MONTHYEARML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21085A8652021-04-0808 April 2021 Summary of March 17, 2021, Category 1 Public Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (EPID L-2020-LLA-0164) Non ML20325A3212020-12-17017 December 2020 Summary of November 4, 2020, Nonproprietary - Category 1 Meeting with Entergy Operations, Inc. Regarding LAR to Install Digital Upgrade in Accordance with Digital I&C Interim Staff Guidance No. 06, Rev. 2, Licensing Processes (Redacted) ML20337A1572020-12-0808 December 2020 Summary of Teleconference Meeting with Entergy Operations, Inc. to Discuss the Forthcoming Supplemental Response Concerning Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 ML20150A4372020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc., Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Waterford 3 ISFSI ML20149K5412020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One I ML20150A4212020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Nuclear Company, LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf ISFSI ML20057G5182020-02-27027 February 2020 Notice of Enforcement Conference with Waterford 3 Steam Generating Station to Discuss Apparent Violations of NRC Requirements Related to Waterford 3 Steam Electric Station'S Radiation Safety and Security Program ML19204A2972019-07-31031 July 2019 Memo to Management Review Board Arkansas Follow-up FY2019 Proposed Final Report ML19204A1482019-07-15015 July 2019 FEMA Region VI Memo 07-15-19: Hurricane Barry Preliminary Capabilities Assessment ML18257A0382018-11-23023 November 2018 Communications Plan Regarding the Renewal of the Waterford Steam Electric Station, Unit 3, Renewed Operating License ML18303A2692018-10-30030 October 2018 License Renewal Application ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers IR 05000382/20170112017-12-20020 December 2017 NRC Special Inspection Report 05000382/2017011 ML17153A0012017-06-0606 June 2017 Staff Observations of Testing for Generic Safety Issue 191 During a May 10 to May 11, 2017, Trip to the Alden Test Facility for Control Components Inc. Strainer Tests ML16323A2292017-01-24024 January 2017 08/23-25/2016 Summary of Teleconference Meetings with Entergy Operations Inc., Concerning RAI Set 1 Pertaining to the Waterford Steam Electric Station, Unit 3 License Renewal Application ML16351A0452016-12-19019 December 2016 Requests for Additional Information for the Review of the Waterford Steam Electric Station, Unit 3, License Renewal Application - Set 11 ML16158A2232016-06-0202 June 2016 Submittal of Revision 302 to Emergency Plan Implementing Procedure EP-002-140, Reentry ML16145A3392016-05-24024 May 2016 NRC Supplemental Inspection Procedure 95003 (Report - 05000313/2016007, and 05000368/2016007) List of Documents Reviewed ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16076A2212016-03-16016 March 2016 NRC Supplemental Inspection Procedure 95003 (Report 05000313/2016007, 05000368/2016007) Request for Information ML16061A3622016-03-0101 March 2016 OEDO-15-00641 DPO-2015-001 on the Significance Determination Process Evaluation for a Finding at Arkansas Nuclear One Involving the March 2013, Unit 1 Stator Drop Event, Redacted-Public ML15292A2412015-10-21021 October 2015 October 28, 2015, Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Arkansas Nuclear One, Units 1 and 2 ML15218A6042015-08-0606 August 2015 Inspection Procedure 95003 Communication Team Charter ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML14356A1722014-12-22022 December 2014 Summary of Site Audit to Support the Review of a License Amendment Request for Arkansas Nuclear One, Unit 2 to Transition to the National Fire Protection Association (NFPA) Standard 805 Fire Protection Licensing Basis ML14351A2602014-12-19019 December 2014 Memo C K Bladey Re Notice of Issuance of Exemption from Holtec Intl CoC No. 1014 Fuel Specification and Loading Conditions at Arkansas Nuclear One ISFSI ML14356A5612014-12-17017 December 2014 Third-Party Assessment of Safety Culture ML14345B0652014-12-11011 December 2014 Memo C Bladey Re Federal Register Notice of Issuance of Environmental Assessment and Finding of No Significant Impact ANO Units 1 & 2 ISFSI 72-12 and 72-1014 ML14213A4272014-09-12012 September 2014 Summary of July 16, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers Nuclear Regulatory Commission, and Entergy Operations Inc. to Discuss Flooding Analysis Associated with Arkansas Nuclear One, Units 1 and 2 ML14132A1162014-09-0505 September 2014 Review of Final Safety Analysis Report, Revision 307, Covers Period from 4/13/2012 Through 6/17/2013 ML14184B2432014-07-10010 July 2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Arkansas Nuclear One, Units 1 and 2 ML14163A0502014-06-13013 June 2014 Summary of Conference Call with Arkansas Nuclear One, Unit 2, Regarding the Spring Steam Generator Inspections ML14023A2792014-01-23023 January 2014 Notice of Meeting with Entergy Operations, Inc., to Discuss Waterford Unit 3 License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition ML13269A2082013-12-12012 December 2013 Cover Memo from B. Caldwell to M. Markley RAI for Arkansas Nuclear One (ANO) Revision 15 Security Plan Review ML13255A4872013-09-10010 September 2013 Request for Additional Information to Entergy Operations, Arkansas Nuclear One-Units 1 and 2, Regarding NTTF Recommendation 9.3 Phase 1 Staffing Assessment Submittal ML12319A1222012-11-14014 November 2012 Notice of Forthcoming Meeting with Entergy Operations, Inc. to Discuss Resubmittal of License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 ML12324A4222012-11-14014 November 2012 Meeting Notice with Entergy Operations, Inc. to Discuss the Status of the Revised Application for Arkansas Nuclear One, Unit 2 to Transition to National Fire Protection Association (NFPA) Standard 805 ML12271A2482012-09-27027 September 2012 10/9/2012 Notice of Forthcoming Meeting with Entergy Operations, Inc. to Discuss Resubmittal of License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 2023-03-21
[Table view] |
Text
January 17, 2002 MEMORANDUM TO: File FROM: N. Kalyanam, Project Manager /RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
ENTERGY OPERATIONS INC., PRESENTATION OF THE MNSA 2 CLAMPS FOR WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3), AND ARKANSAS NUCLEAR ONE, UNIT 2 (ANO-2)
Entergy Operations Inc., the licensee for Waterford 3 and ANO-2, telephoned the staff on January 14, 2002, to indicate that they, along with manufacturers of MNSA clamps, would make a presentation on the new MNSA 2 clamps on January 31, 2002.
The original MNSA clamps, approved for use on Waterford 3 and a few other Combustion Engineering plants, provide a temporary fix if leakage from the Reactor Coolant System is observed during an outage. Use of the original MNSA clamps is restricted to certain shapes.
The manufacturers of MNSA clamps have now developed MNSA 2 clamps, which are a "new and improved version" of the original model clamps, can be used on "non-symmetrical" shapes and have additional features, such as compensation for seal shrinkage.
Docket Nos. 50-382 and 50-368
January 17, 2002 MEMORANDUM TO: File FROM: N. Kalyanam, Project Manager /RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
ENTERGY OPERATIONS INC., PRESENTATION OF THE MNSA 2 CLAMPS FOR WATERFORD STEAM ELECTRIC STATION, UNIT 3 (WATERFORD 3), AND ARKANSAS NUCLEAR ONE, UNIT 2 (ANO-2)
Entergy Operations Inc., the licensee for Waterford 3 and ANO-2, telephoned the staff on January 14, 2002, to indicate that they, along with manufacturers of MNSA clamps, would make a presentation on the new MNSA 2 clamps on January 31, 2002.
The original MNSA clamps, approved for use on Waterford 3 and a few other Combustion Engineering plants, provide a temporary fix if leakage from the Reactor Coolant System is observed during an outage. Use of the original MNSA clamps is restricted to certain shapes.
The manufacturers of MNSA clamps have now developed MNSA 2 clamps, which are a "new and improved version" of the original model clamps, can be used on "non-symmetrical" shapes and have additional features, such as compensation for seal shrinkage.
Docket Nos. 50-382 and 50-368 DISTRIBUTION:
Public PDIV-1 Reading File NrrRidsDlpmLpdiv1 (RGramm)
NrrRidsPMNKalyanam NrrRidsLADJohnson Accession No.: ML020170125 OFFICE PDIV-1/PM PDIV-1/LA PDIV-1/SC NAME NKalyanam DJohnson RGramm DATE 01/16/02 01/16/02 01/17/02 OFFICIAL RECORD COPY