Text
Stephen A. Byrne Senior Vice President, Nuclear Operations 803.345.4622 January 11, 2002 A SCANA COMPANY Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management Gentlemen:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 DECEMBER MONTHLY OPERATING REPORT Enclosed is the December 2001 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1. This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.
If there are any questions, please call me at your convenience.
Very truly yours, Stephen A. Byrne SAB/nkk Attachment c:
G. H. Halnon T. G. Eppink (w/o Attachment)
R. J. White L. A. Reyes R. R. Assa T. D. Gatlin NRC Resident Inspector K. M. Sutton W. R. Higgins Paulette Ledbetter INPO Records Center J&H Marsh & McLennan William G. Wendland (ANI)
Pat Haught (Westinghouse)
RTS (0-L-99-0350-1)
File (818.03-1, RR 4100)
DMS (RC-02-0005)
SCE&G I Virgil C. Summer Nuclear Station
- P. 0. Box 88
- Jenkinsville, South Carolina 29065
- T (803) 345.5209
- www.scono.com
Director, Office of Resource Management December Monthly Operating Report RC-02-005 Page 1 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE DECEMBER 2001 DAY AVERAGE DAILY POWER LEVEL DAY (MWe-Net)
- 1.
978
- 17.
- 2.
979
- 18.
- 3.
978
- 19.
- 4.
978
- 20.
- 5.
978
- 21.
- 6.
978
- 22.
- 7.
975
- 23.
- 8.
965
- 24.
- 9.
968
- 25.
- 10.
977
- 26.
- 11.
977
- 27.
- 12.
977
- 28.
- 13.
978
- 29.
- 14.
978
- 30.
- 15.
978
- 31.
- 16.
977 50/395 V. C. SUMMER I 01/09/2002 W. H. BELL (803) 345-4389 AVERAGE DAILY POWER LEVEL (MWe-Net) 979 979 978 979 979 980 980 980 980 980 980 980 980 980 979
Director, Office of Resource Management December Monthly Operating Report RC-02-005 Page 2 ATTACHMENT II OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I 01/09/2002 W. H. BELL (803) 345-4389 OPERATING STATUS
- 1.
Reporting Period:
December 2001 Gross Hours in Reporting Period:
744
- 2.
Currently Authorized Power Level (MWt):
2900 Max. Depend. Capacity (MWe-Net):
966 Design Electrical Rating (MWe-Net):
972.7
- 3.
Power Level to Which Restricted (If Any) (MWe-Net):
N/A
- 4.
Reasons for Restrictions:
N/A THIS MONTH YR TO DATE CUMULATIVE Number of Hours Reactor Critical Reactor Reserve Shutdown Hours Hours Generator on Line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)
Gross Electrical Energy (MWH)
Net Electrical Energy Generated (MWH)
Reactor Service Factor Reactor Availability Factor Unit Service Factor Unit Availability Factor Unit Capacity Factor (Using MDC)
Unit Capacity Factor (Design MWe)
Unit Forced Outage Rate 744.0 0.0 744.0 0.0 2153770 756150 727476 100.0 100.0 100.0 100.0 101.2 100.5 0.0 7295.4 0.0 7096.9 0.0 20182210 7039330 6757528 83.3 83.3 81.0 81.0 79.9 79.3 0.9
- 19.
Shutdowns Scheduled Over Next 6 Months (Type, Date & Duration of Each):
- 20.
If Shut Down at End of Report Period, Estimated Date of Startup:
- 21.
Units in Test Status (Prior to Commercial Operation):
131449.3 0.0 129624.4 0.0 348886408 117548749 112271181 83.3 83.3 82.1 82.1 78.7 77.5 3.3 N/A N/A N/A
- 5.
- 6.
- 7.
- 8.
- 9.
- 10.
- 11.
- 12.
- 13.
- 14.
- 15.
- 16.
- 17.
18.
Director, Office of Resource Management December Monthly Operating Report RC-02-005 Page 3 ATTACHMENT III UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I 01/09/2002 W. H. BELL (803) 345-4389 DECEMBER 2001 NO.
DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS N/A 1.0 REASON A:
Equipment Failure B:
Maintenance or Test C:
Refueling D:
Regulatory Restriction E:
Operator Training and License Examination F:
Administrative G:
Operational Error H:
Other (Explain) 2.0 METHOD 1 :
Manual 2:
Manual Scram 3:
Continuation (Use initial Date) 5:
Power Reduction (Duration 0.0) 9:
Other (Explain)
Director, Office of Resource Management December Monthly Operating Report RC-02-005 Page 4 ATTACHMENT IV NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50/395 UNIT V. C. SUMMER I DATE 01/09/2002 COMPLETED BY W. H. BELL TELEPHONE (803) 345-4389 DECEMBER 2001 At 22:33 on December 7 th a reduction to 91% reactor power began to support planned main turbine control valve testing. 91 % power was reached at 23:25. Valve testing was completed and 100% power was restored at 04:37 on December 8 th At 09:25 on December 9 th, a reduction to 98% reactor power began to support repairs to the No. 1 B feedwater heater level transmitter probe. Problems with the Magnetrol level transmitter probe on ILT03773A required the replacement of the probe. 98% power was reached at 09:36.
Transmitter probe replacement was completed and 100% power was restored at 23:22. The plant operated at 100% power at all other times during the month.