W Duke WPower A Duke Energy Company Gary R. Peterson Vice President Catawba Nuclear Station Duke Power 4800 Concord Rd.
York, SC 29710 (803) 831-4251 OFFICE (803) 831-3221 FAX grpeters@duke-energy. com May 22, 2002 U.S. Nuclear Regulatory Commission ATTENTION:
Document Control Desk Washington, D.C.
20555-0001
Subject:
Duke Energy Corporation Catawba Nuclear Station Unit 1 Docket No.: 50-413 Core Operating Limits Report (COLR)
Catawba Unit 1 Cycle 14, Revision 22 Attached, pursuant to Catawba Technical Specification 5.6.5, is an information copy of the Core Operating Limits Report for Catawba Unit 1 Cycle 14.
The Unit 1 COLR is being revised to update the limits of the new Catawba 1 Cycle 14 reload core.
The COLR Appendix A power distribution monitoring factors is included with the letter to the NRC Document Control Desk within the CD-ROM.
The attachment and CD do not contain any new commitments.
Please direct any questions or concerns to George Strickland at (803) 831-3585.
Sincerely, G.
R. Peterson Attachments
U.
S. Nuclear Regulatory Commission May 22, 2002 Page 2 xc w/att: L.
A.
Reyes, Regional, Administrator
- USNRC, Region II C.
P. Patel, NRC Senior Project Manager (CNS)
- USNRC, ONRR D.
J.
Roberts Senior Resident Inspector (CNS)