ML022400529
| ML022400529 | |
| Person / Time | |
|---|---|
| Site: | Catawba |
| Issue date: | 08/26/2002 |
| From: | Binoy Desai NRC/RGN-II/DRP/RPB1 |
| To: | Gordon Peterson Duke Energy Corp |
| Shared Package | |
| ML022400446 | List: |
| References | |
| IMC 0305 | |
| Download: ML022400529 (4) | |
Text
August 26, 2002 Duke Energy Corporation ATTN: Mr. G. R. Peterson Vice President Catawba Nuclear Station 4800 Concord Road York, SC 29745
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - CATAWBA NUCLEAR STATION
Dear Mr. Peterson:
On August 5, 2002, the NRC staff completed its mid-cycle plant performance assessment of Catawba Nuclear Station. In accordance with NRC Inspection Manual Chapter 0305 Operating Reactor Assessment Program, the mid-cycle review involved the participation of all technical divisions in evaluating the performance of your Catawba facility for the first half of the current assessment cycle, January 1 - December 31, 2002. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections which may conflict with your plant activities.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we curently plan to conduct baseline inspections and license renewal related inspections at your facility through September 30, 2003.
The enclosed inspection plan details the inspections scheduled through September 30, 2003.
The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The last six months of the inspection plan is tentative and may be revised at the end-of-cycle review. In addition, the NRC is in the process of finalizing a Temporary Instruction that will be used to review implementation of the Interim Compensatory Measures required by the Agencys Security Order to all commercial nuclear power plants dated February 25, 2002. Schedules have not yet been finalized, but it is anticipated that these inspections will begin within the next calendar quarter. Once finalized, the details will be communicated by separate correspondence.
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
DEC 2
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Robert Haag at 404-562-4550 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA R. E. Carroll Jr. for/
Binoy B. Desai, Acting Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 50-413, 50-414 License Nos. NPF-35, NPF-52
Enclosure:
Catawba Inspection/Activity Plan cc w/encl:
Regulatory Compliance Manager Duke Energy Corporation Electronic Mail Distribution Lisa Vaughn Legal Department (PB05E)
Duke Energy Corporation 422 South Church Street Charlotte, NC 28242 Anne Cottingham Winston and Strawn Electronic Mail Distribution North Carolina MPA-1 Electronic Mail Distribution Henry J. Porter, Director Div. of Radioactive Waste Mgmt.
S. C. Department of Health and Environmental Control Electronic Mail Distribution R. Mike Gandy Division of Radioactive Waste Mgmt.
S. C. Department of Health and Environmental Control Electronic Mail Distribution Richard P. Wilson, Esq.
Assistant Attorney General S. C. Attorney Generals Office Electronic Mail Distribution Vanessa Quinn Federal Emergency Management Agency Electronic Mail Distribution North Carolina Electric Membership Corporation Electronic Mail Distribution Peggy Force Assistant Attorney General N. C. Department of Justice Electronic Mail Distribution County Manager of York County, SC Electronic Mail Distribution Piedmont Municipal Power Agency Electronic Mail Distribution Manager Nuclear Regulatory Licensing Duke Energy Corporation 526 S. Church Street Charlotte, NC 28201-0006
DEC 3
Distribution w/encl:
C. Patel, NRR RIDSNRRDIPMLIPB PUBLIC OFFICE SIGNATURE NAME RCarroll DATE 8/22/2002 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO PUBLIC DOCUMENT YES NO OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML022400529.wpd