December 2001 Monthly Operating Report for Oyster Creek
ML020440393
Person / Time
Site: Oyster Creek
Issue date: 01/09/2002
From: Degregorio R
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2130-02-20001, GL-97-002
Download: ML020440393 (3)


Text

AmerGen An Exelon/British Energy Company AmerGen Energy Company, LLC Oyster Creek US Route 9 South P.O. Box 388 Forked River, NJ 08731-0388 January 9, 2002 2130-02-20001 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington DC 20555

Dear Sir:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Monthly Operating Report - December 2001 Enclosed is the December 2001 Monthly Operating Report for the Oyster Creek Generating Station. The content and format of information submitted in this report is in accordance with the guidance provided by Generic Letter 97-02.

If any additional information or assistance is required, please contact Mr. John Rogers of my staff at 609.971.4893.

Very truly yours, Ron J. DeGregorio, Vice President Oyster Creek Generating Station Enclosure cc:

Administrator, RegionI NRC Senior Project Manager Senior Resident Inspector

APPENDIX A Operating Data Report Docket No:

Date:

Completed By:

Telephone:

50-219 1/07/02 Roger B. Gayley (609) 971-4406 Reporting Period:

December 2001 Design values have no "Year to Date" or "Cumulative" significance.

YEAR TO MONTH DATE CUMULATIVE DESIGN ELECTRICAL RATING (MWe NET).

The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.

650

2.

MAXIMUM DEPENDABLE CAPACITY (MWe NET).

The gross electrical output as measured at the output terminals of the turbine generator during the most restrictive seasonal 619 conditions minus the normal station service loads.

3.

NUMBER OF HOURS REACTOR WAS CRITICAL.

The total number of hours during the gross hours of the reporting period that the reactor was critical.

744 8546.8 201,686.7

4.

HOURS GENERATOR ON LINE.

(Service Hours) The total number of hours during the gross hours 744 84 9 7.8 197,511.7 of the reporting period that the unit operated with the breakers closed to the station bus. The sum of the hours that the generator was on line plus the total outage hours should equal the gross hours in the reporting period.

5.

UNIT RESERVE SHUTDOWN HOURS.

The total number of hours during the gross hours of the reporting 0

0 918.2 period that the unit was removed from service for economic or similar reasons but was available for operation.

6.

NET ELECTRICAL ENERGY (MWH).

The gross electrical output of the unit measured at the output terminals ofthe turbine generator minus the normal station service 470,154 5,226,368 112,107,157 loads during the gross hours of the reporting period, expressed in megawatt hours. Negative quantities should not be used.

Appendix B Unit Shutdowns Docket No:

Date:

Completed By:

Telephone:

50-219 1/07/02 Roger B. Gayley (609) 971-4406 Reporting Period:

December 2001 I

2 F Forced Reason:

Method:

S Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Other (Explain)

E-Operator Training & Licensing Examination F-Administrative G-Operational Error (Explain)

H-Other (Explain)

Summary:

During December, Oyster Creek generated 470,154 net MW electric, which was 102.1% of its MDC rating.

Cause & Corrective Action to Prevent Recurrence The reactor was not shutdown during the report period.