ý Duke EPower A Duke Energy Company M. S. Tuckman Executive Vice President Nuclear Generation Duke Power 526 South Church St. EC07H Charlotte, NC 28202 P. O. Box 1006 EC07H Charlotte, NC 28201-1006 (704) 382-2200 OFFICE (704) 382-4360 FAX February 28, 2002 U. S. Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555-0001
Subject:
Duke Energy Corporation Oconee Nuclear Station, Units 1, 2, and 3 Docket Nos. 50-269, 50-270, 50-287 McGuire Nuclear Station, Units 1 and 2 Docket Nos. 50-369, 50-370 Catawba Nuclear Station, Units 1 and 2 Docket Nos. 50-413, 50-414 Response to NRC Regulatory Issue Summary 2001-21 Licensing Action Estimates for Operating Reactors As requested in NRC Regulatory Issue Summary 2001-21, the attached provides estimates of the number of licensing actions Duke Energy Corporation expects to submit in fiscal years 2002 and 2003.
The projected number of licensing action submittals are estimates which are subject to change and do not constitute Duke Energy Corporation commitments. Therefore, there are no commitments contained in this submittal. If you have any question, please contact L. B. Jones at (704) 382-4753.
-?V1 s-
.5 M. S. Tuckman Attachment (D o \\
U. S. Nuclear Regulatory Commission February 28, 2002 Page 2 xc:
L. A. Reyes, Regional Administrator U. S. Nuclear Regulatory Commission, Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, GA 30303 R. E. Martin (addressee only)
NRC Senior Project Manager (MNS)
U. S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555-0001 C. P. Patel (addressee only)
NRC Senior Project Manager (CNS)
U. S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555-0001 L. N. Olshan (addressee only)
NRC Senior Project Manager (ONS)
U. S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555-000 S. M. Shaeffer NRC Senior Resident Inspector McGuire Nuclear Station D. J. Roberts NRC Senior Resident Inspector Catawba Nuclear Station M. C. Shannon NRC Senior Resident Inspector Oconee Nuclear Station
U. S. Nuclear Regulatory Commission February 28, 2002 Page 3 bc:
L. E. Nicholson - ON03RC C. J. Thomas - MG01 RC G. D. Gilbert - CN01 RC NCMPA-1 SREC PMPA NCEMC ONS Master File - ON03DM (File OS 801.01)
MNS Master File - MGO1 DM CNS Master File - CN01 DM ELL
Topical Reports and License Amendment Requests Scheduled PLANT LICENSING ACTION ESTIMATED NAME DATE OF SUBMITTAL Topical Report Rev. 2 DPC-NE-2009 02/02 Topical Report CASMO-4 and SIMULATE 3 03/02.
Topical Report DPC-NE-2007 12/02 Topical Report Rev. 4 to DPC-NE-2005 02/03 CATAWBA TSTF359, Rev. 5 Increase flexibility in Mode Restraints 9/02 CATAWBA TS 3.7.15, 4.2, 4.3, 5.6.5 MOX Lead Assemblies 03/02.
CATAWBA Licensing basis chg. To resolve SG overfill OBD 04/02 CATAWBA TS 3.1.7 -TSTF234, Rev. 1 Revise Rod Position Indication TS to add new Condition for more than one DRPI per group inoperable.
05/02 Required action is to place the controls under manual control.
CATAWBA TS -5.5.13 Revise DIG fuel oil testing program. Additionally, delete the 10-yr. FD tank inspection requirements which will result in 05/02 longer intervals for inspection CATAWBA TS Change interval for ESFAS slave relay testing from 92 days to 18 mos.
05/02 CATAWBA TS - Require PR low setpoint flux trip to be operable below Mode 2 05/02 CATAWBA NC Elbow Tap Coefficients Change 06/02 CATAWBA TS - Delete requirements For H2 recombiners/skimmer fans 07/02 CATAWBA TS - Allow positive reactivity additions up to certain value 08/02 CATAWBA TS - VA & VE OBD Iodine pent. & response time 08/02 CATAWBA TS - Leave ECCS pumps racked in >15 min./Chg. LTOP to allow use of ND suction reliefs/Revise NCS HU/CD limit curves 09/02 CATAWBA TS - Revise Spent fuel storage requirements 9/02 CATAWBA TS - Ice Condenser improvements (asymmetric loading) 10/02 CATAWBA TS - Ice Condenser door TS SRs 11/02 CATAWBA TS TSTF30 Increased LCO time for inoperable containment isolation valves 11/02 CATAWBA TSTF426 Risk Informed Initiative #6-Increase AOTs to prevent immediate entry into TS 3.0.3 12/02 CATAWBA TS - Performance based IST 02/03 CATAWBA Power Uprate 03/03 CATAWBA Removal of License Condition for dose equiv. iodine 03/03 CATAWBA SR 3.0.3, TSTF358, R5 Relaxation of missed surveillances 04/02 CATAWBA TS - ILRT Time Extension 04/02 MCGUIRE TS SR 3.4.11 PORV block valve SR 03/03 MCGUIRE Revise TS 5.3.1, Unit Staff Qualifications. Delete sentence that requires lic Oper and SROs to meet or exceed the min. qual of the 10/03.
supplemental requirements specified in Section A and C of Enc 1 of the 3/28/80 NRC letter to all licensees.
MCGUIRE TSTF359, Rev. 5 Increase flexibility in Mode Restraints 9/02 MCGUIRE TS 3.7.15, 4.2, 4.3, 5.6.5 MOX Lead Assemblies 03/02.
MCGUIRE TS 3.1.7 -TSTF234, Rev. 1 Revise Rod Position Indication TS to add new Condition for more than one DRPI per group inoperable.
05/02 Required action is to place the controls under manual control.
Page 1 of 2 02/28/02
MCGUIRE TS -5.5.13 Revise D/G fuel oil testing program. Additionally, delete the 10-yr. FD tank inspection requirements which will result in 05/02 longer intervals for inspection MCGUIRE TS - Allow positive reactivity additions up to certain value 08/02 MCGUIRE TS - Ice Condenser improvements (asymmetric loading) 10/02 MCGUIRE TS - Ice Condenser door TS SRs 11/02 MCGUIRE TS TSTF30 Increased LCO time for inoperable containment isolation valves 11/02 MCGUIRE TSTF426 Risk Informed Initiative #6-Increase AOTs to prevent immediate entry into TS 3.0.3 12/02 MCGUIRE Power Uprate 03/03 MCGUIRE SR 3.0.3, TSTF358, R5 Relaxation of missed surveillances 04/02 MCGUIRE TS 3.7.11 Aux. Bldg. Filtered Exhaust. Add a note to allow intermittent opening of doors w/o entering CONDITION if comp.
05/03 measures are in place.
MCGUIRE TS 3.3.1, 3.3.2 Eliminate response time testing on selected sensors 03/02.
MCGUIRE TS -3.7.15 Address problem with WEST 304 SS Fuel Assemblies 03/02.
MCGUIRE FOL - Submit LAR to permit process of straightening bent fuel pin in SFP 04/02 MCGUIRE TS 3.3.2, 3.3.5 ESFAS Function 5 and related changes 04/02 MCGUIRE TS - ILRT Time Extension 04/02 MCGUIRE TS 3.6.14 Divider Barrier Integrity - Revise TS to allow opening of PZR hatch plug for at least 6 hrs.
12/02 MCGUIRE TS - Allow the containment airlock doors open and penetration flow paths with direct access to the outside atmosphere to be 03/03 unisolated during fuel movement and core alterations.
MCGUIRE TS - Revise wording on SR 3.6.16.1 to indicate only one door for each access opening 03/03 MCGUIRE TS 3.3.2, 3.4.3, 3.4.12 Steam Line Isolation on Steam Line Pressure Negative Rate - High may be blocked below P-11 when Steam 05/03 Line Pressure - Low is not blocked. Update H/U and C/D curves for the RCS to a max of 34 EFPY. Update LTOP limits OCONEE TSTF359, Rev. 5 Increase flexibility in Mode Restraints 9/02 OCONEE TSTF426 Risk Informed Initiative #6-Increase AOTs to prevent immediate entry into TS 3.0.3 12/02 OCONEE SR 3.0.3, TSTF358, R5 Relaxation of missed surveillances 04/02 OCONEE TS 3.05.03, 3.05.02 Increase AOT from one train of LPI inop. from 72 hrs. to 7 days 03/02.
OCONEE Submittal regarding the impact of Mark-B1 I fuel 03/02.
OCONEE TS - Revise Channel B of Turbine Stop Valves to reflect 1 sec. closure 04/02 OCONEE TS 3.08.03 Add note to provide add'l time frame for performance of equalizing charge prior to battery performance test -generic 04/02 change OCONEE TS 3.03.01 Revise SR 3.3.1.3 to clarify imbalance reqmts.
05/02 OCONEE TS 3.04.12 - Allow SR 3.4.12.5 to be performed within 31 days prior to decreasing RCS temp. to < 325F - generic change 05/02 OCONEE TS -3.08.1,3.03.27 Relocate Zone Overlap Circuitry to section 3.3 06/02 OCONEE TS SG Replacement - TS changes for ONS 06/02 OCONEE TS - Delete "RB Essential Isolation" from 3.03.06.b; Other Editorial changes will also be included 07/02 OCONEE TS - 3.05.03 9/02 3.04.14 Reflect LPI Crossover Mod.
OCONEE TS 3.07.06 Revise inventory requirements for UST & Hotwell 9/02 OCONEE RPS Digital Upgrade Mod.
03/03 Page 2 of 2 02/28/02