MONTHYEARML0208403382002-03-23023 March 2002 Request for Withholding Information from Public Disclosure (Tac No. MB3902) Project stage: Withholding Request Acceptance ML0208605052002-03-27027 March 2002 NRC Staff Review of License Amendment Request Regarding the Use of the Westinghouse Master Curve Methodology (Tac No. MB3902) Project stage: Approval ML0215503982002-04-23023 April 2002 Application of Master Curve Facture Toughness for Reactor Pressure Vessel Integrity Evaluation of BVPS-1 Project stage: Request ML0215503882002-05-17017 May 2002 Master Curve Submittal, NRC Staff Observations Project stage: Other ML0215402232002-05-30030 May 2002 Summary of April 23, 2002, Meeting an Application for a License Amendment to Allow Fenoc to Use the Westinghouse Master Curve Methodology to Establish Reactor Vessel Pressure-Temperature Limits (Tac No. MB3902) Project stage: Meeting ML0226000852002-09-17017 September 2002 Withdrawal of an Amendment Request and Requests for Associated Exemptions Project stage: Withdrawal ML0227506272002-10-0303 October 2002 Return of Proprietary Materials Associated with Withdrawn Amendment Request and Requests for Associated Exemptions Project stage: Other 2002-04-23
[Table View] |
|
---|
Category:Slides and Viewgraphs
MONTHYEARML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML22187A0652022-06-0808 June 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - NRC Presentation Slides ML22061A1392022-03-0202 March 2022 Pre-submittal Meeting Slides for Planned License Amendment Request to Consolidate Fuel Decay Time Requirements ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20143A0422020-05-22022 May 2020 Presentation Slides - Technical Justification for the Ghent Version 2 Probe Qualification and Probability of Detection - May 26, 2020 (Non-Proprietary Version) ML20143A0352020-05-22022 May 2020 Presentation Slides - Ghent Version 2 Probe License Amendment Request - Pre-submittal Phone Call - May 26,2020 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML17335A0372017-12-0505 December 2017 Presentation Slides - Beaver Valley Power Station, Unit 2 - Steam Generator Alloy 800 Sleeve License Amendment Request - Pre-Submittal Meeting on 12/05/2017 ML16089A0622016-03-30030 March 2016 Meeting to Discuss BVPS Draft PRA RAI - Slides ML16098A1642016-03-30030 March 2016 Fpra Dependency Analysis ML15230A2882015-08-13013 August 2015 Slides: NRC Fundamental of Emergency Preparedness Beaver Valley Power Station, August 13, 2015 ML12319A1322012-11-15015 November 2012 FENOC - NRC Pre-Application Meeting License Amendment Request November 15, 2012 ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12215A4152012-08-0101 August 2012 Presentation from Firstenergy Nuclear Operating Company Beaver Valley NFPA 805 Transition ML1117303602011-06-21021 June 2011 FENOC Licensee Slides for 6-21-11 All FENOC Meeting ML1112503982011-05-0505 May 2011 Aam - NRC Slides ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 ML1014706172010-05-27027 May 2010 Region I and Region III Fire Protection Organization Meeting Slides ML1014101372010-05-21021 May 2010 Bv NRC Strategic Plans Slides for Aam, May 4, 2010 ML1013700202010-05-17017 May 2010 Bv Slides for Annual Assessment Meeting, May 4, 2010 ML1009102662010-03-31031 March 2010 Slides FENOC and NRC Senior Management Briefing, 3-31-10 ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0835303832008-12-11011 December 2008 Meeting Presentation with FENOC - Beaver Valley Power Station, Unit No. 2 Spent Fuel Pool Rerack Project Pre-submittal Meeting ML0832400512008-11-17017 November 2008 Preliminary Results of Environmental Review ML0834504752008-11-0202 November 2008 11/12/2008 Meeting Slides, Beaver Valley License Renewal Public Exit Meeting. ML0818403982008-06-20020 June 2008 NFPA-805 Workshop Handouts - Beaver Valley Rules-Based Presentation ML0808800882008-03-25025 March 2008 FENOC 3-25-08 Annual Assessment Mtg Slides ML0807003932008-03-10010 March 2008 2007 Beaver Valley Annual Assessment Slides ML0801604842008-01-0909 January 2008 Slides - FENOC Public Meeting, Senior Management Briefing, January 9, 2008 ML0735202822007-11-27027 November 2007 Slides, Beaver Valley Power Station License Renewal Process and Environmental Scoping Meeting. ML0722203882007-08-0202 August 2007 (PA-LR) Beaver Valley Power Station License Renewal Project Presentation to NRC August 2, 2007 ML0708706692007-03-28028 March 2007 Annual Performance Assessment, Slides, 4-24-07 ML0634604162006-10-24024 October 2006 Oct 24, 2006 Regulatory Conference Draft Slides ML0625401632006-09-0808 September 2006 Slides: Accelerated ISTS Conversion (Piilot) by P. Hearn, NRR ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 ML0613704312006-05-10010 May 2006 Summary of Annual Assessment Meeting with Firstenergy (Beaver Valley Station) with Attendee List and Licensee Slides ML0606804412006-03-0909 March 2006 NRC Slides for the Beaver Valley Annual Assessment Public Meeting ML0603002272006-01-10010 January 2006 Multi-Regional NRC Public Meeting Licensee (FENOC) Slide Presentation ML0802205572005-09-12012 September 2005 NRC Commissioners Briefing by Firstenergy Nuclear Operating Co ML0523703812005-08-24024 August 2005 Meeting Slides from Beaver Valley 8/24/05 Public Meeting ML0519303562005-07-11011 July 2005 Steam Generator Replacement Meeting Slides ML0514001202005-03-30030 March 2005 NRC Slides for Annual Assessment Meeting with First Energy Nuclear Operating Company (Fenoc), Beaver Valley Station ML0511902682005-03-23023 March 2005 Meeting Presentation Slides - Summary of Meeting with FENOC Re Category 1, Pre-Application Review Re BVPS-1 Steam Generator (SG) Replacement and Related Alternate Source Term (AST) Approval ML0507504182005-03-16016 March 2005 NRC Slides for Public Meeting with First Energy Nuclear Operating Company (FENOC) Ref: Beaver Valley Annual Assessment Performance ML0521401182005-03-0808 March 2005 RIC 2005 Presentation - C1 - Frank J. Koza - Grid Reliability ML0502702022004-12-15015 December 2004 Beaver Valley Power Station Units 1 & 2, Sildes Re Extended Power Uprate - License Amendment Requests LAR 302 & 173 2024-05-16
[Table view] |
Text
Beaver Valley Unit 1 Master Curve Submittal i
NRC Staff Observations
- Therefore, based on these observations, the NRC staff requested that FENOC reevaluate their submittal and address, as necessary:
(1) What data should be used to establish RTTO(U) and the baseline data for measuring shifts in To (i.e., ARTTO) due to irradiation for BVPS-1 limiting plate B6903-1 ?
(2) Given the answer to (1), what effect does this have on their characterization of the margin term to be applied in the calculation of ART?
(3) Given the answer to (1), what effect does this have on their characterization of the bias term to be applied in the calculation of ART?
Beaver Valley Unit 1 Master Curve Submittal NRC Staff Observations
- The staff reviewed FENOC's January 25, 2002, submittal and concluded that the general methodology employed by the licensee was consistent with the methodology approved for Kewaunee in the staff's May 1, 2001, safety evaluation.
RTTO(u) + ARTTO + Margin Term + Bias Term = ART
- However, the staff identified significant issues related to FENOC's use of fracture toughness data available from the testing of unirradiated specimens from BVPS-1 limiting plate B6903-1 (plate heat B6317-1).
- The issues raised by the staff may affect the determination of specific values for RTTO(U), ARTTO, the margin term, and the bias term used to calculate ART values for BVPS-1 limiting plate B6903-1.
Enclosure 2
Beaver Valley Unit 1 Master Curve Submittal NRC Staff Observations
° FENOC chose to determine their RTTO(u) value (and their baseline for measuring shifts in To due to irradiation) based using only the data from the unirradiated /2 T-CT specimens.
a
- FENOC claimed that this was "conservative" since it would provide maximum value for RTTO(u).
also claimed that since they were using this "conservative"
- FENOC initial approach to determine RTTO(U) they did not need to account for property variability when establishing the margin term used in their calculation of ART.
Beaver Valley Unit 1 Master Curve Submittal NRC Staff Observations
- The NRC staff disagrees with FENOC's assertion that the use of only the data from the testing of the unirradiated /2 T-CT specimens is "conservative
- While use of the unirradiated /2 T-CT specimen data alone does give the "most conservative" value for RTTo(U), it's use as the baseline for establishing shifts in To due to irradiation results in a minimum (least conservative) value for ARTTO.
- The NRC staff concluded that, when resultant ART values are considered, the use of the unirradiated /2 T-CT specimen data alone results in ART values which are the smallest (least conservative) values which could be determined from the available unirradiated specimen data.