ML020080166

From kanterella
Jump to navigation Jump to search

RPV Capsule Schedule and SE - (TAC MB2761) - ML020080166
ML020080166
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/05/2002
From: Jaffe D
NRC/NRR/DLPM/LPD4
To: Terry C
TXU Electric
References
TAC MB2761
Download: ML020080166 (7)


Text

February 5, 2002 Mr. C. Lance Terry Senior Vice President &

Principal Nuclear Officer TXU Generation Company LP Attn: Regulatory Affairs Department P. O. Box 1002 Glen Rose, TX 76043

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2: RE REQUEST TO REVISE REACTOR PRESSURE VESSEL MATERIAL SURVEILLANCE PROGRAM SCHEDULE (TAC NO. MB2761)

Dear Mr. Terry:

By letter dated August 16, 2001, TXU Electric (subsequently renamed TXU Generation Company LP, the licensee) submitted its revised reactor vessel material surveillance program withdrawal schedule for Comanche Peak Steam Electric Station (CPSES), Unit 2, which is based on the American Society for Testing and Materials (ASTM) E 185-70 recommendations.

The change requested was a delay in withdrawing the surveillance capsule (located in the reactor pressure vessel), for CPSES, Unit 2. No changes were requested for the CPSES, Unit 1, capsule withdrawal schedule. The specific change for the CPSES, Unit 2, was to change the withdrawal time for Capsule X from eight effective full power years (EFPY) to nine EFPY.

The U.S. Nuclear Regulator Commission (NRC) staff has completed its review of the licensees submittal and noted that the proposed withdrawal and testing schedule of this capsule is in accordance with the recommendations of the ASTM E 185-70 Code. The NRC staff has independently verified that the proposed withdrawal schedule for the CPSES reactor pressure vessel surveillance program capsule complies with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix H. The NRC staffs safety evaluation is enclosed.

Sincerely,

/RA/

David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page

February 5, 2002 Mr. C. Lance Terry Senior Vice President &

Principal Nuclear Officer TXU Generation Company LP Attn: Regulatory Affairs Department P. O. Box 1002 Glen Rose, TX 76043

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2: RE REQUEST TO REVISE REACTOR PRESSURE VESSEL MATERIAL SURVEILLANCE PROGRAM SCHEDULE (TAC NO. MB2761)

Dear Mr. Terry:

By letter dated August 16, 2001, TXU Electric (subsequently renamed TXU Generation Company LP, the licensee) submitted its revised reactor vessel material surveillance program withdrawal schedule for Comanche Peak Steam Electric Station (CPSES), Unit 2, which is based on the American Society for Testing and Materials (ASTM) E 185-70 recommendations.

The change requested was a delay in withdrawing the surveillance capsule (located in the reactor pressure vessel), for CPSES, Unit 2. No changes were requested for the CPSES, Unit 1, capsule withdrawal schedule. The specific change for the CPSES, Unit 2, was to change the withdrawal time for Capsule X from eight effective full power years (EFPY) to nine EFPY.

The U.S. Nuclear Regulator Commission (NRC) staff has completed its review of the licensees submittal and noted that the proposed withdrawal and testing schedule of this capsule is in accordance with the recommendations of the ASTM E 185-70 Code. The NRC staff has independently verified that the proposed withdrawal schedule for the CPSES reactor pressure vessel surveillance program capsule complies with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix H. The NRC staffs safety evaluation is enclosed.

Sincerely,

/RA/

David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446 cc: See next page DISTRIBUTION PUBLIC PDIV-1 Reading RidsOgcRp RidsAcrsAcnwMailCenter RidsNrrDlpmLpdiv1 (RGramm) RidsNrrPMDJaffe RidsNrrLADJohnson RidsRgn4MailCenter (KBrockman)

EAndruszkiewicz ACCESSION NO.: ML020080166 OFFICE PDIV-1/PM PDIV-1/LA OGC PDIV-1/SC NAME DJaffe DJohnson DCummings RGramm DATE 01/15/02 01/15/02 01/24/029 02/05/02 OFFICIAL RECORD COPY

Comanche Peak Steam Electric Station cc:

Senior Resident Inspector Jim Calloway U.S. Nuclear Regulatory Commission Public Utility Commission of Texas P. O. Box 2159 Electric Industry Analysis Glen Rose, TX 76403-2159 P. O. Box 13326 Austin, TX 78711-3326 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 Mr. Roger D. Walker Regulatory Affairs Manager TXU Generation Company LP P. O. Box 1002 Glen Rose, TX 76043 George L. Edgar, Esq.

Morgan, Lewis & Bockius 1800 M Street, N.W.

Washington, DC 20036-5869 Honorable Dale McPherson County Judge P. O. Box 851 Glen Rose, TX 76043 Office of the Governor ATTN: John Howard, Director Environmental and Natural Resources Policy P. O. Box 12428 Austin, TX 78711 Arthur C. Tate, Director Division of Compliance & Inspection Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 January 2002

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REQUEST TO REVISE THE REACTOR PRESSURE VESSEL MATERIAL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE FACILITY OPERATING LICENSE NPF-89 TXU GENERATION COMPANY LP COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 DOCKET NO. 50-446

1.0 INTRODUCTION

By letter dated August 16, 2001, TXU Electric (subsequently renamed TXU Generation Company LP, the licensee) submitted its revised reactor pressure vessel (RPV) material surveillance program withdrawal schedule for Comanche Peak Steam Electric Station (CPSES),

Unit 2, which is based on the American Society for Testing and Materials (ASTM) E 185-70 recommendations. The change requested was a delay in withdrawing the surveillance capsule (located in the RPV), for CPSES, Unit 2. No changes were requested for the CPSES, Unit 1, capsule withdrawal schedule. The specific change for the CPSES, Unit 2, was to change the withdrawal time for Capsule X from eight effective full power years (EFPY) to nine EFPY.

2.0 BACKGROUND

Appendix H of Title 10 of the Code of Federal Regulations (10 CFR) Part 50 requires a material surveillance program to monitor changes in the fracture toughness properties of ferritic materials in the RPV beltline region which result from exposure of these materials to neutron irradiation and the thermal environment. Under this program, fracture toughness test data is obtained and analyzed from material specimens exposed in surveillance capsules which are withdrawn periodically from the RPV. Test results must be reported to the U. S. Nuclear Regulatory Commission (NRC) within one year of the date of capsule withdrawal. Also,Section III.B.3 of Appendix H of 10 CFR Part 50 requires the capsule withdrawal schedule to be approved by the NRC prior to implementation.

The design of the surveillance program and the withdrawal schedule must meet the requirements of the edition of ASTM E 185 that is current on the issue date of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code) to which the RPV was purchased. The RPV surveillance programs for the CPSES units were initially established in accordance with ASTM E 185-70. This edition of the ASTM standard was in effect on the issue date of Section III of the ASME Code (1971) to which the CPSES, Units 1 and 2, RPVs were fabricated.

The surveillance capsule withdrawal schedule and testing criteria for ASTM E 185-70 recommends that sets of specimens be withdrawn at three or more separate times. It specifically recommends that one of the data points obtained shall correspond to the neutron exposure of the RPV at no greater than 30 percent of its design life. There is no specific requirement for when the data point shall be obtained for the second capsule; the third data point obtained shall correspond to the neutron exposure of the RPV near the end of its design life.

3.0 EVALUATION Prior to initial licensing of CPSES, the licensee and Westinghouse Electric Company developed an overall plan for the withdrawal and analysis of the RPV material surveillance capsule at CPSES. The first surveillance capsules for Units 1 and 2 (Capsule U) were withdrawn and post-irradiation embrittlement tests were performed. Results from the embrittlement tests and capsule dosimeters suggested that RPV beltline material Adjusted Reference Temperature -

Nil-ductility Temperature (ARTNDT) values would remain below 100 EF at end-of license (EOL) neutron exposure, and the limiting material in both the units would not be highly susceptible to irradiation damage. Results from evaluation of the second capsule removed from Unit 1 (Capsule Y) confirmed these findings.

In light of the favorable embrittlement test results obtained from the analysis of the withdrawn capsules, the licensee requested the NRC to allow revising the original capsule withdrawal schedule for CPSES, Units 1 and 2, and to remove only three capsules over the life of each RPV. The request was granted by the NRC by letter dated August 9, 2000. The revised capsule withdrawal schedule is shown in the Pressure and Temperature Limits Report (PTLR) for the respective CPSES units. The revised withdrawal schedule did not impact the pressure and temperature limit curves located in the PTLRs. These limit curves satisfy the requirements of 10 CFR Part 50, Appendix G, and remain applicable up to 16 EFPY for both CPSES units.

The first capsules (both designated Capsule U) for both CPSES units were withdrawn at 0.9 EFPY, thus satisfying the ASTM E 185-70 recommendation to obtain one data point corresponding to the neutron exposure of the RPV at no greater than 30% of its design life.

The capsule neutron fluence for CPSES, Unit 1, was 3.70 x 1018 neutrons per centimeter squared (n/cm2), and the capsule neutron fluence for CPSES, Unit 2, was 3.28 x 1018 n/cm2.

The second capsule for Unit 1 (Capsule Y) was withdrawn at 6.25 EFPY, and that for Unit 2 (Capsule X) is scheduled for withdrawal at 8 EFPY. This schedule would meet the ASTM E 185-70 recommendation for the second capsule to be withdrawn and tested (note that ASTM E 185-70 does not outline any specific requirement for when the data point shall be obtained for the second capsule). The third capsules for Unit 1 (Capsule X) and Unit 2 (Capsule W) are scheduled to be withdrawn and tested at 13 EFPY and 14 EFPY, respectively. The recommendation of ASTM E 185-70 for the third capsule is that the third data point obtained shall correspond to the neutron exposure of the RPV near the end of its design life.

Accumulated radiation damage is reflected as an upward shift in the ARTNDT. Under the rules of 10 CFR 50.61, the pressurized thermal shock (PTS) screening criteria for plate material, reference temperature (RTPTS) is 270 EF at EOL. Before vessel-specific data was available, ARTNDTs were forecast using the methodology of 10 CFR 50.61 and Regulatory Guide 1.99, Revision 2. In 1992, the EOL RTPTS for the Unit 1 vessel was forecast to be 100 EF; three years later the EOL RTPTS for the Unit 2 vessel was forecast to be 94 EF. The corresponding shifts in reference temperature (RTPTS) were forecast to be 66 EF for the Unit 1 vessel and 50 EF for

the Unit 2 vessel. The forecast RTPTS show both the CPSES Unit 1 and Unit 2 RPVs have very substantial margins against PTS (based on the 270 EF screening criteria), which translates into substantial fracture toughness margins.

Analysis of material in surveillance capsules adds assurance that the forecast RTPTS are an "upper-bound" for the vessel-specific reference temperatures. Changes in the CPSES fuel management strategies and core designs have tended to lower the neutron exposure in the RPV beltline region. Results from the surveillance capsule dosimetry show the rate at which fluence is accumulating in the RPV beltline region is at or possibly below initial projections.

With the implementation of 18-month fuel cycles and shorter refueling outages, the capacity factor at CPSES has increased to approximately 93%. This increased capacity factor is considerably higher than the 80% capacity factor utilized in determining the present capsule withdrawal schedule for CPSES. The capacity factor of 93% for the CPSES units places EOL at 37.2 EFPY, based on the current plant license of 40 years (40 years x 0.93). With the present capsule withdrawal schedule for CPSES, Unit 2, the post-irradiation tests of Capsule X (scheduled for withdrawal at 8 EFPY) will provide embrittlement and dosimetry results that would be projected to 32.8 EFPY [8 EFPY x Capsule X Lead Factor (4.10)]. The heatup and cooldown curves in the current PTLR are intended to be replaced at 16 EFPY, and replacement curves would be needed for both units before the end of this period. In order to cover the current estimated EOL of about 37 EFPY, a delay in the withdrawal of the second Unit 2 surveillance capsule until 9.1 EFPY is proposed. This delay in the withdrawal will allow the licensee to use RPV specimens that have been exposed to a more representative fluence to generate replacement cooldown and heatup curves.

The scheduled withdrawal of the third capsules from Units 1 and 2 at 13 EFPY and 14 EFPY, respectively, will provide the necessary data needed to generate heatup and cooldown curves beyond 37 EFPY, in the event a plant life extension is pursued for CPSES in the future. In addition, there are three standby capsules in the RPV of each unit that could be used to supplement the scheduled capsule withdrawals, if necessary.

The NRC staff independently verified that the proposed capsule withdrawal and testing schedule for the capsules of the CPSES, Unit 2, RPV surveillance program are in accordance with the recommendations of ASTM E 185-70. The NRC staff has independently verified that the proposed withdrawal schedule for the capsules for the CPSES, Unit 2, RPV surveillance program complies with the requirements of 10 CFR Part 50, Appendix H.

4.0 CONCLUSION

Based on the NRC staffs review of the licensee's August 16, 2001, submittal, the NRC staff found that the revised withdrawal schedule for the CPSES, Unit 2, RPV material surveillance program capsule satisfies the requirements of Appendix H to 10 CFR Part 50 and is, therefore, acceptable.

Principal Contributor: E. Andruszkiewicz Date: February 5, 2002