June 2002 Monthly Operating Report for Surry Power Station Units 1 & 2
ML022040005
Person / Time
Site: Surry  Dominion icon.png
Issue date: 07/15/2002
From: Blount R
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
02-426, SPSLic/JSA R0
Download: ML022040005 (16)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 July 15, 2002 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Serial No.

SPS Lic/JSA Docket Nos.

License Nos.

Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT The Monthly Operating Report for Surry Power Station Units 1 and 2 for the month o0 June 2002 is provided in the attachment.

If you have any questions or require additional information, please contac.L us.

Very truly yours, Richard H. Blount, Site Vice President Surry Power Station Attachment Commitments made by this letter: None cc:

United States Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23 T85 Atlanta, Georgia 30303-8931 Mr. R A. Musser NRC Senior Resident Inspector Surry Power Station 02-426 RO 50-280 50-281 DPR-32 DPR-37

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT No. 02-06 Approved:

e Vicle resident Yate

Surry Monthly Operating Report No. 02-06 Page 2 of 15 TABLE OF CONTENTS Section Page Operating Data Report - Unit No. 1............................................................................................................................

3 Operating Data Report - Unit No. 2............................................................................................................................

4 Unit Shutdowns and Power Reductions - Unit No. 1.............................................................................................

5 Unit Shutdowns and Power Reductions - Unit No. 2..............................................................................................

6 Average Daily Unit Power Level - Unit No. 1.......................................................................................................

7 Average Daily Unit Power Level - Unit No. 2......................................................................................................

8 Summary of Operating Experience - Unit Nos. 1 and 2.........................................................................................

9 Facility Changes That Did Not Require NRC Approval.........................................................................................

10 Procedure or Method of Operation Changes That Did Not Require NRC Approval............................................

11 Tests and Experiments That Did Not Require NRC Approval..............................................................................

12 Chemistry Report.....................................................................................................................................................

13 Fuel Handling - Unit Nos. 1 and 2............................................................................................................................

14 Description of Periodic Test(s) Which Were Not Completed Within the Time Limits Specified in Technical Specifications.......................................................................................................................

15

Surry Monthly Operating Report No. 02-06 Page 3 of 15 OPERATING DATA REPORT Docket No.:

Date:

Completed By:

Telephone:

50-280 07/01/02 R. Stief (757) 365-2486 Unit Name:...........................................................

Reporting Period:.................................................

Licensed Thermal Power (MW t):..........................

Nameplate Rating (Gross MW e):.........................

Design Electrical Rating (Net MW e):....................

Maximum Dependable Capacity (Gross MWe):...

Maximum Dependable Capacity (Net MWe):.......

Surry Unit 1 June 2002 2546 847.5 788 842 810

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

9.

Power Level To Which Restricted, If Any (Net MWe):

10.

Reasons For Restrictions, If Any:

Hours in Reporting Period Hours Reactor Was Critical Reactor Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy Generated (MWH)

Net Electrical Energy Generated (MWH)

Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC Net)

Unit Capacity Factor (Using DER Net)

Unit Forced Outage Rate This Month 720.0 720.0 0.0 720.0 0.0 1833120.0 620301.0 588362.0 100.0%

100.0%

100.9%

103.7%

0.0%

Year-To-Date 4343.0 4343.0 0.0 4343.0 0.0 10999962.5 3691874.0 3548111.0 100.0%

100.0%

100.9%

103.7%

0.0%

Cumulative 258791.0 190104.6 3774.5 187445.2 3736.2 446307440.4 146771977.0 140140972.0 72.4%

73.9%

69.2%

68.7%

12.5%

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 2000]

25.

If Shut Down at End of Report Period, Estimated Date of Start-up:

Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26.

Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

1.
2.
3.
4.
5.
6.

7.

11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.

23.

Surry Monthly Operating Report No. 02-06 Page 4 of 15 OPERATING DATA REPORT Docket No.:

Date:

Completed By:

Telephone:

50-281 07/01/02 R. Stief (757) 365-2486 Unit Name:...........................................................

Reporting Period:.................................................

Licensed Thermal Power (MW t):..........................

Nameplate Rating (Gross MW e):.........................

Design Electrical Rating (Net MW e):....................

Maximum Dependable Capacity (Gross MWe):...

Maximum Dependable Capacity (Net MWe):.......

Surry Unit 2 June 2002 2546 847.5 788 847 815

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:

9.

Power Level To Which Restricted, If Any (Net MWe):

10.

Reasons For Restrictions, If Any:

Hours in Reporting Period Hours Reactor Was Critical Reactor Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy Generated (MWH)

Net Electrical Energy Generated (MWH)

Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC Net)

Unit Capacity Factor (Using DER Net)

Unit Forced Outage Rate This Month 720.0 720.0 0.0 720.0 0.0 1833058.9 611693.0 589501.0 100.0%

100.0%

100.5%

103.9%

0.0%

Year-To-Date 4343.0 3684.8 0.0 3646.3 0.0 9203747.3 3087619.0 2979759.0 84.0%

84.0%

84.2%

87.1%

0.0%

Cumulative 255672.0 187502.8 328.1 185262.7 0.0 442228651.5 145464626.0 138936809.0 72.5%

72.5%

69.2%

69.0%

10.0%

24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 20001

25.

If Shut Down at End of Report Period, Estimated Date of Start-up:

Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26.

Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

1.
2.
3.
4.
5.
6.

7.

11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.

23.

Surry Monthly Operating Report No. 02-06 Page 5 of 15 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: June 2002 Docket No.:

50-280 Unit Name:

Surry Unit 1 Date:

07/01/02 Completed by:

R. Stief Telephone:

(757) 365-2486 None during the Reporting Period (1)

F:

Forced S:

Scheduled (2)

REASON:

A -

Equipment Failure (Explain)

B -

Maintenance or Test C -

Refueling D -

Regulatory Restriction E

Operator Training & Licensing Examination F

Administrative G -

Operational Error (Explain)

H Other (Explain)

(3)

METHOD:

1 Manual 2

Manual Scram 3

Automatic Scram 4

Other (Explain)

(4)

Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG 0161)

(5)

Exhibit 1 - Same Source

Surry Monthly Operating Report No. 02-06 Page 6 of 15 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: June 2002 Docket No.:

Unit Name:

Date:

Completed by:

Telephone:

50-281 Surry Unit 2 07/01/02 R. Stief (757) 365-2486 None during the Reporting Period (1)

F:

Forced SR Scheduled (2)

REASON:

A -

Equipment Failure (Explain)

B -

Maintenance or Test C -

Refueling D -

Regulatory Restriction E -

Operator Training & Licensing Examination F -

Administrative G -

Operational Error (Explain)

H Other (Explain)

(3)

METHOD:

1 Manual 2

Manual Scram 3

Automatic Scram 4

Other (Explain)

(4)

Exhibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG 0161)

(5)

Exhibit 1 - Same Source

Surry Monthly Operating Report No. 02-06 Page 7 of 15 AVERAGE DAILY UNIT POWER LEVEL MONTH:

June 2002 Day 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 Average Daily Power Level (MWe - Net) 818 818 819 819 818 817 820 821 820 819 818 818 818 818 Day 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Docket No.:

50-280 Unit Name:

Surry Unit 1 Date:

07/03/02 Completed by:

R. Stief Telephone:

(757) 365-2486 Average Daily Power Level (MWe - Net) 818 816 816 817 818 817 816 815 814 813 813 814 815 815 819 819 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 02-06 Page 8 of 15 AVERAGE DAILY UNIT POWER LEVEL Docket No.:

50-281 Unit Name:

Surry Unit 2 Date:

07/03/02 Completed by:

R. Stief Telephone:

(757) 365-2486 MONTH:

June 2002 Day 1

2 3

4 5

6 7

8 9

10 11 12 13 14 15 16 Average Daily Power Level (MWe - Net) 821 822 821 821 821 820 820 822 821 820 820 819 818 819 818 819 Day 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Average Daily Power Level (MWe - Net) 818 819 819 819 819 817 817 816 816 816 817 817 816 816 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 02-06 Page 9 of 15

SUMMARY

OF OPERATING EXPERIENCE MONTH/YEAR; June 2002 The following chronological sequence by unit is a summary of operating experiences for this month that required load reductions or resulted in significant non-load related incidents.

0000 2400 0000 2400 Unit started the month at 100% / 848 MWe.

Unit finished the month at 100% / 846 MWe.

Unit started the month at 100% / 851 MWe.

Unit finished the month at 100% / 848 MWe.

UNIT ONE:

06/01/02 06/30/02 UNIT Two:

06/01/02 06/30/02

Surry Monthly Operating Report No. 02-06 Page 10 of 15 FACILITY CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTH/YEAR: June 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-06 Page 11 of 15 PROCEDURE OR METHOD OF OPERATION CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTH/YEAR: June 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-06 Page 12 of 15 TESTS AND EXPERIMENTS THAT DID NOT REQUIRE NRC APPROVAL MONTHNEAR: June 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-06 Page 13 of 15 CHEMISTRY REPORT MONTHIYEAR: June 2002 Unit No. 1 Unit No. 2 Primary Cooiant Analysis Max.

Min.

Avg.

Max.

Min.

Avg.

Gross Radioactivity, liCi/ml 3.41 E-1 2.38E-1 2.91E-1 3.29E-1 2.21 E-1 2.65E-1 Suspended Solids, ppm 0.01 0.01 0.01 0.01 0.01 0.01 Gross Tritium, ýtCi/ml 1.23E+0 1.14E+0 1.19E+0 7.54E-1 5.07E-1 6.25E-1 1131, gCtI/ml 2.08E-4 1.06E-4 1.51 E-4 1.27E-4 7.23E-5 1.02E-4 1131/1133 0.13 0.06 0.08 0.17 0.08 0.12 Hydrogen, cc/k_

-35.6 34.3 35 39.1 36.2 37 Lithium, p~m 2.33 2.08 2.22 2.61 2.33 2.46 Boron-iC, pp-

  • 206 190 198 276 264 272 Oxygen, (DO), ppm

< 0.005

_ 0.005

  • 0.005

< 0.005

< 0.005

  • 0.005 Chloride, porn 0.006 0.004 0.005 0.008 0.003 0.003 pH @ 25 degree Celsius I

Boron - 1C = Total Boron x 0196 Comments:

None 6.67 6.56 6.61 6.46 6.31 6.4

Surry Monthly Operating Report No. 02-06 Page 14 of 15 FUEL HANDLING UNITS 1 & 2 MONTHIYEAR: June 2002 Number of Date Stored or Assemblies Received Der Shipment Assembly Number New or Spent ANSI Initial Fuel Shipping Number Enrichment Cask Activity None duing the Reporting Period New Fuel Shipment or Cask No.

Surry Monthly Operating Report No. 02-06 Page 15 of 15 DESCRIPTION OF PERIODIC TEST(S) WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS MONTH/YEAR: June 2002 None during the Reporting Period