Farley Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/26/2002 13:15:24 Report 22 6
EB1-TFP
- TRIENNIAL FIRE PROTECTION INSP Baseline Inspections 09/09/2002 09/13/2002 Fire Protection IP 7111105T 1, 2 3
PS-RP
- RADIATION PROTECTION Baseline Inspections 09/16/2002 09/20/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 09/16/2002 09/20/2002 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 09/16/2002 09/20/2002 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 09/16/2002 09/20/2002 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 09/23/2002 09/27/2002 Inservice Inspection Activities IP 7111108 2
1 EB2-ISI
- INSERVICE INSPECTION-CRDM TI-U2 Safety Issues 09/23/2002 09/27/2002 Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles (NRC Bulletin 2001-01)
Baseline Inspections 09/23/2002 09/27/2002 Inservice Inspection Activities IP 7111108 2
1 2515/145
- TI 2515/145 (U2) RE: BULLETIN 01-01 Safety Issues 09/23/2002 09/29/2002 Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles (NRC Bulletin 2001-01)
2 PS-RP
- RADIATION PROTECTION Baseline Inspections 09/30/2002 10/04/2002 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 09/30/2002 10/04/2002 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 09/30/2002 10/04/2002 Performance Indicator Verification IP 71151 1, 2 1
PS-SEC
- SECURITY - PI VERIFICATION Baseline Inspections 03/10/2003 03/14/2003 Access Authorization Program (Behavior Observation Only)
IP 7113001 1, 2 Baseline Inspections 03/10/2003 03/14/2003 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorization)
IP 7113002 1, 2 Baseline Inspections 03/10/2003 03/14/2003 Performance Indicator Verification IP 71151 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U1 Baseline Inspections 04/07/2003 04/11/2003 Inservice Inspection Activities IP 7111108 1
3 OL EXAM
- INITIAL EXAM Not Applicable 05/19/2003 05/23/2003 FARLEY/EXAMS AT POWER FACILITIES V23183 1
1 BR2-FP
- FLOOD PROTECTION Baseline Inspections 06/23/2003 06/26/2003 Flood Protection Measures IP 7111106 1, 2 3
PS-RP
- RADIATION PROTECTION Baseline Inspections 07/28/2003 08/01/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 07/28/2003 08/01/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 07/28/2003 08/01/2003 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 07/28/2003 08/01/2003 Radiological Environmental Monitoring Program IP 7112203 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Farley Inspection / Activity Plan 09/01/2002 - 09/30/2003 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/26/2002 13:15:24 Report 22 3
PS-RP
- RADIATION PROTECTION Baseline Inspections 07/28/2003 08/01/2003 Performance Indicator Verification IP 71151 1, 2 1
- EP INSPECTION Baseline Inspections 08/04/2003 08/08/2003 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 08/04/2003 08/08/2003 Performance Indicator Verification IP 71151 1, 2 3
EB2-MODS - MODIFICATIONS/10CFR50.59 Baseline Inspections 08/11/2003 08/15/2003 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 08/11/2003 08/15/2003 Permanent Plant Modifications IP 7111117B 1, 2 1
EB2-PIMR
- PI&R/MR Baseline Inspections 09/15/2003 09/19/2003 Maintenance Effectiveness IP 7111112B 1, 2 Baseline Inspections 09/15/2003 09/19/2003 Identification and Resolution of Problems IP 71152 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Maintenance Effectiveness IP 7111112B 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Identification and Resolution of Problems IP 71152 1, 2 1
PS-SEC
- SECURITY Baseline Inspections 09/29/2003 10/03/2003 Response to Contingency Events (Protective Strategy and Implementation of Protective Strategy)
IP 7113003 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.