ SSands THarris AMendiola SBajwa JStrosnider LBurkhart DATE OFFICE BC:DSSA/SPSB OGC D:DLPM ADPT D:NRR NAME RBarret LChandler JZwolinski/ BSheron SCollins/
LMarsh JJohnson DATE