Meeting with Firstenergy Nuclear Operating Company and Their Consultants Regarding Application to the Westinghouse Master Curve Methodology to Beaver Valley Power Station, Unit No. 1
ML020980437
Person / Time
Site: Beaver Valley
Issue date: 04/08/2002
From: Dan Collins
NRC/NRR/DLPM/LPD1
To: Richard Laufer
NRC/NRR/DLPM/LPD1
Collins D S, NRR/DLPM, 415-1427
References
Download: ML020980437 (6)


Text

April 8, 2002 MEMORANDUM TO: Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Daniel S. Collins, Project Manager, Section 1 /RA/

Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC) AND THEIR CONSULTANTS REGARDING APPLICATION OF THE WESTINGHOUSE MASTER CURVE METHODOLOGY TO BEAVER VALLEY POWER STATION, UNIT NO. 1 DATE & TIME: Tuesday, April 23, 2002 1:00 p.m. - 4:00 p.m.

LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room 9B4 Rockville, Maryland 20852-2738 PURPOSE: To discuss FENOCs application for approval to use the Westinghouse Master Curve Methodology for establishing pressure-temperature limits for Beaver Valley Power Station, Unit No. 1.

PARTICIPANTS:* See Attachment Docket No. 50-334 cc: See next page CONTACT: Daniel Collins, NRR, 301-415-1427

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to Commission Policy Statement on Staff Meetings Open to the Public: Final Policy Statement, 65 Federal Register 56964, September 20, 2000.

ML020980437 NRC-001 OFFICE PDI-1/PM PDI-2/LA PDI-1/SC NAME DCollins MOBrien RLaufer DATE 4/5/02 4/5/02 4/8/02 G:\PDI-1\Beaver1&2\Mtgnotice112701 PROSPECTIVE ATTENDEES FOR THE APRIL 23, 2002, MEETING APPLICATION OF THE WESTINGHOUSE MASTER CURVE METHODOLOGY TO BEAVER VALLEY POWER STATION, UNIT NO. 1 FirstEnergy Nuclear Operating Co. Nuclear Regulatory Commission William Kline Office of Nuclear Reactor Regulation Dennis Weakland Daniel Collins Brian Sepelak Matthew Mitchell Steve Sarver Stephanie Coffin Keith Wichman Barry Elliot Westinghouse Lambros Lois Randy Lott Charles Kim Nuclear Regulatory Commission Office of Nuclear Regulatory Research Mark Kirk ATI Consulting William Server Attachment

Date: April 8, 2002

SUBJECT:

FORTHCOMING MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC) AND THEIR CONSULTANTS REGARDING APPLICATION OF THE WESTINGHOUSE MASTER CURVE METHODOLOGY TO BEAVER VALLEY POWER STATION, UNIT NO. 1 Meeting Date: April 23, 2002 DISTRIBUTION:

PUBLIC PMNS Receptionist(OWFN and TWFN)

PDI-1 Reading RidsNrrAdptBSheron and KJohnson JZwolinski and LMarsh SRichards RLaufer DCollins MOBrien BPlatchek/JRogge, RGN1 DScrenci, OPA OGC ACRS MMitchell TBergman, EDO DMcCain cc: See next page

Beaver Valley Power Station, Units 1 and 2 Mary OReilly, Attorney Bureau of Radiation Protection FirstEnergy Nuclear Operating Company ATTN: Larry Ryan FirstEnergy Corporation P O Box 2063 76 South Main Street Harrisburg, PA 17120 Akron, OH 44308 Mayor of the Borough of FirstEnergy Nuclear Operating Company Shippingport Regulatory Affairs/Corrective Action P O Box 3 Section Shippingport, PA 15077 Larry R. Freeland, Manager Beaver Valley Power Station Regional Administrator, Region I Post Office Box 4, BV-A U.S. Nuclear Regulatory Commission Shippingport, PA 15077 475 Allendale Road King of Prussia, PA 19406 Commissioner James R. Lewis West Virginia Division of Labor Resident Inspector 749-B, Building No. 6 U.S. Nuclear Regulatory Commission Capitol Complex Post Office Box 298 Charleston, WV 25305 Shippingport, PA 15077 Director, Utilities Department FirstEnergy Nuclear Operating Company Public Utilities Commission Beaver Valley Power Station 180 East Broad Street ATTN: M. P. Pearson, Director Columbus, OH 43266-0573 Services and Projects (BV-IPAB)

Post Office Box 4 Director, Pennsylvania Emergency Shippingport, PA 15077 Management Agency 2605 Interstate Dr. FirstEnergy Nuclear Operating Company Harrisburg, PA 17110-9364 Beaver Valley Power Station Mr. B. F. Sepelak Ohio EPA-DERR Post Office Box 4, BV-A ATTN: Zack A. Clayton Shippingport, PA 15077 Post Office Box 1049 Columbus, OH 43266-0149 Mr. L. W. Myers Senior Vice President Dr. Judith Johnsrud FirstEnergy Nuclear Operating Company National Energy Committee Beaver Valley Power Station Sierra Club Post Office Box 4 433 Orlando Avenue Shippingport, PA 15077 State College, PA 16803 L. W. Pearce, Plant Manager (BV-IPAB)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077