SScott A. Bauer 10 CFR 140.21(e)

Department Leader Regulatory Affairs Tel 623/393-5978 Mail Station 7636 Palo Verde Nuclear Fax 623/393-5442 P.O. Box 52034 Generating Station e-mail sbauer@apsc.com Phoenix, AZ 85072-2034 102-04822 - SAB/TNW/CJJ July 26, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station: P1-37 Washington, DC 20555-0001

Dear Sir:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528/529/530 Licensee Guarantee of Payment of Deferred Premium Pursuant to the requirements of 10 CFR 140.21(e), Arizona Public Service Company (APS), for itself and on behalf of the PVNGS Participants, has enclosed projected cash flow statements for each participant. Please note that the projected cash flow statement for the El Paso Electric Company is considered a confidential document, for which an affidavit is provided. The affidavit sets forth the basis on which the Commission may withhold the information from public disclosure. Accordingly, it is requested that the El Paso Electric Company projected cash flow statement be withheld from public disclosure.

No commitments are being made to the NRC in this letter. If you have any questions, please contact Thomas N. Weber at (623) 393-5764.

Sincerely, SAB/TNW/CJJ Enclosure cc:

E. W. Merschoff (all w/o enclosure)

J. N. Donohew D. G. Naujock PVNGS Resident Inspector