October 18, 2001 Mr. Alexander Marion, Director Engineering Nuclear Energy Institute 1776 I Street, NW Suite 400 Washington, DC 20006-3708
Dear Mr. Marion:
As stated previously in our letter of August 13, 2001, the staff of the Mechanical and Civil Engineering Branch has completed an acceptance review of the Seismic Experience-based Qualification Owners Group (SEQUAL) topical report, Basis for Adoption of Experience-Based Seismic Equipment Qualification (EBSEQ) Methodology by Non-A46 Nuclear Power Plants, Revision (0), dated April 17, 2001. The EBSEQ method is proposed to be used for the qualification of equipment in nuclear power plants that are not included in the scope of Unresolved Safety Issue (USI) A-46. In the acceptance review, the staff identified eight areas of concern, seven of which were initially described in a letter from Brian W. Sheron (NRC) to Gregory Ferguson (SEQUAL), dated August 24, 2000. In meetings and phone calls subsequent to our August 13, 2001 acceptance review letter, the NRC staff and SEQUAL representatives have attempted to reach a general consensus on some of these initial concerns.
The staff will now begin a formal review of the topical report together with the recent responses provided by SEQUAL to the staff about our preliminary findings identified in the acceptance review. Attached to this letter is a schedule that contains target dates for the formal review process.
Please contact me (301-415-2832), if you have any questions.
/RA/ Signed by P. Wen Peter Wen, Project Manager Risk Informed Initiatives, Environmental, Decommissioning, and Rulemaking Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No.:
689
Attachment:
As stated
Nuclear Energy Institute Project No. 689 cc:
Mr. Ralph Beedle Senior Vice President and Chief Nuclear Officer Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Alex Marion, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. John Butler, Project Manager Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Gregory Ferguson, Chairman Seismic Experience-Based Qualification Owners Group Waterford 3 SES 17265 River Road Kilona, LA 70066
October 18, 2001 Mr. Alexander Marion, Director Engineering Nuclear Energy Institute 1776 I Street, NW Suite 400 Washington, DC 20006-3708
Dear Mr. Marion:
As stated previously in our letter of August 13, 2001, the staff of the Mechanical and Civil Engineering Branch has completed an acceptance review of the Seismic Experience-based Qualification Owners Group (SEQUAL) topical report, Basis for Adoption of Experience-Based Seismic Equipment Qualification (EBSEQ) Methodology by Non-A46 Nuclear Power Plants, Revision (0), dated April 17, 2001. The EBSEQ method is proposed to be used for the qualification of equipment in nuclear power plants that are not included in the scope of Unresolved Safety Issue (USI) A-46. In the acceptance review, the staff identified eight areas of concern, seven of which were initially described in a letter from Brian W. Sheron (NRC) to Gregory Ferguson (SEQUAL), dated August 24, 2000. In meetings and phone calls subsequent to our August 13, 2001 acceptance review letter, the NRC staff and SEQUAL representatives have attempted to reach a general consensus on some of these initial concerns.
The staff will now begin a formal review of the topical report together with the recent responses provided by SEQUAL to the staff about our preliminary findings identified in the acceptance review. Attached to this letter is a schedule that contains target dates for the formal review process.
Please contact me (301-415-2832), if you have any questions.
/RA/ Signed by P. Wen Peter Wen, Project Manager Risk Informed Initiatives, Environmental, Decommissioning, and Rulemaking Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No.:
689 Accession No.: ML012910044
Attachment:
As stated Template NRR-106 Distribution:
ADAMS-PUBLIC RGEB R/F Dmatthews/FGillespie CCarpenter S West JStrosnider/FEltawila PT Kuo KManoly CMunson Document Name: G:\\RGEB\\PCW\\SEQUAL-L.WPD
- see previous concurrence sheet*
OFFICE REGB:DRIP EMEB:DE REBG:DRIP EMEB:DE EMEB:DE Dir:DE NAME PWen CMunson*
SWest KManoly*
PTKuo*
JStrosnider*
DATE 10/17/01 10/11/01 10/18 /01 10/15/ 01 10/15/01 10/17/01 OFFICIAL OFFICE COPY
ATTACHMENT REVIEW SCHEDULE FOR SEQUAL TOPICAL REPORT, BASIS FOR ADOPTION OF EXPERIENCE-BASED SEISMIC EQUIPMENT QUALIFICATION (EBSEQ) METHODOLOGY BY NON-A46 NUCLEAR POWER PLANTS.
TASK DATE STATUS Staff acceptance review of topical report 04/01 to 08/01 Complete Staff and SEQUAL discussion of acceptance review 08/01 to 10/01 Complete Staff review of topical report 10/01 to 10/02 Staff Requests for Additional Information (RAIs) 01/02 SEQUAL Response to RAIs 03/02 Staff review of RAI responses 05/02 Staff preparation of draft safety evaluation 7/02 Staff issues final safety evaluation 10/02