Category:License-Operator
MONTHYEARML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17234A6362017-08-22022 August 2017 Requalification Program Inspection - Pilgrim Nuclear Power Station ML18081A9342017-02-0808 February 2017 Final Qa/Related Forms - Form ES-401-6 (Folder 1) ML17046A1002017-02-0808 February 2017 NRC- Initial Operator Licensing Operating Test Approval - Pilgrim Nuclear Power Station ML17046A0912017-02-0808 February 2017 Initial Operator Licensing Written Examination Approval - Pilgrim Nuclear Power Station ML17118A3052017-02-0303 February 2017 Final Outlines (Folder 3) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML15212A6072015-07-30030 July 2015 Requalification Program Inspection ML15148A3382015-05-28028 May 2015 Response to Request for Qualification Review of a Proposed Senior Operator Applicant at Pilgrim Nuclear Power Station ML15043A7112015-02-0505 February 2015 Addendum to Final Operator Exam (Folder 3) ML14094A1652014-04-0202 April 2014 Post Exam Comments, Resolution, and Technical References (Folder 1) ML14141A1882014-03-31031 March 2014 Final Qa/Related Forms (Folder 1) ML14094A1572014-03-25025 March 2014 Final Operating Exam (Sections a, B and C) (Folder 3) ML14094A1642014-03-25025 March 2014 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML14094A1612014-03-25025 March 2014 Draft Written Exam (Folder 2) ML14094A1602014-03-25025 March 2014 Draft - Outlines (Folder 2) ML14094A1592014-03-25025 March 2014 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML14094A1582014-03-25025 March 2014 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML14094A1562014-03-25025 March 2014 Written Exam Handouts to Applicants (Folder 3) ML14094A1552014-03-25025 March 2014 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML14094A1532014-03-25025 March 2014 Final Outlines (Folder 3) ML14058A0062014-02-26026 February 2014 Initial Operator Licensing Written Test Approval Pilgrim Nuclear Power Station ML14049A4932014-02-18018 February 2014 Initial Operator Licensing Operating Test Approval ML1202300092012-01-0606 January 2012 Final Qa/Related Forms (Folder 1) ML1202300182011-12-20020 December 2011 Handouts to Applicants-Summary of References (Folder 3) ML1202300142011-12-20020 December 2011 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML1202300122011-12-20020 December 2011 Final Outlines (Folder 3) ML1135305992011-12-19019 December 2011 Operator Licensing Written Retake Examination Approval - Pilgrim Nuclear Power Station ML1202300202011-11-27027 November 2011 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML1202300222011-11-10010 November 2011 Draft Written (SRO Only)Exam (Folder 2) ML1130000532011-10-27027 October 2011 Announcement of Generic Fundamentals Examination 2012 Administration Dates ML1202300212011-10-27027 October 2011 Draft - Outlines (Folder 2) ML1118701782011-02-0101 February 2011 Final Qa/Related Forms (Folder 1) ML1118701762011-02-0101 February 2011 Post Exam Comments (Folder 1) ML1110104112011-01-24024 January 2011 Final Operating Exam (Sections a, B, and C) (Folder 3) ML1110104062011-01-24024 January 2011 Final Written Examination with Answer Key (401-5 Format) ML1110104092011-01-24024 January 2011 Handouts to Applicants (Folder 3) ML1110104022011-01-24024 January 2011 Final Outlines (Folder 3) ML1101403432011-01-14014 January 2011 Announcement of Generic Fundamentals Examination (GFE) 2011 Administration Dates ML1106204742011-01-0707 January 2011 Draft Written Exam (Draft 2) ML1106204792011-01-0707 January 2011 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML1027800572010-10-0505 October 2010 Senior Reactor and Reactor Operator Initial Examinations - Pilgrim Nuclear Power Station ML1001200182010-01-0808 January 2010 2010 Annual Letter - Generic Fundamentals Examination (GFE) Section, Dated 01/08/10 ML1001100212010-01-0808 January 2010 December 9, 2009 NRC Generic Fundamentals Examination (GFE) Results for Pilgrim Nuclear Power Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML0924702012009-09-0404 September 2009 Requalification Program Inspection (Pilgrim Nuclear Power Station) ML0913101102009-05-12012 May 2009 Final Qa/Related Forms (Folder 1) ML0911302182009-04-23023 April 2009 NRC Operator Licensing Initial Exam Results, Pilgrim Nuclear Power Station (Cover Letter Publicly Available; Enclosures Withheld from Public) ML0910006432009-03-31031 March 2009 Draft - Outlines (Folder 2) ML0912505492009-03-20020 March 2009 Final - RO & SRO Written Examination with Answer Key (401-5 Format) (Folder 3) 2019-05-15
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML17046A1002017-02-0808 February 2017 NRC- Initial Operator Licensing Operating Test Approval - Pilgrim Nuclear Power Station ML17046A0912017-02-0808 February 2017 Initial Operator Licensing Written Examination Approval - Pilgrim Nuclear Power Station ML18081A9342017-02-0808 February 2017 Final Qa/Related Forms - Form ES-401-6 (Folder 1) ML17118A3052017-02-0303 February 2017 Final Outlines (Folder 3) ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML15212A6072015-07-30030 July 2015 Requalification Program Inspection ML15148A3382015-05-28028 May 2015 Response to Request for Qualification Review of a Proposed Senior Operator Applicant at Pilgrim Nuclear Power Station ML15043A7112015-02-0505 February 2015 Addendum to Final Operator Exam (Folder 3) ML14094A1652014-04-0202 April 2014 Post Exam Comments, Resolution, and Technical References (Folder 1) ML14141A1882014-03-31031 March 2014 Final Qa/Related Forms (Folder 1) ML14094A1562014-03-25025 March 2014 Written Exam Handouts to Applicants (Folder 3) ML14094A1642014-03-25025 March 2014 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML14094A1612014-03-25025 March 2014 Draft Written Exam (Folder 2) ML14094A1602014-03-25025 March 2014 Draft - Outlines (Folder 2) ML14094A1592014-03-25025 March 2014 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML14094A1582014-03-25025 March 2014 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML14094A1572014-03-25025 March 2014 Final Operating Exam (Sections a, B and C) (Folder 3) ML14094A1552014-03-25025 March 2014 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML14094A1532014-03-25025 March 2014 Final Outlines (Folder 3) ML14058A0062014-02-26026 February 2014 Initial Operator Licensing Written Test Approval Pilgrim Nuclear Power Station ML14049A4932014-02-18018 February 2014 Initial Operator Licensing Operating Test Approval ML1202300092012-01-0606 January 2012 Final Qa/Related Forms (Folder 1) ML1202300182011-12-20020 December 2011 Handouts to Applicants-Summary of References (Folder 3) ML1202300142011-12-20020 December 2011 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML1202300122011-12-20020 December 2011 Final Outlines (Folder 3) ML1135305992011-12-19019 December 2011 Operator Licensing Written Retake Examination Approval - Pilgrim Nuclear Power Station ML1202300202011-11-27027 November 2011 NRC Comments on Draft Licensee-Developed Exam (Written) (Folder 2) ML1202300222011-11-10010 November 2011 Draft Written (SRO Only)Exam (Folder 2) ML1130000532011-10-27027 October 2011 Announcement of Generic Fundamentals Examination 2012 Administration Dates ML1202300212011-10-27027 October 2011 Draft - Outlines (Folder 2) ML1118701762011-02-0101 February 2011 Post Exam Comments (Folder 1) ML1118701782011-02-0101 February 2011 Final Qa/Related Forms (Folder 1) ML1110104092011-01-24024 January 2011 Handouts to Applicants (Folder 3) ML1110104112011-01-24024 January 2011 Final Operating Exam (Sections a, B, and C) (Folder 3) ML1110104022011-01-24024 January 2011 Final Outlines (Folder 3) ML1110104062011-01-24024 January 2011 Final Written Examination with Answer Key (401-5 Format) ML1101403432011-01-14014 January 2011 Announcement of Generic Fundamentals Examination (GFE) 2011 Administration Dates ML1106204792011-01-0707 January 2011 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML1106204742011-01-0707 January 2011 Draft Written Exam (Draft 2) ML1027800572010-10-0505 October 2010 Senior Reactor and Reactor Operator Initial Examinations - Pilgrim Nuclear Power Station ML1001100212010-01-0808 January 2010 December 9, 2009 NRC Generic Fundamentals Examination (GFE) Results for Pilgrim Nuclear Power Station (Cover Letter Publicly Available, Enclosures Withheld from Public) ML1001200182010-01-0808 January 2010 2010 Annual Letter - Generic Fundamentals Examination (GFE) Section, Dated 01/08/10 ML0924702012009-09-0404 September 2009 Requalification Program Inspection (Pilgrim Nuclear Power Station) ML0913101102009-05-12012 May 2009 Final Qa/Related Forms (Folder 1) ML0911302182009-04-23023 April 2009 NRC Operator Licensing Initial Exam Results, Pilgrim Nuclear Power Station (Cover Letter Publicly Available; Enclosures Withheld from Public) ML0910006432009-03-31031 March 2009 Draft - Outlines (Folder 2) ML0912505492009-03-20020 March 2009 Final - RO & SRO Written Examination with Answer Key (401-5 Format) (Folder 3) ML0912505522009-03-0101 March 2009 Handouts to Applicants (Folder 3) 2019-05-15
[Table view] |
Text
Written question ID 5-rewording in stem to clarify that turbine speed is 1700 RPM.
Written question ID 9-changed distracter 'c' to "be maintained in service until the RCIC quad water level reaches the max safe operating limit.
Written question ID 10-added "Torus bulk water temperature is 90 degrees F" to stem Written question ID 18-reworded stem to clarify that the plant was operating normally prior to the transient in question.
Written question ID 23-reworked question such that it asks about CRD temperatures instead of cooling water flow and pressure.
Written question ID 26-Added "In accordance with plant procedures" to stem.
Written question ID 32-Rewrote question to focus on Area Hi Rad instead of Process Hi Rad.
Written question ID 37-changed distracter 'a' to "Spray the drywell."
Written question ID 46-Reworded stem to ask for the basis for action.
Written question ID 51-Deleted "and" from distracter 'd'.
Written question ID 55-Added "Drywell sprays have been initiated per EOP-03 in response to a high drywell pressure condition" to the stem.
Written question ID 62-Added "power" to the stem.
Written question ID 63-rewrite distracters to delete references to channels and only discuss no action/half scram/full scram where appropriate.
Written question ID 66-added second part of question to include the procedural guidance (ARPs) that would be needed to address a stuck IRM detector.
Written question ID 69-rewrote question to discuss a lowering of SRM detector gas pressure and SRM UO enrichment Written question ID 71-changed "is" to "are" in stem.
Written question ID 80-rewrote question to ask about what components limits steam flow as power is increasing.
Written question ID 82-added part to question to ask what action is required if timer does not function.
Written question ID 84-added second part of question to ask what procedural guidance would direct in response to given situation.
Written question ID 86-changed question to ask about the permissibility of opening disconnects under load as well as the basis for this.
Written question ID 101-changed question to also ask the reason for delaying Recirc Pump Field Breaker Trip.
Written question ID 115-changed question to ask about how long you can go below minimum manning.
Admin Section RO Question A.3-1-Changed "Under what conditions may the RP Technician remain outside the area" to read "What four (4) conditions must be met in order for the RP Technician to remain outside the area?"
Designated steps 5, 12, and 13 on Admin JPM 4 as critical steps.
On JPM 1, changed PNPS 2.1.1 from Rev 118 to Rev 119.
On JPM 2, Step 9, changed "Set EPR SETPT to" to "Verify EPR SETPT set to" and made step non-critical.
On JPM 3, Step 10, added verify VEX 21 OB starts.
On JPM 5, Step 15, added note to IF operator to Delete the MO-1201-2 override.
On JPM 6, Initial Conditions changed such that Rod 30-31 was the last rod complete; changed the cue to indicate that rod 34-31 should be the next rod exercised; step 2, changed rod 18-31 to rod 34-31; step 5 deleted comment about JPM steps 2-5 being repeated for each rod until 38-31 is reached; step 6 added "per 8.3.2" to the comment and made step non-critical
Scenario 2 Event 4 change 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> LCO to tracking LCO Scenario 2 Event 4 change from C IRM to G IRM Scenario 2 Event 3 set up lesson plan to drift 4 th rod in next step and 8 th rod in next step, will allow examiner to specify which rod is to be drifted based on how much they need to see on reactivity manip.
Scenario 3 Event 5 add steps to allow resetting locked up FRV Scenario 3 Event 4 delete step to determine EAL not exceeded Scenario 3 Event 6 add note that power may be reduced below Stop Valve Closure Scram Setpoint and changed responsibility for changing speed load changer setting from RO to BOP Scenario 3 Event 7 add note that if the 'A' FRV Lockup is not reset, the operator must trip the RFPs or close HP Feed Heater Block MOVs and add note that examiner will cue the simulator operator when RPS/ARI bypass should be inserted.
Scenario 3 Event 8 add note that Boron may be injected with either RWCU or SBLC systems.
Scenario 4 Event 3 add note that the non-licensed operator may be called to the Control Room for a brief prior to placing RPS on backup power supply.
Scenario 4 Event 6 change step on manually placing Recirc Pumps at Minimum Speed to Trip Recirc Pumps (Scoop Tubes are locked up) and change step for recognizing that MSIVs have closed to CloseNerify Closed MSIVs