Letter Sequence Request |
---|
|
|
MONTHYEARML0211504602002-04-25025 April 2002 Notice of Meeting with Firstenergy Nuclear Operating Company on Root Cause Analysis Report Project stage: Request ML0212905242002-05-0707 May 2002 May 7, 2002 Meeting Handouts Forthcoming Meeting with Firstenergy Nuclear Operating Company on Root Cause Analysis Report Project stage: Meeting 2002-04-25
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML23129A6062023-05-0404 May 2023 Special Inspection Team Charters to Evaluate the Circumstances Surrounding the Ground Settling at the Davis-Besse Nuclear Power Station ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML21096A2282021-03-30030 March 2021 FEMA Disapproval of Davis-Besse Exercise Exemption ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML19162A0102019-06-0707 June 2019 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Davis Besse ISFSI ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML15205A1692015-08-0707 August 2015 ACRS Review of the Davis Besse Nuclear Plant LRA - Transmittal of the Sser ML15182A1912015-07-16016 July 2015 Annual Financial Test for a Parent Company Guarantee Given by Firstenergy Solutions Corporation and Firstenergy Corporation ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis IR 05000334/20004122014-07-0808 July 2014 NRC Staff'S Spot-Check Review of First Energy Nuclear Operating Company'S Ownership Interest in Beaver Valley, Units 1 and 2, Perry, and Davis-Besse, Docket No. 05000334, 05000412, 05000440, and 05000346, on June 10, 2014-Finding of No Pote ML14099A4642014-05-0606 May 2014 Summary of Public Meetings to Discuss Draft Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Generating Station, Unit 1 ML13280A9062013-10-21021 October 2013 Forthcoming Meeting with Firstenergy Nuclear Operating Company (FENOC) to Discuss Voluntary Risk Informed Fire Protection Amendment for Davis-Besse ML13142A5122013-07-0202 July 2013 Summary of Telephone Conference Call Held on May 21, 2013, Between NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse Nuclear Power Station, LRA ML13171A2922013-06-13013 June 2013 LTR-13-0540 - Bill Hawkins and Vinod Arora Email San Onofre Nuclear Generating Station (SONGS) Lessons Learn for Davis-Besse ML13154A4442013-06-0404 June 2013 Rai'S Following Ifib Analysis of Fenoc'S 2013 Decommissioning Funding Status Report for Davis-Besse and Perry ML12199A2072012-07-17017 July 2012 Public Meeting Notice to Discuss the 2011 End-of-Cycle Performance Assessment ML12158A4002012-06-0808 June 2012 6/26/2012 Forthcoming Meeting Firstenergy Nuclear Operating Company (FENOC) ML1206901652012-03-0909 March 2012 Memo - Summary of Public Meeting with Industry Regarding Pwrog'S Boric Acid Corrosion Test Program ML12018A1652012-01-27027 January 2012 Summary of Telephone Conference Call Held on November 9, 2011, Between the NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse, LRA ML14028A5462012-01-25025 January 2012 NRC Telecon Regarding Davis-Besse License Renewal Severe Accident Mitigation Alternatives Analysis Questions ML11363A1712012-01-23023 January 2012 Summary of Telephone Conference Call Held on December 12, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Request for Additional Information ML11355A0952011-12-29029 December 2011 Summary of Telephone Conference Call Held on December 8, 2011, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning RAIs Pertaining to the Davis-Besse Nuclear Power Station, LRA ML11348A0212011-12-21021 December 2011 Summary of Telephone Conference Call Held on November 1, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis Besse Nuclear Pow ML11341A1182011-12-14014 December 2011 Summary of Telephone Conference Call Held on June 15, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power ML11339A0862011-12-13013 December 2011 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning RAIs Pertaining to the Davis-Besse Nuclear Power Station LRA ML11327A0082011-12-0202 December 2011 Summary of Telephone Conference Call Held on September 29, 2011, Between the NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse, LRA ML11327A0792011-12-0202 December 2011 Summary of Telephone Conference Call Held on Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis Besse Nuclear Power Station ML11327A0872011-12-0202 December 2011 Summary of Telephone Conference Call Held on July 27, 2011, Between the NRC and Firstenergy Nuclear Operating Company Concerning RAI Pertaining to the Davis-Besse, LRA ML11279A2182011-10-0606 October 2011 Memo - Task Interface Agreement - Evaluation of Compliance with Code for Examination of Flange Stud Holes on the Replacement Vessel Head at the Davis-Besse Nuclear Power Station (TIA 2011-015) ML11242A0032011-09-12012 September 2011 Summary of Conference Call Held on August 4, 2011, Between the NRC and FENOC Concerning Requests for Additional Information Pertaining to the Davis-Besse License Renewal Application ML1122701392011-08-15015 August 2011 Request for Additional Information Response Clarification from Davis-Besse Nuclear Power Station in Support of License Renewal Application Review ML11173A2002011-08-0101 August 2011 Summary of Public Scoping Meetingsconducted Related to the Review of the Davis-Besse Nuclear Power Station, Unit 1, LRA ML11193A2032011-07-26026 July 2011 Final Response to TIA 2011-001, Davis-Besse Nuclear Power Station Safety-Related Batteries Electrical Separation Design and Licensing Bases ML11174A2322011-06-21021 June 2011 for the Record-06-21-2011: NRC Ensures Public Safety Through Rigorous Oversight of Nuclear Power Plant Safety Standards ML1108202762011-06-0303 June 2011 Summary of Site Audit Related to the Review of the License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1 ML11174A2472011-05-31031 May 2011 for the Record-05-31-2011: NRC Chairman Gregory B. Jaczko'S Statement on Nrc'S Commitment to Safety ML1110806902011-04-20020 April 2011 Notice of Meeting with First Energy Nuclear Operating Company (FENOC) to Discuss a Proposed LAR to Delete Technical Specification 5.5.8g, Steam Generator (SG) Program Auxiliary Feedwater Header Inspections ML1028702612010-10-22022 October 2010 11/04/10 Notice of Meeting to Discuss the License Renewal Process and Environmental Scoping for Davis-Besse Nuclear Power Station License Renewal Application Review ML1029106182010-10-14014 October 2010 Documentation of Telephone Conversation Between Mr. David Lochbaum Regarding Follow-Up Questions Related to NRC Letter Dated July 28, 2010 (ML102040807) ML1028503032010-10-12012 October 2010 Acceptance of License Renewal Application, Davis-Besse Nuclear Power Station ML0935101922009-12-14014 December 2009 Completion of Davis-Besse Lessons Learned Task Force Recommendation 3.3.4(8) ML0825606772008-09-15015 September 2008 Presentation Disc ML0814207532008-05-20020 May 2008 Summary of Public Meeting with Firstenergy Nuclear Operating Company to Discuss the 2008 Davis-Besse End-of-Cycle Performance Assessment ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0723302222007-08-28028 August 2007 09/12/2007 Notice of Meeting with Firstenergy to Discuss the August 3, 2007 License Amendment Request for Conversion to Improved Technical Specifications for Davis-Besse, Unit 1 ML0722108432007-08-0707 August 2007 Request for Renewal of Deviation to the Reactor Oversight Process Action Matrix for Davis-Besse Nuclear Power Station ML0717103462007-06-21021 June 2007 Revised Notice of Meeting with Firstenergy to Discuss Response to Nrc'S 05/14/2007, Demand for Information Regarding Fenoc'S Re-analysis of the Timeline and Root Causes for the 2002 Davis-Besse Reactor Pressure Vessel Head Degradation Event ML0716202122007-06-13013 June 2007 Notice of Meeting with Firstenergy Regarding May 14, 2007 Demand for Information Davis-Besse ML0712803322007-05-18018 May 2007 April 2007 Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations (10 Cfr), Section 2.206 2023-05-04
[Table view] |
Text
April 25, 2002 MEMORANDUM TO: Anthony J. Mendiola, Chief, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Stephen Sands, Project Manager, Section 2 /RA by Douglas Pickett for/
Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY ON ROOT CAUSE ANALYSIS REPORT DATE & TIME: Tuesday, May 7, 2002 1:00 p.m. - 5:00 p.m.
LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Auditorium**
Rockville, Maryland 20852 PURPOSE: To provide the results of the root cause analysis of the degradation of the Davis-Besse Nuclear Power Station reactor pressure vessel head.
PARTICIPANTS:* NRC FirstEnergy B. Sheron H. Bergendahl J. Strosnider D. Eshelman T. Marsh S. Loehlein B. Bateman, et al. M. McLaughlin R. Fast, et al.
Docket No. 50-346 cc: See next page CONTACTS: Stephen Sands, 301-415-3154 Douglas Pickett, 301-415-1364
- Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to Commission Policy Statement on Staff Meetings Open to the Public: Final Policy Statement, 65 Federal Register 56964, 9/20/2000.
- Stakeholders wishing to participate via telephone may call the bridge at (888) 810-3138 and enter the passcode 1234 at the prompt. One hundred and fifty bridge lines will be available.
April 25, 2002 MEMORANDUM TO: Anthony J. Mendiola, Chief, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Stephen Sands, Project Manager, Section 2 /RA by Douglas Pickett for/
Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY ON ROOT CAUSE ANALYSIS REPORT DATE & TIME: Tuesday, May 7, 2002 1:00 p.m. - 5:00 p.m.
LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Auditorium**
Rockville, Maryland 20852 PURPOSE: To provide the results of the root cause analysis of the degradation of the Davis-Besse Nuclear Power Station reactor pressure vessel head.
PARTICIPANTS:* NRC FirstEnergy B. Sheron H. Bergendahl J. Strosnider D. Eshelman T. Marsh S. Loehlein B. Bateman, et al. M. McLaughlin R. Fast, et al.
Docket No. 50-346 cc: See next page CONTACTS: Stephen Sands, 301-415-3154 Douglas Pickett, 301-415-1364
- Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to Commission Policy Statement on Staff Meetings Open to the Public: Final Policy Statement, 65 Federal Register 56964, 9/20/2000.
- Stakeholders wishing to participate via telephone may call the bridge at (888) 810-3138 and enter the passcode 1234 at the prompt. One hundred and fifty bridge lines will be available.
ADAMS Accession Number: ML021150460 OFFICE PM:LPD3-2 LA:LPD3-2 BC:EMCB SC:LPD3-2 NAME DPickett for THarris* BBateman* AMendiola SSands DATE 04/25/02 04/25/02 04/25/02 04/25/02
- See previous concurrence OFFICIAL RECORD COPY
Distribution for Meeting Notice for May 7, 2002:
Hard Copy: E-mail:
PDIII-2 r/f PMNS OGC OPA ACRS JShea OWFN Receptionist HNeih TWFN Receptionist BSheron JStrosnider/RBarrett BBateman KWichman KKarwoski AHiser ALee JZimmerman JZwolinski/TMarsh GHolahan/SBlack MReinhart JChung SLong AMendiola SBajwa SSands SBloom WCullen EHackett BWetzel DPickett GGrant, R3 KJohnson THarris JStrasma
Davis-Besse Nuclear Power Station, Unit 1 cc:
Mr. Howard Bergendahl Dennis Clum Vice President-Nuclear, Davis-Besse Radiological Assistance Section Supervisor FirstEnergy Nuclear Operating Company Bureau of Radiation Protection Davis-Besse Nuclear Power Station Ohio Department of Health 5501 North State Route 2 P.O. Box 118 Oak Harbor, OH 43449-9760 Columbus, OH 43266-0118 Mary E. OReilly Carol OClaire, Chief, Radiological Branch FirstEnergy Corporation Ohio Emergency Management Agency 76 South Main St. 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-2206 Manager - Regulatory Affairs Zack A. Clayton First Energy Nuclear Operating Company DERR Davis-Besse Nuclear Power Station Ohio Environmental Protection Agency Oak Harbor, OH 43449-9760 P.O. Box 1049 Columbus, OH 43266-0149 Director Ohio Department of Commerce State of Ohio Division of Industrial Compliance Public Utilities Commission Bureau of Operations & Maintenance 180 East Broad Street 6606 Tussing Road Columbus, OH 43266-0573 P.O.Box 4009 Reynoldsburg, OH 43068-9009 Attorney General Department of Attorney Regional Administrator 30 East Broad Street U.S. Nuclear Regulatory Commission Columbus, OH 43216 801 Warrenville Road Lisle, IL 60523-4351 President, Board of County Commissioners of Ottawa County Michael A. Schoppman Port Clinton, OH 43252 Framatome ANP 1911 N. Ft. Myer Drive Rosslyn, VA 22209 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Plant Manager, Randel J. Fast FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760