ML011150055

From kanterella
Jump to navigation Jump to search
Issues to Be Addressed in a Generic Justification for Continued Operation of Pwrs
ML011150055
Person / Time
Site: Nuclear Energy Institute
Issue date: 04/17/2001
From: Sheron B
NRC/NRR/ADPT
To: Marion A
Nuclear Energy Institute
References
Download: ML011150055 (3)


Text

April 17, 2001 Mr. Alex Marion, Director Engineering Nuclear Energy Institute 1776 I Street, N.W., Suite 400 Washington, D.C. 20006-3708

SUBJECT:

ISSUES TO BE ADDRESSED IN A GENERIC JUSTIFICATION FOR CONTINUED OPERATION OF PWRS

Dear Mr. Marion:

The NRC staff met with the EPRI Materials Reliability Program (MRP) on Thursday, April 12, 2001, to discuss the generic implications of circumferential cracking found on the pressurized water reactor (PWR) upper head control rod drive mechanism (CRDM) penetrations at the Oconee Nuclear Station, Unit 3. The staff had requested, by letter dated April 5, 2001, that the MRP include in this presentation, among other items, a discussion of proposed industry actions to address the generic aspects of the CRDM nozzle circumferential cracking issue.

During this meeting, the staff raised several concerns (e.g., need for expanded inspections for plants presently in refueling or maintenance outages, industry assessment of risk involved in not immediately inspecting, and others to be detailed in the staffs meeting summary) regarding the initiation and growth of significant circumferential cracks in PWR Alloy 600 weldments, apparently at growth rates that are faster than previously modeled. The staff requested that the MRP address the questions raised both in the staffs letter dated April 5, 2001, and during the April 12, 2001, public meeting, in its preliminary safety assessment of the generic implications of this cracking issue. The MRP stated that this assessment will be submitted to the staff by April 27, 2001.

The staff is primarily concerned with those plants that have either never inspected or have not recently inspected their CRDM penetrations. In order to ensure that the staffs concerns related to this potentially significant safety concern are addressed, we request that the MRPs assessment answer the following questions related to a generic justification for continued operation (JCO) for PWRs. If you can not provide responses to these questions by April 27, 2001, we request that you immediately notify the staff of the date by which you can provide responses.

Mr. Alex Marion

- 2 of 3 -

1. The MRP stated during the April 12, 2001, meeting that they are conducting a survey of the PWR plants to determine the scope and extent, to date, of the under-insulation visual inspections used by PWR licensees to detect boron deposits on the upper reactor pressure vessel (RPV) head. The preliminary results presented indicate that licensees of CE and Westinghouse PWR-designed plants may not be capable of performing comprehensive VT-2 leakage examinations of the upper vessel heads without having to remove the existing vessel head insulation materials. Based on this, provide a technical justification, supported by appropriate deterministic and/or risk-informed assessments, as to why it is safe, for each of the various PWR vessel designs, to continue to operate, or for those in or entering outages to restart, until such time that appropriate inspections of all of the RPV upper head penetrations have been performed. This discussion should include, but not be limited to:
a. description of inspections of the upper RPV head penetrations that have been performed to date, and their applicability to plants that have not yet inspected;
b. an assessment of the probability for circumferential flaw(s) to exist in the upper RPV head penetrations, with lengths and depths, on the order of or greater than that found at Oconee for those plants that have not yet performed comprehensive leakage examinations of all of the upper RPV head penetrations; c.

means utilized to detect and characterize through-wall cracks in the upper RPV head penetrations;

d. MRP recommendations regarding any expanded operator actions/training on beyond design basis accident (DBA) scenarios involving rod ejection(s), small-, medium-and large-break loss of coolant accidents (LOCA), rod insertion failure(s), etc.; and,
e. MRP recommendations regarding increased operator actions during periods of highest rod worth (e.g., Startup, Cool-down and Hot Standby periods).
2. Postulated crack growth rates (CGR) were discussed during the April 12, 2001, meeting.

Based on the staffs comments regarding the likelihood for an exceptionally aggressive operating environment in the CRDM housing annulus, where potentially highly concentrated borated primary water could become oxygenated, discuss the acceptability of your CGR model, and conditions under which the model was developed consistent with the conditions to which it is being applied. Include a technical basis for this CGR, including postulated times it will take to initiate and grow a through-wall crack, and the environmental factors (e.g., temperature, boron concentrations, oxygen levels, etc.) that will effect this CGR.

Based on this proposed CGR, identify the frequency and scope of inspections that would be necessary to detect a circumferential flaw before it could exceed the critical size for failure of the CRDM penetration.

Mr. Alex Marion

- 3 of 3 -

If you have any question regarding this letter, please contact Mr. Jack Strosnider of my staff at 301-415-3298.

Sincerely,

/ra/

Brian W. Sheron, Associate Director For Project Licensing and Technical Analysis Office of Nuclear Reactor Regulation Project No. 689 cc:

See next page

Mr. Alex Marion

- 3 of 3 -

If you have any question regarding this letter, please contact Mr. Jack Strosnider of my staff at 301-415-3298.

Sincerely, Brian W. Sheron, Associate Director For Project Licensing and Technical Analysis Office of Nuclear Reactor Regulation Project No. 689 cc:

See next page Distribution:

File Center EMCB R/F PUBLIC ACRS WDTravers WFKane SJCollins JRJohnson JAZwolinski GMHolahan DBMatthews BABoger MEMayfield NCChokshi WDBecker LBMarsh WDLanning, R1 CCasto, R2 JGrobe, R3 AHowell, R4 Document Name: C:\\MRP JCO Qs.wpd INDICATE IN BOX: C=COPY W/O ATTACHMENT/ENCLOSURE, E=COPY W/ATT/ENCL, N=NO COPY EMCB:DE E

EMCB:BC E

REXB:BC E

DE:D E

NRR:ADPT E

CECarpenter:cec WHBateman:

LBMarsh:lbm JRStrosnider:jrs BWSheron:bws 04/17/2001 04/

/2001 04/17/2001 04/17/2001 04/17/2001 OFFICIAL RECORD COPY

Nuclear Energy Institute Project No. 689 cc:

Mr. Ralph Beedle Senior Vice President and Chief Nuclear Officer Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Ms. Lynnette Hendricks, Director Plant Support Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Jim Davis, Director Operations Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Charles B. Brinkman, Director Washington Operations ABB-Combustion Engineering, Inc.

12300 Twinbrook Parkway, Suite 330 Rockville, Maryland 20852 Mr. David Modeen, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. H. A. Sepp, Manager Regulatory and Licensing Engineering Westinghouse Electric Company P.O. Box 355 Pittsburgh, Pennsylvania 15230-0355 Mr. Anthony Pietrangelo, Director Risk & Performance Based Regulation Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Larry Mathews, MRP Southern Nuclear Operating Company Manager, Inspection and Testing Services P. O. Box 1295 Birmingham, AL 35201 Vaughn Wagoner, Technical Chair Assessment Committee Carolina Power & Light Company One Hannover Square 9C1 P.O. Box 1551 Raleigh, NC 27612 Avtar Singh, EPRI MRP Manager Electric Power Research Institute P. O. Box 10412 3412 Hillview Ave.

Palo Alto, CA 94303 C. Thomas Alley, Jr., Technical Chair Inspection Task Duke Power Company Nuclear General Office 526 South Church Street Mail Code EC09O PO Box 1006 Charlotte NC 28201 Mr. Allan McIlree, EPRI Assessment Manager Electric Power Research Institute P. O. Box 10412 3412 Hillview Ave Palo Alto, CA 94304 Gary D. Moffatt, Technical Chair Repair/Mitigation Task V. C. Summer Nuclear Station P. O. Box 88 Jenkinsville, SC 29065 Frank Ammirato, EPRI Inspection Manager EPRI NDE Center P. O. Box 217097 1300 W. T. Harris Blvd.

Charlotte, NC 28221