RAI, Related to License Amendment Request
ML021360164
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 05/21/2002
From: Miranda S
NRC/NRR/DLPM/LPD3
To: Forbes J
Nuclear Management Co
References
TAC MB3187
Download: ML021360164 (4)


Text

May 21, 2002 Mr. Jeffrey S. Forbes Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST (TAC NO. MB3187)

Dear Mr. Forbes:

By application dated October 17, 2001, Nuclear Management Company, LLC, requested a license amendment to update the multiplier values for the single-loop operation Average Planar Linear Heat Generation Rate, in Monticellos Technical Specification Section 3.11.A.a. The staff is reviewing your application and requests that you provide some additional information as indicated in the enclosure to this letter.

The enclosed request for additional information was discussed with Mr. D. Neve of your staff on May 8, and May 15, 2002. It was agreed that your response will be submitted by June 21, 2002. If you need to revise this date, please contact me at (301) 415-2303, at the earliest opportunity.

Sincerely,

/RA/

Samuel Miranda, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosure:

Request for Additional Information cc w/encl: See next page

ML021360164 OFFICE PDIII-1/PM PDIII-1/LA PDIII-1/SC NAME SMiranda RBouling /RA by THarris/

LRaghavan DATE 05/21/02 05/21/02 05/21/02 REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST DATED OCTOBER 17, 2001 NUCLEAR MANAGEMENT COMPANY, LLC MONTICELLO NUCLEAR GENERATING PLANT DOCKET NO. 50-263 In Exhibit A of the submittal, the licensee stated that "the primary reason the multiplier value for GE14 fuel is different from GE11 and GE12, is that GE14 has the benefit of the latest upper bound peak cladding temperature (PCT) calculation improvements, which allows the nominal PCT to go higher. Please provide a detailed description of the PCT calculation improvement and identify those differences from the results obtained from NEDE-23785-PA, "The GESTR-LOCA and SAFER Models for Evaluation of Loss-of-Coolant Accident (Volume III),

SAFER/GESTR Application Methodology, 1984. Also, identify the latest approved document in this regard and justify its applicability to GE14 fuel only.

Monticello Nuclear Generating Plant cc:

J. E. Silberg, Esquire Shaw, Pittman, Potts and Trowbridge 2300 N Street, N. W.

Washington, DC 20037 U.S. Nuclear Regulatory Commission Resident Inspectors Office 2807 W. County Road 75 Monticello, MN 55362 Site Licensing Manager Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637 Robert Nelson, President Minnesota Environmental Control Citizens Association (MECCA) 1051 South McKnight Road St. Paul, MN 55119 Commissioner Minnesota Pollution Control Agency 520 Lafayette Road St. Paul, MN 55155-4194 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Commissioner Minnesota Department of Health 717 Delaware Street, S. E.

Minneapolis, MN 55440 Douglas M. Gruber, Auditor/Treasurer Wright County Government Center 10 NW Second Street Buffalo, MN 55313 Commissioner Minnesota Department of Commerce 121 Seventh Place East Suite 200 St. Paul, MN 55101-2145 Adonis A. Neblett Assistant Attorney General Office of the Attorney General 445 Minnesota Street Suite 900 St. Paul, MN 55101-2127 Mr. Roy A. Anderson Executive Vice President and Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Xcel Energy, Inc.

414 Nicollet Mall Minneapolis, MN 55401 March 2002