SAFEGUARDS INFORMATION February 25, 2002 Michael B. Sellman President and CEO Point Beach Nuclear Plant, Units 1 & 2 Nuclear Management Company, LLC 700 First Street Hudson, WI 54016
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - POINT BEACH NUCLEAR PLANT, UNITS 1 & 2
Dear Mr. Sellman:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
M Sellman The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
Point Beach Nuclear Plant, Units 1 and 2 cc:
Mr. John H. ONeill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW Washington, DC 20037-1128 Mr. Richard R. Grigg President and Chief Operating Officer Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Site Licensing Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Ms. Sarah Jenkins Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Mr. Roy A. Anderson Executive Vice President and Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Mr. Mark Reddemann Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241
M Sellman February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD3-1 DSpaulding RBouling SBajwa WReckley RidsRgn3MailCenter Accession No. ML020490066 (Package)
Accession No. ML020 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY