January 2002 Monthly Operating Report for Surry Power Station, Units 1 and 2
ML020580183
Person / Time
Site: Surry  Dominion icon.png
Issue date: 02/06/2002
From: Blount R
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
02-071
Download: ML020580183 (19)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 February 06, 2002 U. S. Nuclear Regulatory Commission Serial No.02-071 Attention: Document Control Desk SPS Lic/JSA RO Washington, D.C. 20555-0001 Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT The Monthly Operating Report for Surry Power Station Units 1 and 2 for the month of January 2002 is provided in the attachment.

If you have any questions or require additional information, please contact us.

Very truly yours, Richard H. Blount, Site Vice President Surry Power Station Attachment Commitments made by this letter: None cc: United States Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23 T85 Atlanta, Georgia 30303-8931 Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station 1-11ý V'/

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION MONTHLY OPERATING REPORT REPORT No. 02-01 Approved:

Site Vice President D e-

Surry Monthly Operating Report No. 02-01 Page 2 of 18 TABLE OF CONTENTS Section Page Operating Data Report - Unit No. 1 ........................................................................................................................... 3 Operating Data Report - Unit No. 2 ........................................................................................................................... 4 Unit Shutdowns and Power Reductions - Unit No. 1 ............................................................................................ 5 Unit Shutdowns and Power Reductions - Unit No. 2 ............................................................................................. 6 Average Daily Unit Power Level - Unit No. 1 ...................................................................................................... 7 Average Daily Unit Power Level - Unit No. 2 ........................................................................................................ 8 Summary of Operating Experience - Unit Nos. 1 and 2 ......................................................................................... 9 Facility Changes That Did Not Require NRC Approval ......................................................................................... 10 Procedure or Method of Operation Changes That Did Not Require NRC Approval ........................................... 11 Tests and Experiments That Did Not Require NRC Approval .............................................................................. 12 Chemistry Report ..................................................................................................................................................... 13 Fuel Handling - Unit Nos. 1 and 2 ............................................................................................................................ 14 Description of Periodic Test(s) Which Were Not Completed Within the Time Limits Specified in Technical Specifications ...................................................................................................................... 18

Surry Monthly Operating Report No. 02-01 Page 3 of 18 OPERATING DATA REPORT Docket No.: 50-280 Date: 02/04/02 Completed By: R. Stief Telephone: (757) 365-2486

1. U nit Nam e : ............................................................ Surry Unit 1
2. Reporting Period: .................................................. January 2002
3. Licensed Thermal Power (MW t): .......................... 2546
4. Nameplate Rating (Gross MW e): .......................... 847.5
5. Design Electrical Rating (Net MWe): .................... 788
6. Maximum Dependable Capacity (Gross MWe): .... 842
7. Maximum Dependable Capacity (Net MW e): ........ 810
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-To-Date Cumulative

11. Hours in Reporting Period 744.0 744.0 255192.0
12. Hours Reactor Was Critical 744.0 744.0 186505.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 3774.5
14. Hours Generator On-Line 744.0 744.0 183846.2
15. Unit Reserve Shutdown Hours 0.0 0.0 3736.2
16. Gross Thermal Energy Generated (MWH) 1893551.9 1893551.9 437201029.8
17. Gross Electrical Energy Generated (MWH) 635091.0 635091.0 143715194.0
18. Net Electrical Energy Generated (MWH) 613399.0 613399.0 137206260.0
19. Unit Service Factor 100.0% 100.0% 72.0%
20. Unit Availability Factor 100.0% 100.0% 73.5%
21. Unit Capacity Factor (Using MDC Net) 101.8% 101.8% 68.8%
22. Unit Capacity Factor (Using DER Net) 104.6% 104.6% 68.2%
23. Unit Forced Outage Rate 0.0% 0.0% 12.7%
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 20001

25. If Shut Down at End of Report Period, Estimated Date of Start-up: Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26. Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

Surry Monthly Operating Report No. 02-01 Page 4 of 18 OPERATING DATA REPORT Docket No.: 50-281 Date: 02/04/02 Completed By: R. Stief Telephone: (757) 365-2486

1. U nit Na m e : ............................................................ Surry Unit 2
2. Reporting Period: .................................................. January 2002
3. Licensed Thermal Power (MWt): .......................... 2546
4. Nameplate Rating (Gross MWe): .......................... 847.5
5. Design Electrical Rating (Net MWe): .................... 788
6. Maximum Dependable Capacity (Gross MWe): .... 847
7. Maximum Dependable Capacity (Net MWe): ........ 815
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-To-Date Cumulative

11. Hours in Reporting Period 744.0 744.0 252073.0
12. Hours Reactor Was Critical 744.0 744.0 184562.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 328.1
14. Hours Generator On-Line 744.0 744.0 182360.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1894040.7 1894040.7 434918944.9
17. Gross Electrical Energy Generated (MWH) 637175.0 637175.0 143014182.0
18. Net Electrical Energy Generated (MWH) 615322.0 615322.0 136572372.0
19. Unit Service Factor 100.0% 100.0% 72.3%
20. Unit Availability Factor 100.0% 100.0% 72.3%
21. Unit Capacity Factor (Using MDC Net) 101.5% 101.5% 69.0%
22. Unit Capacity Factor (Using DER Net) 105.0% 105.0% 68.8%
23. Unit Forced Outage Rate 0.0% 0.0% 10.1%
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

April 2002 Type and duration of scheduled shutdowns are no longer provided.

[

Reference:

Letter S/N 00-069, dated February 7, 2000]

25. If Shut Down at End of Report Period, Estimated Date of Start-up: Estimated start-up dates are no longer provided. [

Reference:

Letter S/N 00-069, dated February 7, 2000]

26. Unit In Test Status (Prior to Commercial Operation):

FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

Surry Monthly Operating Report No. 02-01 Page 5 of 18 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: January 2002 Docket No.: 50-280 Unit Name: Surry Unit 1 Date: 02/04/02 Completed by: R. Stief Telephone: (757) 365-2486 None during the Reporting Period (1) (2) (3)

F: Forced REASON: METHOD:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & Licensing Examination F - Administrative G - Operational Error (Explain)

H Other (Explain)

(4) (5)

Exhibit G - Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source for Licensee Event Report (LER) File (NUREG 0161)

Surry Monthly Operating Report No. 02-01 Page 6 of 18 UNIT SHUTDOWN AND POWER REDUCTION (EQUAL To OR GREATER THAN 20%)

REPORT MONTH: January 2002 Docket No.: 50-281 Unit Name: Surry Unit 2 Date: 02/04/02 Completed by: R. Stief Telephone: (757) 365-2486 None during the Reporting Period (1) (2) (3)

F: Forced REASON: METHOD:

S: Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Other (Explain)

E - Operator Training & Licensing Examination F - Administrative G - Operational Error (Explain)

H Other (Explain)

(4) (5)

Exhibit G - Instructions for Preparation of Data Entry Sheets Exhibit 1 - Same Source for Licensee Event Report (LER) File (NUREG 0161)

Surry Monthly Operating Report No. 02-01 Page 7 of 18 AVERAGE DAILY UNIT POWER LEVEL Docket No.: 50-280 Unit Name: Surry Unit 1 Date: 02/04/02 Completed by: R. Stief Telephone: (757) 365-2486 MONTH: January 2002 Average Daily Power Level Average Daily Power Level Day (MWe - Net) Day (MWe - Net) 1 825 17 826 2 827 18 826 3 825 19 824 4 825 20 825 5 825 21 824 6 825 22 824 7 823 23 824 8 824 24 825 9 825 25 825 10 825 26 824 11 825 27 825 12 825 28 824 13 825 29 824 14 823 30 824 15 824 31 824 16 824 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 02-01 Page 8 of 18 AVERAGE DAILY UNIT POWER LEVEL Docket No.: 50-281 Unit Name: Surry Unit 2 Date: 02/04/02 Completed by: R. Stief Telephone: (757) 365-2486 MONTH: January 2002 Average Daily Power Level Average Daily Power Level (MWe - Net) Day (MWe - Net)

Day 1 827 17 828 2 827 18 828 3 826 19 828 4 827 20 827 5 828 21 827 6 827 22 828 7 827 23 828 8 826 24 827 9 826 25 827 10 825 26 827 11 826 27 828 12 825 28 828 13 826 29 828 14 827 30 829 15 828 31 828 16 826 INSTRUCTIONS On this format, list the average daily unit power level in MWe - Net for each day in the reporting month. Compute to the nearest whole megawatt.

Surry Monthly Operating Report No. 02-01 Page 9 of 18

SUMMARY

OF OPERATING EXPERIENCE MONTHIYEAR: January 2002 The following chronological sequence by unit is a summary of operating experiences for this month that required load reductions or resulted in significant non-load related incidents.

UNIT ONE:

01/01/02 0000 Unit started the month at 100% / 854 MWe.

01/31/02 2400 Unit finished the month at 100% / 854 MWe.

UNIT Two:

01/01/02 0000 Unit started the month at 100% / 855 MWe.

01/31/02 2400 Unit finished the month at 100% / 855 MWe.

Surry Monthly Operating Report No. 02-01 Page 10 of 18 FACILITY CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTH/YEAR: January 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-01 Page 11 of 18 PROCEDURE OR METHOD OF OPERATION CHANGES THAT DID NOT REQUIRE NRC APPROVAL MONTHIYEAR: January 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-01 Page 12 of 18 TESTS AND EXPERIMENTS THAT DID NOT REQUIRE NRC APPROVAL MONTHIYEAR: January 2002 None during the Reporting Period

Surry Monthly Operating Report No. 02-01 Page 13 of 18 CHEMISTRY REPORT MONTH/YEAR: January 2002 Unit No. 1 Unit No. 2 Primary Coolant Analysis Max. Min. Avg. Max. Min. Avg.

Gross Radioactivity, p.Ci/ml 3.36E-1 2.37E-1 2.79E-1 3.24E-1 2.10E-1 2.64E-1 Suspended Solids, ppm - -

Gross Tritium, pCi/ml 5.87E-1 3.55E-1 4.72E-1 1.51 E-1 1.39E-1 1.47E-1 1131, AtCi/mI 1.74E-4 5.51E-5 1.22E-4 1.97E-4 8.11E-5 1.15E-4 1131/1133 0.12 0.04 0.09 0.12 0.05 0.07 Hydrogen, cc/kg 39.6 35.4 37.7 43 36.7 39.9 Lithium, ppm 2.48 2.23 2.38 2.03 1.54 1.79 Boron - 10, ppm* 269 258 263 56.6 37.6 48.5 Oxygen, (DO), ppm _0.005 _0.005 < 0.005 < 0.005 < 0.005 _ 0.005 Chloride, ppm 0.022 0.005 0.008 0.002 0.001 0.001 pH @ 25 degree Celsius 6.5 6.29 6.39 7.38 7.2 7.29

None

Surry Monthly Operating Report No. 02-01 Page 14 of 18 FUEL HANDLING UNITS 1 & 2 MONTHIYEAR: January 2002 New Fuel Number of New or Spent Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received per Shipment Number Number Enrichment Cask Activity Unit 2 Batch 20 Shipment #1 01/03/02 12 01R LM1CNM 4.1011 571.00 GBq 04R LM1CNQ 4.0923 1OR LMICNW 4.0992 16R LMICP2 4.1074 22R LM1CP8 4.1010 33R LM1CPK 4.1077 38R LMICPQ 4.2437 39R LM1CPR 4.2486 41R LM1CPT 4.2440 45R LM1CPX 4.2459 53R LM1CQ5 4.2675 59R LM1CQB 4.2500 Unit 2 Batch 20 01/08/02 12 02R LM1CNN 4.1000 568.69 GBq Shipment #2 06R LM1CNS 4.1007 13R LM1CNZ 4.1018 17R LM1CP3 4.0986 19R LM1CP5 4.1089 20R LM1CP6 4.1007

Surry Monthly Operating Report No. 02-01 Page 15 of 18 FUEL HANDLING UNITS 1 & 2 MONTH/YEAR: January 2002 New Fuel Number of New or Spent Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received per Shipment Number Number Enrichment Cask Activity 21 R LM1CP7 4.0985 36R LM1CPN 4.0999 48R LM1CQ0 4.2554 52R LM1CQ4 4.2646 54R LM1 CQ6 4.2747 56R LM1CQ8 4.2432 Unit 2 Batch 20 01/09/02 12 05R LMICNR 4.1083 569.06 GBq Shipment #3 11R LM1CNX 4.1013 18R LM1CP4 4.1075 23R LM1CP9 4.1080 27R LM1CPD 4.1031 31 R LM1CPH 4.1076 32R LM1CPJ 4.1011 34R LM1CPL 4.1102 42R LM1 CPU 4.2453 43R LMICPV 4.2466 49R LM1CQ1 4.2516 60R LM1CQC 4.2564

Surry Monthly Operating Report No. 02-01 Page 16 of 18 FUEL HANDLING UNITS I & 2 MONTHIYEAR: January 2002 New Fuel Number of New or Spent Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received per Shipment Number Number Enrichment Cask Activity Unit 2 Batch 20 Shipment #4 01/10/02 12 07R LM1CNT 4.1082 570.17 GBq 08R LM1CNU 4.1003 12R LMICNY 4.1023 24R LM1 CPA 4.0989 25R LM1CPB 4.1067 30R LMICPG 4.1025 35R LM1CPM 4.1005 37R LM1CPP 4.2445 44R LM1CPW 4.2446 47R LM1CPZ 4.2486 51R LM1CQ3 4.2413 55R LM1CQ7 4.2517 Unit 2 Batch 20 01/11/02 12 03R LM1CNP 4.0935 570.17 GBq Shipment #5 09R LM1CNV 4.0988 14R LM1CP0 4.1015 15R LMICP1 4.0986 26R LM1CPC 4.1085 28R LM1CPE 4.1029

Surry Monthly Operating Report No. 02-01 Page 17 of 18 FUEL HANDLING UNITS 1 & 2 MONTH/YEAR: January 2002 New Fuel Number of New or Spent Shipment or Date Stored or Assemblies Assembly ANSI Initial Fuel Shipping Cask No. Received ner Shioment Number Number Enrichment Cask Activity Cask No Der Shipment 29R LM1CPF 4.1004 40R LM1CPS 4.2477 46R LM1CPY 4.2521 50R LM1CQ2 4.2482 57R LM1CQ9 4.2445 58R LM1CQA 4.2465

Surry Monthly Operating Report No. 02-01 Page 18 of 18 DESCRIPTION OF PERIODIC TEST(S) WHICH WERE NOT COMPLETED WITHIN THE TIME LIMITS SPECIFIED IN TECHNICAL SPECIFICATIONS MONTHIYEAR: January 2002 None during the Reporting Period